Title: ECN WeSea: Offshore wind energy activities in North Netherlands
1ECN / We_at_Sea Offshore wind energy activities
in North Netherlands
Chris Westra General manager We_at_Sea(senior
consultant ECN )
Berlin 2007
2(No Transcript)
3Locations of offshore wind farms
4Harlingen
Den Helder
ECN / WMC
ECN
ECN / Test field
Lely 4 x NedWind
Egmond / Zee
Q7
IJmuiden
5Wind farm Lely 4 x 0,5 MW
1994
6Dutch offshore projects
OWEZ 108 MW, October 2006
Q7 120 MW,2008
7Offshore project OWEZ
- Shell-NUON
- 36 x Vestas 3MW V90 ? 108 MW
- 10 18 km from the coast
- 18 m water depth
- Monopiles 70 m above sea level,30 m into seabed
- total investment appr. M 260
- Status in operation
8Dutch offshore project OWEZ
9Egmond / zee
10Egmond aan zee
11Dutch offshore project OWEZ
Photographs Chris Westra, Jaap t Hooft, Jos
Beurskens
12Egmond aan Zee in operation
13Egmond aan zee 36 x 3 MW
14The Dutch offshore project Q7
- E-Connection ? Evelop
- 60 Vestas 2 MW V80 ? 120 MW
- 23 km from coast
- 19 - 24 m water depth
- mono piles
- total investment appr. M 380
- Status under construction
15Q7 wind farm
Picture from IRO seminar or Presentation Korean
visit
Mammoet van Oord -Jumping jack
16Picture from Module 9.ppt
IJmuiden
17The Dutch wind farm Q7 under construction
18Q7 wind farm
19Involved companies
- Ballast Nedam
- Mammoet van Oord
- Shell, Nuon, Eneco
- Rabobank, Fortis
- Vestas (offshore, maintenance)
- A2Sea
- Oceanteam (cable works)
- Windcat workboats
- Various local companies
20NL Offshore Wind energy
21(No Transcript)
22State of the art NL
- Small wind turbine manufactures
- Excellent production facilities offshore
constructions (I.e. monopiles) - Strong RD position
- Strong offshore industry and project development
- A lot of activities (rotor design, mechanical
engineering, design facilities) in NH
23Bringing down costs
24bringing down costs
innovation! (RD)
ECN TU-Delft
25In North-Holland
- Petten We_at_Sea (RD programme management)
- Petten ECN wind energy (technology development)
- ECN WMC (test facility materials and blades)
- ECN Wind Turbine Test Farm Wieringermeer (EWTW)
- Den Helder / TNO / DarwinD / Harokosan
- IJmuiden Windcat workboats Vestas
Maintenance harbour activities
26We_at_Sea Research areas
www-we-at-sea.org
integration scenarios
27the We_at_Sea consortium
- RD Establishments
- ECN windenergie,
- TNO
- TU-Delft
- WMC
- environment, nature
- safety
- Bureau Waardenburg /
- IMARES Texel (univ Wageningen)
- Greenpeace
- St.Noordzee
- University Twente
- wind turbine manufacturers
- GE wind energy
- Vestas
- offshore technology
- Ballast Nedam
- Fabricom
- Fugro Engineers BV
- GustoMSC
- (Marine Structure Consultants)
- Lloyds Register NL
-
- project developers
- E-connection,
- E-concern (Evelop)
- Shell Wind Energy BV
-
- wind energy technology
- Smulders Group
- Siemens
- energy consultants
- Kema Power
- Ecofys
-
- energy sector
- Delta
- ENECO
- Nuon
- Statkraft
- TenneT
- logistics and harbour development
- STC
- financers
- NIBC
-
28ECNs Wind Energy Research
- Aero-elastics
- Wake and Farm aerodynamics
- Wind turbine control systems
- Condition Monitoring and Measurement techniques
- Decision supporting models
29 ECN Wind Energy Research Programme
Wake Farm aerodynamics
Project designers/ Developers/ Offshore operators
LocationFarm design Realisation Commissioning
Operation Dismantling
Control
Manufacturers of turbines and components
Aero elastics
Experiments
Condition monitoring
Owners/ Operators/ OM specialists
Decision support systems for OM
30Multi-MW turbines in the market
- GE 3.6 3.6s
- Enercon E-112
- REpower 5M
- Multibrid M5000
- Siemens SWT-3.6-107
31Future developments
- Announced by leading manufacturers
- Vestas V120 (4.5 MW)
- Upgrade Enercon E-112 ? E-126 (?? MW)
- Developers involvement
- Bard Engineering Bard VM (5 MW)
- Econcern DarwinD (4.5 MW) NL
- No end to scale and concept evolution
32DarwinD
33Research Turbines at EWTW
- A 108m high mast is installed with equipment at
52m, 80m and 108m heights.
- EWTW Test Turbines are five N80 turbines in a
single line
34ECN Wind Turbine Test Farm Wieringermeer (EWTW)
- Five research turbines Nordex (N80) 108m high
metmast - 4 prototypes (GE Siemens)2 metmasts 108m
high - Measurement infrastructure
- Measurement Pavilion
355 x Nordex N80
pavilion
4 prototypes
36Big wind power stations Wake and Farm
aerodynamics
Riso
37OM Optimisation Long Term OM Cost Estimator
- Quantification of future OM costs and
uncertainties - Based on among others condition monitoring data
- changing from corrective maintenance to condition
based maintenance - less consequence damage
- better planning of maintenance actions strategy
38Access technology
39IJmuiden
7 Windcats (3 under construction)
40 access technology(fabricom)
IJmuiden
- Offshore Access System (OAS)
- 1 in operation
- 1 waiting to be installed
- fair speed
- fair price
- handle bar
41 access technology
The Ampelmann - TU- Delft invention -
fair price ?
42(No Transcript)
43Harlingen
Den Helder
ECN / WMC
ECN
ECN / Test field
Lely 4 x NedWind
Egmond / Zee
Q7
IJmuiden
44Harlingen
- Wind power centre
- Turbine Training Centre
- Polymarin (blade production and repair)
45- Den Helder (Texel)
- Harakosan Direct Drive Technology (gt 2MW onshore)
- DarwinD (gt 4.5 MW Offshore)
- AMC-RF Asset management
- Peterson (Logistics North Sea)
- TNO, offshore corrosion en fouling
- ATO-NH Marketing / Development
- DHTC offshore training centre
- IMARES, marine ecology research
- NIOZ, sea- and ocean research
- KIM, maritime technology
46IMARES (Texel, Den Helder, IJmuiden)
- Nature research issues
- Impacts on fish and benthos
- Development bird radar techniques
- Seabird distribution
- Acoustic detection (porpoises and dolphins)
- Grey Seals
- Hearing sensitivity seals
47(No Transcript)
48(No Transcript)
49Thanks for your attention !
- Acknowledgments
- Jos Beurskens (ECN)
- Michiel Zaaijer (TUDelft)
- Jacob Asjes (Imares)
- We_at_Sea partners
Berlin 2007
Westra_at_ecn.nl