Fallback Plans - PowerPoint PPT Presentation

1 / 28
About This Presentation
Title:

Fallback Plans

Description:

only concern is non-planarity of some ladders. impact on silicon track trigger has been studied ... procedure developed to improve planarity. DOE Review. June 6, ... – PowerPoint PPT presentation

Number of Views:45
Avg rating:3.0/5.0
Slides: 29
Provided by: michae661
Category:

less

Transcript and Presenter's Notes

Title: Fallback Plans


1
Fallback Plans
  • John Womersley

2
How did we get here?
  • December 1999
  • letter from Directorate to DØ asking us to
    investigate fallback options
  • January 2000
  • established a Contingency Planning Panel within
    DØ to advise the spokesmen, solicit input from
    the collaboration, and review the documents
  • Ken Johns (chair), Alice Bean, John Ellison, Paul
    Grannis, Nick Hadley (physics coordinator),
    Sijbrand de Jong, Greg Landsberg, Darien Wood
  • Weekly open meetings to present studies, discuss
    issues

3
Documents
  • January 2000
  • Looked at Options
  • DØ Note 3724 Fallback Options for the DØ
    Upgrade
  • March/April 2000
  • Formed a plan
  • DØ Note 3741 DØ Schedule and Contingency Plan
  • Physics Justification
  • Physics Impact of Tracking Detector Contingency
    Plans
  • these three documents are part of the materials
    made available to the committee

4
Our goals
  • We fully intend to complete the whole DØ detector
    for the start of Run II on March 1, 2001
  • In exploring fallbacks and contingency plans, we
    have not learned of anything that would prevent
    this from being accomplished
  • We have taken the view that developing these
    fallback strategies will help us accomplish this
    goal

5
Where are we exposed?
  • In general the critical areas are
  • Silicon Tracker
  • Electronics
  • Installation (time constraints)
  • The following are either complete or schedule is
    not an issue
  • central muon system
  • calorimeters
  • solenoid
  • central preshower
  • forward preshower and ICD
  • fiber tracker detector assembly
  • forward muon detector assembly
  • online system
  • Not an issue, despite some concerns in January
  • availability of sufficient SVX chips

6
DØ central tracker
7
Physics goals for tracking
  • The Run II Physics menu is a broad one
  • QCD, B-physics, precision EW, top, SUSY, Higgs .
    . .
  • High pT processes
  • typically require good performance at moderate to
    high momenta and central rapidities (?lt 2)
  • SUSY multilepton signals
  • demand pT 5 GeV and coverage in ? up to the
    limits of electron ID (?lt 2.5)
  • B-physics
  • requires even lower pT 1 GeV and maximal
    coverage in ?
  • The environment
  • vertex ? 30 cm in z
  • radiation 400 krad per fb-1 at the inner layer

8
DØ Silicon Tracker
Six Barrels Four layers barrels 2-5 two 2º, two
90º stereo layers barrels 1-6 two 2º stereo,
two axial layers
12
11
10
9
6
5
4
4
3
2
3
1
2
1
8
7
6
5
Twelve F-disks each with 12 double-sided wedges
15º stereo
Four H-disks each with 24 single-sided wedges
glued back-to-back
9
SMT acceptance
  • Barrels
  • Provide acceptance at relatively low rapidity and
    for central zvtx
  • Disks
  • Primary tracking system at moderate to large
    rapidity (2 lt?lt 3)
  • Cover gaps between barrel detectors for ?lt 1.5

10
Physics studies
  • Evaluated existing design studies
  • Heinson, Heintz, 1993-98
  • To assess the impact of descope options, new
    studies were carried out
  • Barberis, Demina, Heinson, Jesik, Kulik, Khanov,
    Whiteson
  • MCFAST
  • GEANT DØ C tracking code
  • GEANT silicon groups standalone tracking code
  • Have investigated single tracks, top events, and
    B ? ? KS

11
B ? ? KS
MCFAST, R. Jesik
12
Barrels
  • Small angle stereo ladders (used in all barrels)
  • crucial for pattern recognition no viable
    fallback except to use lower quality devices if
    necessary
  • layer 2 detectors suffer significant radiation
    damage use higher depletion voltage devices in
    this layer
  • Single-sided ladders (barrels 1 and 6)
  • only concern is non-planarity of some ladders
  • impact on silicon track trigger has been studied
  • procedure developed to improve planarity

13
Barrels 90 ladders
  • 90 stereo ladders (barrels 2-5)
  • several concerns at the start of this process
  • p-stop shorts (manufacturing defects)
  • fears about ability to bias at sufficiently high
    voltage to withstand the radiation dose
  • high occupancy raised questions about usefulness
    of 90 strip information to the pattern
    recognition
  • it was therefore suggested that we resort to
    using single-sided axial detectors everywhere

14
Barrels 90 ladders
  • Studies showed
  • p-stop defects cause only 1-2 loss of strips
  • radiation damage studies show layer 1 probably OK
    to 3-4 fb-1
  • subsequent studies of B-physics observables show
    that the 90 strips are crucial
  • omission of 90 strip information worsens the
    proper time resolution from 95 fs to 150 fs
  • reduces effective flavor tagging efficiency by
    10 (worsens sin2? error by 10)
  • We therefore have no plan to discard the 90
    double sided ladders

15
Close up the barrels?
  • There is a loss of acceptance between the barrel
    modules
  • gaps in z are required for the F-disks
  • if the barrels were pushed closer together, a
    3-5 gain in acceptance for high pT tracks could
    be realized (for barrel hits alone)
  • BUT
  • this would still leave gaps due to inactive
    detector area
  • in principle all the tracks passing through these
    gaps can be recovered using F-disk hits
  • On April 26, we committed to cut the openings in
    the support cylinder in such a way that the
    barrels are positioned as designed
  • accommodate full complement of central F-disks
  • precludes possibility of closing the gaps between
    the barrels
  • this has now been done

16
F-disks
  • Concerns
  • Component deliveries
  • Assembly
  • these are the most complex combination of
    sensors, HDI and SVX chips
  • Physics impact
  • central disks
  • acceptance of central tracks without these
    disks, we would lose 15 of fully reconstructed B
    ? ? K0S events ( 3-4 ? single track
    inefficiency)
  • expect similar problems whenever three or four
    tracks are required e.g. secondary vertex
    tagging of high pT b-jets
  • end disks
  • in B ? ? K0S, primarily influence tagging
    efficiency and proper time resolution
  • Disks 1 and 12 carry radiation sensors, and disks
    2 and 11 carry kinematic mounts

17
H-disks
  • Affect acceptance and resolutions for ?? 2
  • Production is well advanced with little schedule
    risk
  • Modules can be installed very late, if necessary

18
Fallback Strategy
  • Small angle stereo ladders
  • install detectors with imperfections if necessary
  • we have already done this in barrel 1
  • 90 stereo ladders
  • install detectors with one p-stop defect (1-2
    bad channels) if necessary
  • Single sided ladders
  • no issue
  • F-disks
  • Decision of the Contingency Planning Panel
    (April 19)if there is a need to reduce the
    complement of F-disks installed, sacrifice disks
    3 10 leaving a triplet of disks at each end

19
First Barrel Assembly
Grade B (electrical)
Grade C (electrical)
20
Reducing F-disk complement
Remove disks 3 and 10
  • IF DONE, THIS WOULD BE A NON-RECOVERABLE DESCOPE
  • The first decision point for this is July 1

21
Decision Triggers
22
June 1
  • Schedule calls for
  • 2 barrels, 4 disks complete
  • Actual status was
  • 1.5 barrels, 2.5 disks
  • Actions required
  • Review likelihood of SMT-S installation by
    8/1/00. Consider early reduction of F disk
    complement if 3 disks are not complete
  • What we did
  • Project managers and spokesmen discussed progress
    with silicon management
  • all parts are in hand for first six disks (first
    half SMT)
  • support rings were a holdup, but now proceeding
  • F-disk managers believe that all six disks can be
    completed by August 1
  • we will revisit the status on July 1, as called
    for in our plan

23
July 1
  • Schedule calls for
  • 3 barrels, 5 disks complete
  • Actions required
  • If two barrels are not complete
  • Delay SMT-S installation date to 10/1/00.
  • If 3 F disks are not complete
  • reduce F disk complement by two to 10.
  • Silicon managers anticipate that the second
    barrel and two more F-disks should be complete
    by this date, so we do not presently anticipate
    triggering the descope.

24
Installation
  • Over the last six months a great deal of effort
    has gone into understanding and tuning the
    installation schedule
  • We have been able to gain significant schedule
    contingency through logistical changes and by
    splitting the SMT into two halves
  • Nonetheless, the present schedule does not have a
    lot of slack left
  • Exposure in
  • possible late delivery of silicon
  • hookup time for CFT and SMT
  • forward muon installation
  • engineering design and fabrication still required
    on supports
  • delayed availability of electronics and VLPC
    cassettes
  • mainly impacts commissioning activities, and
    complicates hookup

25
Silicon Installation
  • Baseline dates for detector completion (ready to
    move to DØ)
  • SMT-S August 10, SMT-N October 27
  • silicon group internal goal is completion of
    SMT-S by August 1
  • Baseline dates for start of installation in DØ
  • SMT-S September 21, SMT-N November 2
  • Latest possible dates for installation in DØ
    consistent with roll-in
  • SMT-S November 1, SMT-N January 1
  • SMT installation depends on completion of the CFT
    waveguide installation two shift operation was
    assumed, could go to three if necessary, or work
    on N and S simultaneously
  • if SMT-N comes this late, hookup will need to be
    done in the collision hall
  • Ultimate option
  • install SMT-N after roll-in

26
Forward Muon Installation
  • We have exercised one fallback option already
  • June 1 decision NOT to install the south muon
    truss in the hall during August
  • it was felt better to use resources elsewhere
  • We have prioritized and largely serialized the
    installation sequence
  • A, C, B
  • B layer occupies the last two months 11/15-1/15
  • ultimately we have the option of installing layer
    B once the detector is rolled into the collision
    hall
  • some additional engineering will be required

27
Electronics
  • We expect all readout electronics to be in place
    for March 1 in any case, delays do not impact
    roll-in
  • We have developed alternative strategies for
    hookup and commissioning
  • Tracking detectors
  • CFT commissioning plan assumes no production
    electronics are available use stereo boards
    (cosmic ray test electronics)
  • SMT will use prototype interface boards
  • Muon system
  • extensively tested before being moved to DØ
  • will commission with limited number of prototype
    boards
  • Calorimeter
  • 5000 channels (one quadrant) will be available in
    September
  • Ultimate fallback
  • start running with a partially instrumented
    detector

28
Conclusion
  • We have developed a set of fallback options and
    contingency plans and have started to implement
    them.
  • The major decisions remaining are in the silicon
    tracker and in the installation.
  • We have learned a great deal about the detector
    and we have also made significant progress in
    production since December 1999 when this process
    was begun.
  • In light of this progress, we do not believe that
    we will need to exercise any of these options
    nonetheless, we now know what to do if we have
    to.
  • The DØ detector will be installed and ready for
    Run II on March 1, 2001
Write a Comment
User Comments (0)
About PowerShow.com