Title: ALCON LABS
1ALCON LABS
- Project Chiron
- SMU TEAM ALCON
2Project Overview
- Project Background
- Problem Description Core Objectives
- Action and Approach Plan
- Analysis of Situational Approach
- Analysis and Managerial Interpretation
- Recommendations
3Project Background
- October 2003 Alcon Madrid manufacturing plant
closed down - Madrids product baseline of 170 SKUs and 12
million units were transferred to Fort Worth
headquarters - Before the Madrid divesture, the Fort Worth
manufacturing plant was producing 230 to 250 SKUs
and 70million units
4Definition of the Problem
- Whitestock Lines 1 2
- Production inefficiency and delays
- Lagging downtime
- Line clearances (LC) occupy 20-30 minutes
- LC occurs 4-5 per day
- Loss of Capacity
5Core Objectives
- Primary objectives
- Minimizing splits
- line clearances and/or QA
- Maximizing utilization of fill rooms
- Secondary objective
- Optimizing the facility layout
- Optimizing the lot size (batch) or economic order
quantity levels
6Core Objectives - Benefits
- Significant cost savings
- Improved uptime and process efficiency
- Improved capacity levels
- Improved overall throughput speed and other
technical performance measures - Reduced or eliminated inventory levels and other
unnecessary costs - Minimized idleness of employees (i.e. employee
output efficiency)
7Action Approach Plan
- Short-term perspective
- Determine and measure Alcon Labs Manufacturing
processes to locate source of problem associated
with LC - PAT and SMED method
- Long-term perspective
- Converting 2-step process to inline process
- ProModel Simulation Models
8Analysis of Situational Approach
- Short-term approach
- Whitestock Line 1 2
- Observed and measured the splits process steps
for cycle time improvements - Recorded the sequence of repeatable activities
with measurable inputs, value-added activities,
and measurable outputs
9Analysis of Situational Approach
- Short-term approach
- PAT Method
- SMED Method
- Internal and External Setup activities
- Improve cycle time or changeover/roll-over time
by reorganizing and reducing setup activities as
well as resources and inventory waste and
rescheduling production schedules for low
quantity batches while sustaining high product
quality - Other benefits of setup reduction include lower
cost (less inventory), better flexibility, better
worker utilization, shorter lead time, increased
capacity, and most importantly, less process
variability
10Analysis of Situational Approach
- SMED Method Process Flow chart
11Analysis of Situational Approach
12Analysis of Situational Approach
- Long-term approach
- Converting 2-step process to inline process
- Observation Data Collection
- - process and layout,
- - setup/changeover times,
- - speeds and capacity, etc.
- - ProModel Simulation software
- Assumptions
- Current Process Simulation Model
- New Process Simulation Model
13Analysis of Situational Approach
- Long-term approach
- Variables/Functions
- - locations
- - entities
- - network paths
- - process/logic
- - arrivals
- product differentiation
- setup downtimes
14Analysis of Situational Approach
- Long-term approach Assumptions
- Setup times for each machine were calculated
using an average from the statistics provided. - Simulation models are programmed to run at
particular speed as opposed to individual actual
speeds. - Offline filling and storage time and activities
are not accounted for in the simulation model. - The proposed filler speeds and product specifics
are assumed to be similar to the current
equipment capabilities - When locations and resources appear to be idle,
setup downtimes are in occurrence.
15Analysis Managerial Interpretation
- Short-term Approach
- Alcon Operation or Process steps
- Staging (storage) area
- Line area inspection
- Changeover
- Production
- Finished goods area
- Reconciliation with Materials Office
16Analysis Managerial Interpretation
- Short-term Approach
- Changeover is the main cause for low efficiency.
- Steps in setup process
- Preparation, after-process adjustments, checking
of materials and tools - Mounting and removing blades, tools, parts
- Measurements, settings, and calibrations
- Trial runs and adjustments
17Analysis Managerial Interpretation
- Short-term Approach
- Calibration and Trial Runs occupy a total of 85
of total time (changeover and LC time)!
18Analysis Managerial Interpretation
- Short-term Approach
- Changeover setup adjustments
- Labelers
- Cartoners
- Magazines
- Ink Jet Coder
- Wrapper/Packaging
- Adjustments are made by trial-and-error as well
as intuition
19Analysis Managerial Interpretation
- Short-term Approach Changeover
20Analysis Managerial Interpretation
- Short-term Approach
- Other inefficiencies
- Incorrect Madrid Translations
- Disconnected communication across divisions
21Analysis Managerial Interpretation
- Long-term Approach
- Decreased product handling and movement
- Increased flexibility and capabilities
- Increased utilization, productivity levels, and
capacity - Automated flex pack line
- Decreased downtimes
22Recommendations
- Long-Term Solution
- Recommend 1-year further analysis and research
- - costs
- - equipment
- - feasibility requirements
- - build a more accurate model
- - implementation
23Recommendations
- Short-Term Solution
- Strongly recommend forming a changeover team of
4-5 members - Labelers
- Cartoners
- Magazines
- Ink Jet Coder
- Wrapper/Packaging
- Update changeover team regarding production
schedules for advanced preparation
24Recommendations
- Short-Term Solution
- Allocate secondary space for storage
- Color code
- Next Raw materials red (stop)
- Current Raw Materials and Finished product
green (go)
25Recommendations
- Short-Term Solution
- Streamline line clearance to a parallel process
- Cross-train personnel
- Require employees to perform other functions in
the changeover process - Ensure prompt arrival of Bill of Materials
- If items arent available, contingency plan
should be developed - Improve coordination between Marketing, Planning,
and Production divisions - Function standardization
- Replace bolts with one-time tighteners!
- Mark individual calibration settings for each
product on each line for easy adjustments
26Questions?
- SMU TEAM ALCON
- Benjamin Luong
- Chris Davis
- Cuong Ngo
- Cindy Nguyen
- Shanta Ramdhanny