SCT Readout Cables - Status
  • Sector 9 18 EC cables installed and tested.
  • Sector 3 18 barrel and 9 EC cables installed,
    out of which 6 barrel cables were tested.
  • Sector 1 18 EC cables installed, no tested.
  • Sector 7 18 barrel cables delivered to the
    pit, likely to be installed next week.
  • In total, 63 cables out of 144 installed, 24
    tested.
  • 39 untested cables should be tested during the
    next week.
  • Problem 1 In a few cases there are one or two
    ribbons in the cable shorter by 15-20mm than the
    other ribbons. The required precision of the
    final connector position is 5mm, which obviously
    can not be achieved for these cables. The
    ribbons are installed such that the shortest
    ribbon reaches the specified position.
    Experience with the mock-up of ribbon connections
    at PPB1 and PPF1 indicate that it should be OK.

2
Suggestion to swap SCT ROD racks
  • Problem 2 barrel cables in sector 3 shorter than
    needed (by 2 meters), since they were by mistake
    ordered without any contingency (normally 7
    meters in addition).
  • Suggested solution swap the EC and barrel ROD
    racks in USA 15. According to the PRR2 document
    we should gain 1.7 meters by the swap of racks,
    perhaps a bit more in reality. This should solve
    the problem in sector 3 (e.g. all cables
    installed so far would be OK).
  • Hopefully the other sectors installed in future
    will be then OK as well. If not, a back-up
    solution is to modify the cable tray routing in
    USA 15 (to make the fibre cable path a bit
    shorter).
  • As a by-product of the suggested solution, we
    will loose some of the excess of the EC cables,
    which is difficult to store at the moment.
  • Request to the steering group could you approve
    the swap of the EC and barrel racks?

3
FSI delivery cables
  • 38 cables in total
  • Sector 3 All 9 cables cut according to the
    length specified in PRR2 document (EDH).
  • Problem The cable lengths were by mistake
    ordered without the 7m contingency, and the
    cables appeared to be too short.
  • Solution The cable path has been changed by
    Serguei Malyukov, now the cables from sector 3
    are OK.