Title: GUJARAT ENERGY TRANSMISSION CORPORATION LIMITED
1- GUJARAT ENERGY TRANSMISSION CORPORATION LIMITED
- Grid related issues in case of Wind/Solar
- based Generation in Gujarat
- 07th February, 2009
- S. K. Negi
- Managing Director
2Power Scenario in Gujarat as on 31.12.2008
- Present power generating capacity including State
sector, Private sector Share from Central
sector 10417 MW.
- 56 is generated from South Gujarat.
- 37 is generated from Central Gujarat.
- 7 is generated from Saurashtra and Kutch area.
- Out of total 10417 MW installed capacity, 63 is
from thermal, 23 is from Gas, 7 from hydro and
7 from nuclear sources.
3Future Power Scenario in Gujarat
- 52 is generated from South Gujarat.
- 31 is generated from Central Gujarat.
- 27 is generated from Saurashtra and Kutch area.
- 4000 MW Mundra, UMPP is also located at Mundra in
Dist Kutch.
- Out of total 19934 MW installed capacity, 67 is
from thermal, 26 is from Gas, 4 from hydro and
3 from nuclear sources.
4Power Scenario in Kutch and Saurashtra
- Present installed capacity of Saurashtra and
Kutch is as under - KLTPS, Panandhro, Kutch - 215 MW
- GMDC, Akrimota, Kutch - 250 MW
- GSECL, Sikka, Saurashtra - 240 MW
- Total. - 705 MW
- Proposed anticipated capacity addition in
Saurashtra and Kutch during 11th five year plan
and subsequent years - KLTPS, Panandhro, Kutch (Unit-IV) - 75 MW
- Adani Power, Mundra, Kutch - 2640 MW
- UMPP, Mundra, Kutch - 4000 MW
- GSECL, Sikka Extension, Saurashtra - 500 MW
- Essar Power, Vadinar, Saurashtra - 1200 MW
- GPPC, Pipavav, Saurashtra - 700 MW
- BECL, Bhavnagar, Saurashtra - 600 MW
- Total. - 9715 MW
- In addition to this, in Western Gujarat itself
the approved proposals for integration of Wind
power are around 3600 MW. -
5Power Scenario in Kutch and Saurashtra
- The pending proposals for integration of Wind
power are around 4000-4500 MW. - Also, a proposal for establishing concentrated
solar thermal power project to the tune of 8000
MW in Kutch is in the conceptual stage. - To summarise West Gujarat generation more than
25000 MW of which - around 10500 MW will be from conventional
sources and - more than 14500 MW from renewable energy sources.
- West Gujarat alone cannot absorb this huge
quantum of power or it can be rather said that
the load of entire State may not reach this
level. - As per 17th Electric Power Survey, published by
Central Electricity Authority, New Delhi,
projected load of Gujarat State is 14374 MW by
March-2012. -
6Amendment in Wind Farm Policy 2007
- The Government of Gujarat through GR No WND
1120082321B dated 7th January 2009, has made
amendments in the Wind Power Policy 2007
notified earlier through GR No EDA-102001-3054-B
dated 13th June 2007 . - Wheeling of power to consumption site at 66 KV
voltage level and above- - The wheeling of electricity generated from the
Wind Turbine Generators (WTGs), to the desired
location(s) within the State, shall be allowed on
payment of transmission charges, and transmission
losses otherwise applicable to normal Open Access
Customer. - Wheeling of power to consumption site below 66
KV voltage level. - The wheeling of electricity generated from the
WTGs, to the desired location(s) within the
State, shall be allowed on payment of
transmission charges, otherwise applicable to
normal Open Access Consumer, and transmission and
wheeling losses _at_ 10 of the energy fed to the
grid. - The wheeling of electricity generated by smaller
investors, having only one WTG in the State, to
the desired location(s), shall be allowed on
payment of transmission charges, otherwise
applicable to normal open access consumer, and
transmission and wheeling losses _at_7 of the
energy fed to the grid. - Wind farm owner desiring to wheel electricity to
more than two locations shall pay 5 paise per
unit on energy fed in the grid to concerned
Distribution Company in whose area, power is
consumed in addition to above mentioned
transmission charges and losses, as applicable - The electricity generated from the WTGs
commissioned from 1st April, 2009, may be sold to
GUVNL and/or any Distribution Licensee within the
state, at a rate of Rs. 3.50 per unit of
electricity for the entire period of PPA . - GUVNL and / or any Distribution licensee may
purchase surplus power from WTGs wheeling power
for their captive use after adjustment of energy
against consumption at recipient unit (s) at a
rate of 85 of tariff applicable to WTGs
(commissioned in same tariff block) selling power
to GUVNL and /or any Distribution licensee. - GETCO is required to erect evacuation facilities
beyond 100 kms between Wind Farm sub-station to
GETCO sub-station - As per the amended Wind Power Policy -2007, GETCO
is required to collect Bank Guarantee _at_ Rs. 5
lacs per MW based on allotment of transmission
capacity and in case the Developer fails to
achieve Commercial Operation within the one year
period in case of installed capacity up to 100
MW, two years in case of installed capacity from
201 MW to 400 MW and three years in case of
installed capacity from 401 MW to 600 MW, the
Bank Guarantee shall be forfeited by GETCO.
7Summary of Wind farms in Gujarat
8Existing Wind farms in Gujarat
9Proposed Wind farms in Gujarat
(Approved and work under progress)
10Contd- Proposed Wind farms in Gujarat
11Proposed Wind farms in Gujarat
Not approved wind farm projects)
12Contd- Proposed Wind farms in Gujarat
13Wind Energy
- Growing concern for the environmental
degradation has led to the worlds interest in
renewable energy resources. Wind is commercially
and operationally the most viable renewable
energy resource and accordingly, emerging as one
of the largest source in terms of the renewable
energy sector. -
- Wind is the natural movement of air across the
land or sea. Wind is caused by uneven heating and
cooling of the earths surface and by the earths
rotation. Land and water areas absorb and release
different amount of heat received from the sun.
As warm air rises, cooler air rushes in to take
its place, causing local winds. The rotation of
the earth changes the direction of the flow of
air. - This type of energy harnesses the power of the
wind to propel the blades of wind turbines. These
turbines cause the rotation of magnets, which
creates electricity.
14Wind Energy
-
- Wind Energy as a source of electricity has
following advantages - Wind power produces no water or air pollution
that can contaminate the environment, - Power from the wind does not contribute to
global warming because it does not generate
greenhouse gases, - Wind generation is a renewable source of energy,
which means that we will never run out of it.
Fuel source is free, abundant and inexhaustible, - Extremely low operating cost,
- Less commissioning period,
- Creates employment, regional growth and
innovation, - Reduces poverty through improved energy access,
- It is very good as a fuel saver.
15Wind Energy
- At the same time, wind has some peculiar
characteristics - Wind is unpredictable therefore, wind power is
not predictably available. When the wind speed
decreases less electricity is generated. This
makes wind power unsuitable for base load
generation. - Limited control or no control on generation.
- Drastic variation in generation due to variation
in wind speed. - (As shown in the graph).
- Electricity produced by wind power sometimes
fluctuates in voltage and power factor, which can
cause difficulties in linking its power to a
utility system. - Because winds do not blow strongly enough to
produce power all the time, energy from wind
machines is considered intermittent, that is,
it comes and goes. Thus, the average plant load
factor of wind generators is very low to the tune
of 15-20. Therefore, utility companies can use
it for only part of their total energy needs.
16Wind Energy
- The maximum wind generation is available during
monsoon / off-peak period of the year when the
total system demand crashes by about 40-50 and
it becomes very difficult for the load dispatcher
to handle the system effectively. In other words,
it can be said that the wind energy is available
in abundance when not needed and not available
when needed most. - Wind energy being green power and excessively
available in monsoon, the load dispatcher is
compelled to back down even the cheaper, firm and
reliable power from thermal and hydro power
stations. - Depends upon wind velocity.
- Geographical locations , potential of wind.
- Limited potential area.
- Proximity to the load centre.
- In Gujarat, Kutch Saurashtra are identified has
a good potential of wind energy.
17Wind Farm Generation for year 2007-08
18Wind Farm Generation for the year 2008-09
19Wind energy variation graph
20Wind energy variation graph
21Wind Generation on 19-11-08
22WIND FARM GENERATION OF 19-11-08 V/S FREQ
23ENERGY FOR 2007
24ENERGY FOR 2008
25(No Transcript)
26(No Transcript)
27(No Transcript)
28(No Transcript)
29(No Transcript)
30(No Transcript)
31Integration with grid
- There are number of unresolved technical,
institutional and regulatory - questions concerning distributed generation in
general and wind - generation in particular.
- On the technical level, major barriers are..
- Novelty and unfamiliarity of distributed
technologies. - Lack of substantial field experience with these
technologies. - Costs and complexity associated with thorough
engineering evaluations. - Weak evacuations network as well as onward
transmission networks. - Less availability of evacuations corridors.
- Less consumptions in local area due to wide
variation in load due to variable load in
agriculture, less and variable industrial demand
and low demand on staggering day. - Variable local load pattern leads to overloading
of transformers and main transmission lines which
requires high capacity of strengthening of
transmission network. - Average PLF observed 15-20 which leads to
inefficient occupation of transformer capacity
and non utilization of infrastructures.
32Electrical grid
- Electrical power grid is an unique one in which
generation and demands are balanced
instantaneously and continuously. - Fluctuations in power consumed by the consumers
and variations in uncontrolled generators are
compensated by the controlled generators. - When generation equal to load, frequency operates
at 50 Hz. Variation in frequency indicates rise
of load or generation vice versa is term as a
balancing. - In the grid system, it is not necessary for
compensating each and every variation from
individual consumers / generators. - Only aggregate variation in the control area is
balanced. - Aggregation is the powerful tools with the power
system operators. - When wind power plants are introduced into the
power system, an additional source of variation
is added to the already variable nature of
system. -
33Load-Generation balance
- In large interconnected system, load generation
is reflected with change in tie line flows. - In a small system, load generation balance is
reflected with variation in frequency. - Variation in frequency is limiting factor for
capacity addition of the wind farms. - In predominantly hydro and gas generation system
with good ramp rate will be positive factor,
helping for compensating variation of wind
generation. -
34Balancing
- Balancing in power system occurs over wide time
frames - Years in advance Enough generation has to be
planned and built so that there is sufficient
capacity available to meet load requirements - Day Ahead Select which available generator can
reliably meet expected requirements at lowest
cost. - Real Time Real time balancing can be obtained
by two different methodology - Load Following (Backing down)
- Load Regulation (Load Shedding)
35Balancing by Load Following
- Load following requirement are highly correlated
. - 24 hours power supply to rural under JGY scheme.
- 24 hours power supply to urban area.
- 8 hours committed agriculture supply in various
groups. - High demand during summer due to domestic
commercial cooling load. - High demand agriculture demand during Ravi crop.
- Demand variation due to festival seasons.
- Load demand during morning evening peak.
36Balancing by Load Regulations
- Load Regulation requirement are correlated by.
- Availability of generation on bar.
- Ramping rate of generating stations.
- Variable cost of generating stations.
- Technical Minimum of generating stations.
- Peak and off peak demand, required generation to
be kept in reserve. - The random variation in demand OR generation is
adjusted instantaneously by primary response
generators. -
37Grid operation with Wind Generation
- Scenario 1
- An increase in load along with increase in wind
generation OR drop in load along with drop of
wind generation Additional generation required
for frequency maintenance is less. - System Operator
-
- It is a safe operation for grid operators.
- Most favorable condition for grid operators.
- During evening peak, maximum wind energy
available and it helps to meet peak demand. -
38Grid operation with Wind Generation
- Scenario 2(A)
- A drop in load along with increase in wind
generation. - System Operator
- Backing down of other generators.
- High Voltage problem and switching off lines.
System operation with critical loading. - If local load is very low, overloading of
associated transmission lines.
39GETCO grid operation with Wind Generation
- Scenario 2(A)
- A drop in load along with increase in wind
generation . - System Operator
-
- When load is very low and wind generation is
maximum, system operator has to back down cheaper
generation at Panandhro and Akrimota to control
loading of 220 KV Sivlakha-Morbi line. - In case of contingency of tripping of either
Morbi-Sivlakha OR Anjar-Deodar OR
Sivlakha-Sankhari lines, total generation at
Panadhro and Akrimota affected badly. - In Kutch area, due to high wind energy
generation, voltage remains high causing frequent
failure of lines disturbing parameters while
synchronizing, delaying in synchronization.
40Grid operation with Wind Generation
- Scenario 2(B)
- An increase in load along with drop in wind
generation . - System Operator
- Increasing load along with decrease in wind
generation is a very critical nature of situation
for system operator. - Additional generation is to be brought into
system very quickly. - If no generation available, heavy load shading
to be resorted. - If frequency permits, overdrawl at that
prevailing rate. - Requisition of costly generation i.e. on SPOT gas
, Naphtha if available - Remedies
- Additional generation capacity is required for
maintenance of load generation balancing
especially gas based and hydro based.
41Power Quality with Wind Generation
- Generally it is believed that with increase in
wind generation, the power quality suffers. - Main power quality problems are
- Voltage Regulation,
- Harmonics.
- Old WTG machines with induction generators have
not been required to participate in system
voltage regulation. Their reactive power demand
are compensated by switched shunt capacitors. - New WTG machines with variable frequency drives
have inherent control of reactive power output
and can participate in voltage regulation. - If wind farm is far from generation source, high
voltage witnessed near to wind farms with
increase in wind generation. - The variable frequency generators in WTGs use
AC-DC converter for connection with Grid, which
increases the Harmonics level in the system.
42Wind Penetration
- Energy penetration is the ratio of the amount of
energy delivered from the wind generation to the
total energy delivered. For example, if 200
megawatthours (MWh) of wind energy is supplied
and 1,000 MWh is consumed during the same period,
winds energy penetration is 20. - Capacity Penetration is the ratio of the
nameplate rating of the wind plant capacity to
the peak load. For example, if a 300-MW wind
plant is operating in a zone with a 1,000-MW peak
load, the capacity penetration is 30 . The
capacity penetration is related to the energy
penetration by the ratio of the system load
factor to the wind plant capacity factor. Say
that the system load factor is 60 and the wind
plant capacity factor is 40. In this case, and
with an energy penetration of 20, the capacity
penetration would be 20 x 0.6/0.4, or 30. - Instantaneous penetration is the ratio of wind
plant output to load at a specific point in time,
or over a short period of time.
43Conclusion
- If the share of wind generation instantaneous
penetration at any point of time is excessively
high compared to the total system demand, then,
following new operating methodology need to be
adopted for ensuing reliability and stability of
system - Methodology for accurate long term short term
forecasting. - Real time data from wind farm to system operator
to be made available for effective grid
operation. - Reserve capacity with high ramp up generators
such as a hydro and gas shall be kept. - All wind energy generation be brought under
regulations of ABT which means elimination of
generation in case of high frequency or system
constraints. - Reinforcement of main transmission network and
power corridors. - Augmentation and reinforcement of voltage
regulating equipments such as reactors, switched
capacitors including FACTS devices.
44Thank you