1Eli Lilly Leveraging SAP XI in Your Landscape
Costs, Benefits, Lessons Learned
- Timothy S Yates tyates_at_dataxstream.com
- Scott A Sanneman sanneman.s_at_lilly.com
2Learning Points
- This presentation will give you a solid starting
point for determining / cost justifying an SAP XI
Implementation. - This presentation will give you specific
considerations that need to addressed up front in
order to control scope creep and cost. - This presentation will give you specific
technical lessons learned that can potentially
impact implementation timeline, delivery quality
and overall implementation cost.
3Background On Eli Lilly XI Implementation
- General Company Information
- SAP Project History
- SAP Integration Infrastructure History
- SAP XI Project
4Eli Lilly General Company Information
- Pharmaceutical company founded on May 10, 1876
- gt 41,000 employees worldwide
- 20,000 OUS, 8000 R/D
- Research and development facilities located in 9
countries - Manufacturing plants located in 13 countries
- Products marketed in 143 countries
- Headquarters Indianapolis, Indiana, U.S.A
- gt 15 Billion in net sales in 2006
5Eli Lilly SAP Project History
- The Eli Lilly philosophy was to implement common
business processes worldwide enabled by an
integrated information environment - Introduced the Global Business Integration
Project (GBIP) to the organization in 1998 - Intent on standardizing common data and systems
worldwide - Scope included HR, Finance, SCM PMP.
Implemented 1st 2 countries (France Spain) in
1999 - Strict release timeline of 6 month cycles for new
countries - 16 countries implemented SAP, all currently on
SAP R/3 4.6c - SAP payroll for the USA introduced in 2006
- All other (Non-SAP) countries following many SAP
processes through integration (i.e. HR data for
all Non-SAP countries integrated into SAP via
global interfaces) - XI successfully implemented, intended to
eventually replace existing data movement
infrastructure - Lilly is currently undertaking an upgrade to
ECC6.0.
6Eli Lilly SAP Infrastructure History
- In The Late 90s Identified The Need For An
Integration Infrastructure To Support The
Integration Needs Of The Project. - Tools Like Mercator and MQSeries Where Selected
Because They Represented The Best Of Class Tools
For Enterprise Architecture Integration At The
Time. - The Last 6 7 Years Have Been Spent Developing A
Set Of Lilly Specific Tools Based On These
Technologies.
7Eli Lilly Existing Infrastructure Challenges
- Infrastructure Built Using Different Tools
- Requires diverse skill set, Upgrade complexities,
Change control - Tool Stability, Agility, Reproducibility
- Using several tools requires many resource to
diagnose issues - Future Of Current Tool Set Not Clear
- Mercator Was Purchased Last Year By Accential
Software. Accential Software Was Purchased By
IBM This Year. Implications Unknown In Short
Term. In The Long Term Should Be Good But
Changes To Tools May/Should Eventually Drive
Significant Upgrades. (Past Changes Have Been
Implemented Without Backward Compatibility)
8Eli Lilly SAP Infrastructure
- Eli Lilly has developed a custom designed routing
system as part of existing infrastructure, which
includes - Transformation and Routing
- Mercator (IBM DataStage TX), Gentran,
Informatica, C Programs - Messaging
- IBM MQ Series
- Delivery
- C Programs (Wrapper / Unwrapper)
- Database
- Oracle
- Source Control
- Rational Clear Case
- Configuration Web Interface
- Java
- Maintenance, Trouble Shooting, Migration and
Consistency Checking - UNIX - Scripting and Security, Manual FTP
9Eli Lilly Existing Infrastructure Diagram
10XI Concept at Eli Lilly Scope
- Implement functionality to determine capabilities
and positioning in GBIP architecture - Pilot Design and implement 40 interfaces
- Technical Criteria Re-implement minimal
interfaces to cover most scenarios (File, IDOC
and MQ to JMS adapters) - Build entire XI infrastructure, including
configuration, development, testing (QA)
production environments - Pilot implementation would be seamless to
existing business users when compared to existing
infrastructure!
11XI Concept at Eli Lilly
- Reduce Number Of Tools To Support Interfaces
- Built On Robust SAP Technology With SAP Support
- Will Reduce Long Term Support
- Eliminates Need To Fund Additional Data Sharing
Infrastructure Improvement Projects. - Technology Is Mature And SAP Community Is Moving
In This Direction - Will Be Required To Leverage New SAP Integration
Development
12Starting Point For Determining / Cost Justifying
SAP XI Implementation
- Building The Foundation
- Project Types
- Project Approaches
- Understanding Project Cost / Savings
- Project Cost Considerations
- Project Cost Savings
13Project Types
- New EAI / B2B Implementation
- Adding SAP XI To Existing EAI / B2B
Implementation - Legacy EAI / B2B Replacement Implementation
- Legacy EAI / B2B Consolidation Implementation
14New EAI / B2B Implementation
- Current Infrastructure
- No Existing EAI / B2B Tools In Use Today
- Business Drivers
- EAI / B2B Functionality Required
- Leverage Existing SAP Skill Sets (ABAP / JAVA)
- Alternative Options
- Build Point To Point Interfaces With Available
Programming Tools - Implement Solution From Different Vendor
- Challenges
- Building Out SAP XI Support Infrastructure
- Internal EAI / B2B Experience
- Finding Good External EAI / B2B Experience
15Adding SAP XI To Existing EAI / B2B Implementation
- Current Infrastructure
- Currently Have Other EAI / B2B Tools In Use Today
You Intend To Keep - Business Drivers
- New SAP XI Functionality Required
- Leverage Existing SAP Skill Sets (ABAP / JAVA)
- Alternative Options
- Implement Solution From Different Vendor
- Continue / Expand Use Of Current Tools
- Challenges
- Building Out SAP XI Support Infrastructure
- Finding Good External EAI / B2B Experience
- Supporting Additional Tool SAP XI
16Legacy EAI / B2B Replacement Implementation
- Current Infrastructure
- Currently Have Another EAI / B2B Tool In Use
Today You Intend To Replace - Business Drivers
- New SAP XI Functionality Required
- Leverage Existing SAP Skill Sets (ABAP / JAVA)
- Consolidation Of Existing Designs
- Current Infrastructure
- Complexity
- Deficiencies
- Substantial Upgrades Required
- Current Vendor Support / Direction Concerns
- Alternative Options
- Implement Solution From Different Vendor
- Continue / Expand Use Of Current Tools
- Challenges
- Building Out SAP XI Support Infrastructure
- Finding Good External EAI / B2B Experience
- Supporting Additional Tool SAP XI (In Phased
Replacement Approach) - Adapting Source and Target Applications To
Leverage New Tool Set
17Legacy EAI / B2B Consolidation Implementation
- Current Infrastructure
- Currently Have Multiple EAI / B2B Tools In Use
Today You Intend To Replace/Consolidate Into XI - Business Drivers
- New SAP XI Functionality Required
- Current Infrastructure
- Complexity
- Deficiencies
- Substantial Upgrades Required
- Current Vendor Support / Direction Concerns
- Consolidation Of
- Existing Designs, Tools, Skill Sets, Teams and
Resources - Alternative Options
- Continue / Expand / Consolidate Use Of Current
Tools - Challenges
- Building Out SAP XI Support Infrastructure
- Finding Good External EAI / B2B Experience
- Supporting Additional Tool SAP XI (In Phased
Replacement Approach) - Adapting Source and Target Applications To
Leverage New Tool Set - Managing Functional / Technical Trade Offs To
Maximize Overall Project Benefit
18Project Approach Types
- Proof Of Concept
- Implement A Representative Set Of SAP XI
Functionality Required To Meet Overall
Architectural Goals. - Big Bang
- Implement All Required SAP XI Functionality In
One Software Release. - Only Really Practical For New and Small
Replacement Implementations. - Phased
- Implement Required SAP XI Functionality Over A
Series Of Software Releases - Only Practical Approach For Large Replacement and
Consolidation Projects
19Project Cost Considerations
- SAP XI Platform Software
- Third Party Adapter Software
- Hardware
- Consulting Services
- Project Approach
20SAP XI Platform Software Costs
- There Are Three Primary Components That Make Up
The Cost Of The SAP XI Platform - SAP XI Software
- Database Software
- Third Party Infrastructure Tools
- Alert Software
- Job Scheduling
- Archiving
- Etc
- Interesting Point About Our Project. The
Software Had Already Been Purchased In A Bundle
Of Functionality Years Earlier - SAP Had Since Moved From An Instance Based
License To A Volume Based License. - The Volume Based License Presented Us With
Several Challenges - How To Measure Volume?
- What Volume Level Would We Need Licensed If We
Fully Implemented XI?
21Third Party Adapter Requirement Costs
- If you are implementing EDI you will need a third
party adapter. - If you require complex content conversion you
will need a third party adapter. - Understand and identify the initial cost and
maintenance cost associated with them when
developing your project costs.
22Hardware Costs
- Hardware Components
- Servers
- Storage
- Network
- Drivers Of Hardware Costs
- Landscape Design
- Number Of Environments Support SAP Promote and
Support Structure - Production Volume Requirements
- Testing Requirements
- Infrastructure Techniques
- Volume / Stress Testing
- Tuning
23Consulting Services Cost
- Cost Of Third Party Assistance
- Consulting Services Cost Vary Drastically By
Provider And So Can The Quality Of The Services
Provided - Drivers Of Consulting Services Costs
- Project Scope
- What Constitutes The Boundaries Of Your Scope Of
Project? - Project Timeline
- How Long Will The Project Take?
- Balanced Pace Business Capacity, Technical
Capacity, Testing Capacity
24Project Approach Impact On Cost
- Each Of The Approaches Has A Cost Associated With
Them. Typically Each Phase Is Aimed At Reducing
Overall Project Risk - Initial Project Assessment
- Many Consulting Firms Will Do This For Free. Get
More Than One And Compare Findings - A Workable Assessment Will Still Typically
Require A Paid In Depth Assessment - Prototype Environment
- Get Your Feet Wet Learn The Tool Identify Early
Areas Of Concern And Monitor As Project
Progresses - Identify Project Specific Cost Drivers That Will
Impact Your Specific Project - Proof Of Concepts Phase
- Test The Functionality Required To Completely
Implement Your Vision - Find The Hidden Challenges / Costs Early
- Overall Implementation
- Internal VS External Resources
- Timeline / Pace
- Other External Drivers That Impact Overall
Implementation Cost - R/3 Upgrades, Existing Infrastructure Upgrades
Required, Unplanned Business Events
25Project Cost Savings
- Cost Savings
- Maintenance Cost Of Existing Software
- Reduction Of Redundant Hardware Support Costs
- Cost Of Skill Sets To Support Existing
Functionality - Maintenance and Support Cost Of Custom Designed
Infrastructure Functionality - Cost Avoidance
- Cost Of Required Infrastructure Software Upgrades
- Cost Of Required or Need Infrastructure
Enhancements
26Maintenance Cost Of Existing Software
- This Cost Savings Will Vary Depending On Your
Type and Scope Of Project - Each Infrastructure Tool Has A Software Support
Cost Associated With It. Therefore Each Tool You
Retire Represents A Potential Maintenance Cost
Savings. - Consideration Some Maintenance Contracts On
Infrastructure Tools Have Different Levels Of
Support, The Higher Levels Can Have Significant
Yearly Costs Associated With Them. - In Large Projects It Will Take Time To Phase Out
The Use Of Certain Tools. So Make Sure Your ROI
Calculations Consider This.
27Reduction Of Redundant Hardware Support Costs
- This Cost Savings Is Primarily Driven By A
Reduction In Hardware Required To Support
Multiple Infrastructure Tools - There Is A Monthly Support Cost Associated With
Any Server Hosted Within A Data Center - On Tool Consolidations Projects, A Significant
Number Of Physical Servers Can Be Eliminated And
Their Associated Support Costs - Hardware Upgrades To Aging Tools Servers Can Also
Be Avoided
28Cost Of Skill Sets To Support Existing
Functionality
- Each Infrastructure Existing Infrastructure Tool
Requires A Team Of Different Software Specific
Skills To Develop, Administer, and Monitor. - Consolidation Of Tools Can Significantly Reduce
The Number Of Resource Skills Required To Support
An Infrastructure - Reduce The Number Of Resource Required Overall To
Support The Infrastructure - This Particular Area Obviously Will Be Subject To
Political Debate Because Of Its Potential Impact
On Head Count. - We Found In Our Project That Our DataStage TX
Resources Easily Adapted Their Mapping Skills To
The XI Skills Required, And Became Productive
Quickly.
29Maintenance and Support Cost Of Custom Designed
Infrastructure Functionality
- Many Existing Integration Infrastructures Are
Developed From Tools Introduced To The Market
Over The Last Ten Years. - As a Result Many Existing Integration
Infrastructures Rely on Custom Developed
Components To Meet Required Infrastructure
Functionality. - This Custom Functionality Can Be Quite Complex
And Require Expert Level Skills In Multiple
Infrastructure Software Products To Effectively
Maintain. - These Infrastructure Components Are Unique Thus
When An Issue Occurs Either You Will Require
Knowledgeable In-house Resources Or You Will Need
Expert Level External Help. - The Cost Of Supporting This Existing Custom
Functionality Is Usually Significant.
30Cost Avoidance Of Required Infrastructure
Software Upgrades
- Many Existing Infrastructure Tools Require
Upgrades To Keep The Product In Support - If Your Infrastructure Is Made Up Of Many
Different Tools. Chances Are One Of Them Is
Going To Be Driving An Infrastructure Upgrade - Some Tool Upgrades Provide Very Little Challenge
From An Effort And Staffing Perspective, Some Are
Significant. - Understand The Impact Of And Drivers Of Future
Tool Upgrades, They Can Be A Driver Of Cost
Savings From An Avoidance Perspective. - When Upgrading A Custom Developed Infrastructure
Made From Different Software Tools, Projecting
The Impact / Required Scope / Cost Of An Upgrade
Can Be A Challenging Undertaking.
31Cost Avoidance Of Required or Need Infrastructure
Enhancements
- If You Have Developed Your Integration
Infrastructure From Off The Shelf Tools and
Custom Designed Components. You Will Find
Yourself Continually Adapting That
Infrastructures Capabilities To Keep Up With
Changing Business Needs and Changing Technology
Needs. - As You Continue To Plan Ahead For Future Business
Requirements, You Will Find The Need To Scope
Design Changes And Improvement Projects. - Most Of Our Future Scoped Functionality Existed
In SAP XI Out Of The Box - In Addition Because It Is An SAP Industry
Supplied Tool As Future Functionality Is
Required, It Will Most Likely Be Added As The
Tool Matures.
32Project Controls and Project Scope Definition
- Scope In Infrastructure Tools Early
- Understand Your Interface Volumes
- Understand Your Adapter Requirements
- Dont Underestimated Content Conversion
- Assessing The Impact Of Environment Copy Backs
- Try Not To Get Sucked Into The Number Of SLDs
Required Vortex
33Scope In Infrastructure Tools Early
- Leave some room in your plan for development of
simple infrastructure tools. - These tools will help you implement better more
maintainable designs as you project progresses. - Some will be required from a technical
perspective. Some will significantly simplify
other activities later. - Dont cut scope on this in early phases of your
project.
34Understand Your Interface Volumes
- Specifically what impact does XML have on your
volume estimates. - Dont get to integration testing and figure out
that your design brings XI to its knees! - Study your interface volumes. Specifically at
production and initial conversion loading
conditions. - Make sure your design accounts for these volumes
and can handle the load effectively. - Specifically do the math on content conversion
for each interface. - Flat file to XML conversion.
- Calculate a conversion factor.
- Multiply production volume estimates by the
conversion fact. - The troublesome interfaces will become apparent
very quickly. - Reworking an interface design can be a costly
mistake and can significantly impact project
timelines.
35Understand Your Adapter Requirements
- What adapters do you need to accomplish your
goals? - Understand that your are not going to implement
EDI in XI without the help of a third party
adapter. - Understand which adapters you will require and
their delivered functionality and functional
gaps. - Some adapters support multiple capabilities such
as FTP and SFTP by changing configuration
settings. Dont buy custom adapters you already
have. - Some standard adapters will require custom
adjustments via custom Java modules. Understand
and scope these custom requirements early in your
project.
36Dont Under Estimated Content Conversion
- Content conversion in SAP XI can prove to be one
of the most difficult tasks to overcome in an
implementation. - Content conversion is somewhat cryptic to
configure and effort balloons as content
structure complexity increases. - We underestimated this effort the most in our
project implementation. - The more complex content conversion requirements
we had forced us to eventually rework a number of
our interface and implement SAP Conversion Agent
by Itemfield.
37Assessing The Impact Of Environment Copy Backs
- In the initial phases of building out a landscape
this is not an important consideration. - Once a landscape is built however you will most
likely not want to copy back XI. This is counter
to most other SAP applications best practices. - Each SAP XI instance has unique ID configuration
for the environment. Copy backs will erase this
unique configuration. - You will not need to copy back your SAP XI
landscape so dont spend a lot of time planning
it or debating it. It will only cause you issues.
38Try Not To Get Sucked Into The Number Of SLDs
Required Vortex
- There is no right answer here. You will find
documentation that states there should only be
one. You will find documentation that says there
could be more than one. - When a consultant tells you it depends on your
project he is right. - Our experience is that less is easier to manage.
- Set a direction and move on.
39Technical Lessons Learned
- Packet Processing Not Supported By IDOC Adapter
- User Defined Java Functions
- Custom Cross Reference Functionality
- Required Setup To Use ABAP Maps
- Message Size After Content Conversion
- Large Message Processing
- Message Pointers
- ABAP Mapping
- JMS Adapter
- Conversion Agent By Itemfield
- Adapter Tracing
40Packet Processing Not Supported By IDOC Adapter
- On the surface this does not appear to be an
issue or a concern. - Each outbound packet from SAP is split into
individual messages in XI. - However this has a negative effects on downstream
applications like Gentran. When outbound EDI
data is processed by Gentran it is typically
grouped by trading partner. This caused Gentran
to generate significantly more EDI envelopes than
normal. - It also impacted other downstream applications by
making them process lots of individual messages
instead of groups of messages. This created
performance issues for certain applications. - Only way to process IDOCs as a group was to
process using a collection BPM.
41User Defined Java Functions
- Writing Custom Code Inside A GUI Map Is Sometimes
A Good Thing - We used user defined JAVA functions in the
following way. - We identified and created user defined functions
that replicated all existing DataStage TX mapping
functions not supported by XI. - When we identified that a particular mapping
requirement was creating specific difficult
challenges for GUI mapping techniques we would
build the required functionality in a user
defined JAVA funciton. - One technical challenge to user defined JAVA
function was that they are map specific. If you
want to reuse a function you must copy it from
another map. - In general our functions required 20 lines of
code or less but significantly simplified our map
conversions and mapping rules.
42Custom Cross Reference Functionality
- SAP provides GUI mapping rules that allow you
convert mapping data via a cross reference. The
issue is the cross reference data is map specific
and can not be reused. - We had many instances where the same cross
reference data was required across multiple maps. - We create with minimal development effort a
custom cross reference solution that utilized a
custom ABAP table, a custom function module and a
custom user defined JAVA function. - The user defined JAVA function had to be copied
from map to map but the logic and cross reference
data was stored in the function module and ABAP
table. Thus allowing us to reference the same
cross reference data across multiple maps.
43Required Setup To Use ABAP Maps
- The exchange profile needs to be modified before
mapping can be done on the ABAP stack. - Modify the exchange profile setting
com.sap.aii.repository.mapping.additionaltypes.
- We added the entry R3_ABAPABAP-Class
MapR3_XSLTABAP-XSL. - This allows both ABAP class maps and XSLT maps
via the ABAP kernel.
44Message Size After Content Conversion
- Make sure you consider the size of you message
after it is converted to XML when designing your
interfaces. - A inbound 5mb flat file can grow to a 50mb xml
document. - An interface that appears to be well within
processing limits quickly becomes too big.
45Large Message Processing
- Why Does XI Not Handle Large Messages Well?
- Netweavers dual stack design (ABAP Java)
results in a bottleneck whenever large data sets
move from processing on one stack to another.
The standard way for the two stacks to
communicate is via RFC.
46Large Message Processing
- The following diagram shows the communication
between the ABAP and Java stacks during normal
message processing.
47Large Message Processing
- Message Pointers
- Lillys existing interfaces were enormous by XI
standards (gt500MB). - These large files usually contained full
refreshes of the data due to technical
constraints on the receiving, non-SAP system. - XIs architecture is not structured to handle
large amounts of data. - The key to processing large messages with XI is
to minimize stack boundary traversal. - We were able to do this by saving the message as
a file and only passing a pointer to the data (ie
filename). It was the job of the processing
agent to delete the file after it was confirmed
that it was sent to the receiver.
48Large Message Processing
- ABAP Mapping
- Some messages were brought in via the J2EE
Adapter Engine, but not converted to XML. This
unconventional design decision was made because
the conversion to XML required added processing
and memory requirements that caused message
processing to take too long. We decided to pass
the data directly to the map unconverted. - In an effort to further streamline message
processing and in addition to the removal of XML
conversion overhead, we also decided to do away
with some of the stack traversal overhead. We
accomplished this by implementing our mapping
requirements with ABAP.
49Large Message Processing
- ABAP Mapping continued
- Doing the mapping in ABAP was doubly advantageous
because message mapping and XSL mapping requires
that the data be in XML format. Since our data
was still in flat file format, our only options
were Java mapping and ABAP mapping. With the
added requirement of reduced stack traversal, our
only remaining option was ABAP. - Our data was in a structured text format. ABAP
turned out to be a very good language for this
type of data mapping. Our large team of
competent ABAP developers made short work of the
ABAP maps.
50JMS Adapter
- The JMS configuration is not out-of-the-box! JMS
drivers must first be installed.including - The correct JAR files in order for the JMS
adapter to function correctly, which is one of
the challenges we faced with the use of JMS. - Performance tuning for XI to operate effectively
that impacted JMS. SAP provides a document that
outlines performance tuning requirements in XI
version 3.0 (see appendix for information).
51JMS Adapter
- Secondly, during integration testing, we
discovered an issue regarding a message of 30mb
in size - Issue The following error occurred when
attempting to connect to the JMS adapter
"Delivery of the message to the application using
connection AFW failed, due to MQJMS1016 an
internal error has occurred. Please contact your
system administrator. Detail java.nio.BufferOverf
lowException. - Resolution The Java Development Kit (JDK) had to
be upgraded to version 1.4.2_08 or higher (or if
using version 1.3.1, upgrade to JDK 1.3.1_16 or
higher). We upgraded our server version to
1.4.2_12 in order to process messages gt25mb (see
appendix for additional information)
52SAP Conversion Agent by Itemfield
- At Eli Lilly, we implemented the SAP Conversion
Agent by Itemfield as an adapter module to help
deal with more complex and unstructured messages! - Issue identified that some special characters
(i.e. German Umlaut) were not displaying
correctly (showing as ??), even though the
character set was configured as Western
ISO-8859-1.
53SAP Conversion Agent by Itemfield
- Resolution CM_TransformModule.sda module that
related to Content Master (as it was known then)
service pack 15 (SP15) was not working to provide
adequate translation of special characters
following data conversion. The
CM_TransformModule.sda of SP17 was deployed in
each environment which eventually fixed the
problem. For information, Eli Lilly was using XI
SP15 and Conversion Agent SP15 at the time this
issue occurred (see appendix)
54SAP Conversion Agent by Itemfield
- Issue We identified that several messages
by-passed the SAP Conversion Agent. Thus, the
payload was not being converted into an XML
format and XI was receiving a flat file instead
of an XML file. - Resolution The fix for this was based on an
existing OSS note (930598). This note was not
only pertained to Conversion agent but it was
more generally specified for any module that was
attached to the adapter.
55Adapter Tracing
- Each Java Adapter Can Be Traced At A Technical
Level. - Adapter Tracing Is Activated By Using The J2EE
Administrator Tool To Change Trace Levels. - Warning At Higher Adapter Trace Levels The
Adapter Polling Frequency Can Really Impact Trace
File Growth. - Make Sure You Polling Frequency Are Reduced
- Or Make Sure You Only Activate Traces For Short
Periods Of Time
56Key Learnings
- Calculating A Cost Savings On An SAP XI
Implementation Will Depend On Your Project Goals,
Your Current Infrastructure, and Your Specific
Infrastructure Challenges. - Prototyping Environments and Proof Of Concept
Implementations Will Help You Control Overall
Project Scope And Requirements By Identifying
Areas In The Project That Will Require Specific
Consideration Up Front - Dont Underestimate Content Conversion
- Scope In Simple Infrastructure Tools That Will
Simplify Long Term Maintenance And Reduce
Interface Development Time. - SAP XI Can Handle Large Sized Message Interfaces.
You Just Have To Handle Them Differently.
570707