Title: THERMAL ISSUES J' Burger, M' Molina
1THERMAL ISSUESJ. Burger, M. Molina
2- C. Vettore
- M. Cova
- W. Du
- G. Xin
- A. Assenza
- R. Zambra
- A. Moroni
- H. Zhang
- J. Zheng
- A. Franzoso
3AMS-02 TCSStructural Test Article
- H. Zhang J. Zheng
- R. Zambra A. Assenza
4WHY NEED STA?
Requested by NASA when FE Analysis of the Flight
Model shows frequency lt 50Hz
5WHAT IS STA?
- Represent the static and dynamic behavior of the
Flight Model - Constraints
- Mass
- Center of Gravity
- Moments of Inertia
- Frequencies / Effective Mass
6FM OF RAM RADIATOR
7Crate Structure
STA
FM
8XPD Structure
STA
FM
9SHVGPS Structure
STA
FM
10RAM Radiator for STA
11Mass, CoG MoI
12Frequency and Effective Mass Comparisonfor RAM
Radiator
13RAM Radiator FM mode 1
RAM Radiator STA mode 1
14RAM Radiator FM mode 5
RAM Radiator STA mode 4
15RAM Radiator FM mode 9
RAM Radiator STA mode 9
16Frequency and Effective Mass Comparisonfor WAKE
Radiator
17WAKE Radiator FM mode 1
WAKE Radiator STA mode 1
18WAKE Radiator FM mode 4
WAKE Radiator STA mode 4
19WAKE Radiator FM mode 8
WAKE Radiator STA mode 8
20CONCLUSIONDifferences between FM and STA
- MASS lt2Kg
- CoG lt8.2mm
- MoI lt3.5Kgm2
- First Frequency lt3Hz
21(No Transcript)
22(No Transcript)
23(No Transcript)
24(No Transcript)
25AMS CDR
26RIDS status
- 87 RIDS submitted (by Boeing , NASA, MIT, Jacobs,
CRISA) - 6 withdrawn
- 13 rejected
- 35 closed
- 33 accepted with actions
27Main TCS requirements
- Allow AMS Electronics to be transported to the
ISS during various phases (STS in free flight,
STS docket to the ISS, transfer to ISS, switch
on) with various power level availability - Allow charging the magnet through CAB
- Keep Electronics within op / Non op range for 3
to 5 years mission (and more) namely all Beta
angle ranges. - see Thermal ICD
28Main TCS requirements
- Provide a suitable sink to the Tracker TCS to
perform nominally (i.e. to have a set point
10C to 15C through the mission) - Maximize the duration of time AMS electronics can
survive without power (8 hours are the best
available design goal for mission success from
NASA) - Provide a system of heaters that
- allow starting up AMS (bringing the electronics
at min. op temp) - Keep AMS within non.op temp ranges when needed
29Main TCS requirements
- all what above NOT affecting the subdetectors
- Each subdetector, in turn, is requested to
- Be able to be transported to the ISS during
various phases (STS in free flight, STS docket to
the ISS, transfer to ISS, switch on) with various
power level availability - Remain within op / Non op range for 35 years
mission (namely all Beta angle ranges) - see Thermal ICD
- Maximize the duration of time it can survive
without power (8 hours are the best available
estimate) - Have a system of heaters that allow starting up
or remaining within non.op temp ranges when needed
- We are coordinating this verification effort
30Subdetectors TCS
- Subdetectors TCS DESIGN is a separate task
- CGS is providing data to the subdetectors to
allow them verifying their thermal design - Special requests are considered case-by-case
31AMS analytical integration
32SUBDETECTORS THERMAL DESIGN STATUS
33(No Transcript)
34(No Transcript)
35(No Transcript)
362 TYPE OF ELECTRONIC UNITS
37Heat Pipes Layout
38Inserts and heat pipes
- 15 tested samples
- requested by NASA
39Heaters on Main radiators
Power density issue
403 TYPE OF BRACKETS
41(No Transcript)
42Tracker Radiator
Face Sheet (0.8mm / Al 2024T81)
CORE (15mm / Rohacell)
Face Sheet (0.2mm / Al 2024T81)
43TCS Radiator Panels
44Bracket between Main and Tracker Radiator
Al 2024 T81
45MLI
Weight issue
46AMS-02 120Vdc Heaters Summary C.Vettore
47(No Transcript)
48(No Transcript)
49PDS Heaters location
50PDS Heater patch panel
51Main Radiators Thermal Analysis
- M.Cova, C. Vettore, W. Du, G. Xin, F. Bodendieck
52Electronics Location
WAKE
RAM
53RAM Nodal Breakdown
- 953 Nodes for radiative face sheet
- 953 Nodes for crates face sheet
- 705 Nodes for ROACHELL
- 258 Nodes for HPs
- ? 2869 nodes
RAM
54WAKE Nodal Breakdown
- 1159 Nodes for radiative face sheet
- 1159 Nodes for crates face sheet
- 824 Nodes for ROACHELL
- 298 Nodes for HPs
- ? 3440 nodes
WAKE
55Thermal Analysis Results
56STS UNMATED ATTITUDE
57Crates I/F temperatures for the Worst Hot Case on
STS free flying
58ON ISS
59Crates main wall I/F temperatures for the Worst
Hot Operative Case on ISS
60Crates main walls I/F temperatures
61On STS free flying
62STS docked - hand off
63On ISS
64On STS free flying
65STS docked - hand off
66On ISS
67Subdetectors thermal analysisConclusions
- ECAL will operate for 97 of mission time
- RICH will operate for 93 of mission time
- No problem for LTA for the subdetectors
- Cooling down after 8 hours power outage is a
marginal issue for ECAL that reaches -30.9C
68Subdetectors thermal analysis(TOF, ECAL, RICH,
HV BRICKS, E-CRATE)
69Lower ToF Thermal Requirements
- Operative Temperature Range
- -30C55C
- confirmed by test results
- Non Operative Temperature Range
- -40C60C
- confirmed by test results
70(No Transcript)
71ECAL Thermal Requirements
- Operative Temperature Range
- -20C40C
- Non Operative Temperature Range
- -30C50C
-
72ECAL can work 97.2 in terms of mission time 7
hours survival time with no power
73RICH Thermal Requirements
- Operative Temperature Range
- -30C50C
- Non Operative Temperature Range
- -35C60C
- confirmed by test results
74RICH can work for Beta angles 55?b?75 and so
for 92.7 in terms of mission time
75E-crate Thermal Requirements
- Operative Temperature Range
- -20C50C
- Non Operative Temperature Range
- -40C80C
76(No Transcript)
77EHV Thermal Requirements
- Operative Temperature Range
- -20C60C
- Non Operative Temperature Range
- -40C70C
78(No Transcript)
79(No Transcript)
80Star Tracker CCD Thermal Requirements
- Operative Temperature Range
- -30C55C
- Best Performance Operative Temperature Range
- -30C35C
- Non Operative Temperature Range
- -40C80C
81(No Transcript)
82ACC PMTsThermal Requirements
- Operative Temperature Range
- -30C55C
- Non Operative Temperature Range
- -40C60C
83(No Transcript)
84UPSThermal Requirements
- Operative Temperature Range (magnet charged)
- -25C50C
- Non Operative Temperature Range (magnet
uncharged) - -40C50C
85(No Transcript)
86UMA Thermal Requirements
- Passive Half Spring
- Operative Temperature Range
- -67C164C
- Non Operative Temperature Range
- -67C164C
- Connector Backshell
- Operative Temperature Range
- -67C93C
- Non Operative Temperature Range
- -67C93C
87(No Transcript)
88PVGF Thermal Requirements
- Operative Temperature Range
- -70C90C
- Non Operative Temperature Range
- -157C121C
89(No Transcript)
90FRGF Thermal Requirements
- Operative Temperature Range
- -76C168C
- Non Operative Temperature Range
- -156C121C
91(No Transcript)
92(No Transcript)
93Propylene LHP
94Cryo-cooler Thermal Control Design
- LHP evaporator and bypass valve
Cryo-cooler
95Cryo-cooler Thermal Control Design
Two heater (Branch A and Branch B), one on each
evaporator side Each 42,9 W _at_126,5 V 2.52 W/cm2
CDR Heater will be smaller to increase power
density. GSFC suggestion from L.A. meeting.
Symmetric heating also to be considered.
96LHP Modelling
97LHP Modelling
- L-level and H-level nodal layout of the AMS
cryo-cooler radiator
- The coarse H-l nodal break down (part of ESATAN
Model) has 10 nodes - The detailed L-l nodal break down (part of LHP
Model) has 176 nodes
Outlet
Inlet
98Performance Prediction maximum heat transport
capability of 1 LHP LHP performance during
hottest case (Beta 75, YPR -15/-20/-15)
- Q 120 W for 1 LHP gt Tmax,Cryo 37.7C
In the worst hot case only 120 Watt can be
handled by a single LHP
99AMS OFF (coldest case considered)
- Q 158 W on 2 LHPs (bypass valves in radiator
mode).
- Cooler at T-5.5C before switch-off. After
switch off cooler temperature decreases to
evaporator temperature of -22.5C during 25 min.
Temperature almost constant (1C) during
following hours. - Feature to be tested with the EM
100LHP EM requirements
- First round table discussion on test required and
EM configuration - April 6, 2005 CERN
101EM testingWHAT CAN BE TESTED?
- Heat transport capability
- Dryout limit
- Power share between the 2 LHPs
- Performance degradation vs. time
- Shut-off capability in case of loss of power
- Performance after vibrations
102EM configuration
- It is composed by 2 LHP
- It has a bypass valve (whose setpoint is manually
adjustable) - It is based on the longest LHP geometry (bottom
cryocooler) - LHP is in flat config with same number and type
of bends of the FM
103EM TESTS
- Vibrations
- Life test
- Power outage
- Filling Level
- Bypass valve performance characterization
104CAB thermal control concept for CDR
105CAB TCS design
- New power requirement
- From 600 W to 740 W (800 W in some operating
modes) - New (lower) I/F temperature requirements
- 40C instead of 50C
- With one LHP (connected to wake radiator, as
baselined so far) CAB cannot charge the magnet
106Plans for system level design CGS tasks
- Enhance the heat exchange between CAB base-plate
and LHP evaporator saddle at contact level (seems
to be the current bottle-neck wrt. the maximum
LHP rejection performance) - Enlarge area
- Enhanced contact conductance, now assumed 1000
W/m2/K
107Ideas for recovering CAB Thermal design
- Additional LHP(s)
- sunk to the WAKE radiator
- sunk to RAM radiator
- CAB unit on Wake radiator
- Reduce the gradient along the CAB base-plate
- Enhance the internal CAB thermal design
- Micro heat pipes in the modules
- Standard HPs directly in contact with modules
- Carbon fiber straps
- PCM embedded in a sandwich panel
108TCS Weight budget
109Additional MLI
110Missing MLI
111(No Transcript)
112DThermal CDR - conclusions
- Is TCS design completed?
- Freeze the TCS configuration of the radiators
- Main RAM and WAKE standard fixation for CAB LHP
- Tracker radiator available area has been
maximized wrt Tracker requirements - TTCS needs to accept current configuration
- Zenith radiator
- EM will be built with curent configuration
- FM will wait until analytical results (LHP CDR,
Summer 2005) - No impacts foreseen on radiator area
- Proceed completing the detailed design (now at
85)
113DThermal CDR - conclusions
- Whats next to get the go-ahead for
manufacturing? - Pending
- Heaters rework
- To meet new NASA power density requirement (3
W/sq(in) instead of 3.5 W/sq(in) ) - Minimum power to switch on RAM electronics in
coldest cases - Inserts verification
- More samples tests (15) requested by NASA
- CAB thermal design
- standard fixation for CAB LHP(s)
114DThermal CDR - conclusions
- We know additional analysis will keep going till
COFR (2 years and more) - Data have been provided to JSE for the Flight
Safety Review II
115Short time schedule
- Meeting in the afternoon about CAB
- Heaters design ready in less than 1 month
116Next milestones
- LHP CDR Summer 2005
- TTCS CDR Summer 2005
- LHP EM DELIVERY Fall 2005
- RADIATORS STA DELIVERY
- Fall 2005
- FM DELIVERY 2006
117REMARKS by NASA
118Configuration of TMMs
- I/F data delivery (environment) must undergo
configuration control - The way system level model and subsystem level
model is put together will be documented by CGS - AMS Thermal model is configured internally at CGS
- This should be documented outside as well
- Each subdetector model should be configured and
provided to CGS for - Review, approval and
- integration
- This addtional work requires additional resources
119Subdetector Models
- System level TCS choices vs. Subdetectors TCS
status - Are the subdetectors at a CDR stage, too?
- Sophisticated TMM bringing them down to a
level that can be analytically integrated into
system level thermal model - Missing TMM
- Every TMM plan to do a subdetector TMM review
- Anything looks marginal should be thoroughly
reviewed
120Power Outage Issues
- Concerns of being able to tolerate power off
conditions for reasonable time period (goal is 8
hours) - Evaluating percentage of the year the 8 hours
goal is respected