Title: Selling an Idea or a Product
1The SCL Protocol Time for Something New? DELAY
ANALYSIS COST EFFECTIVE PROGRAMMING David
Dale Vice President- Warner Construction
Consultants Inc.
2The SCL Protocol
Object Purpose (to provide guidance) Does not
provide a practical solution Problems with delay
disputes during a project Retrospective Delay
Analysis Something New Required? AACE
International Initiatives
3Something New
- Theoretical Impact Analysis Causes Scepticism
- Delay Analysis Technique Depends on Circumstances
- Analysis Must be Based upon Facts (as-built
critical delay) - Use of Contemporaneous Records
- CPM Impacting Used to Complement Facts
(Concurrent Culpable Delay) - Window/Snapshot Most Cost Effective
4- As-Built Critical Path
- Must be meaningful and credible
- Insert e.g. of As Built CP
5- Windows/Snapshot
- Insert e.g.
6Planning Control/Procedures
- If Project is Administered and Planned Well -
Usually no Dispute. - SCL protocol gives good guiadance on Best
Practice - Contractors fearful of implementing Best
Practice due to high cost. - Need Flexible Low Cost System/Procedure
- Follow the Conditions of Contract Requirements
- Dedicated initial Set Up Required
7Project Controls Director
Project Manager Review
Planner
Planner
Site Engineers, QS, Clerks
Site Engineers, QS, Clerks
Site Engineers, QS, Clerks
Site Engineers, QS, Clerks
Site Engineers, QS, Clerks
8Programme Approval Revisions
- Normal requirement to produce within days of
Contract award - Describes Ending as well as Beginning
- Reflect original intention at Contract award
- Involve Client in production
- Save as baseline
- Revisions/updates must be saved as separate files
9Progress Updates
- Enter progress against each activity on the
programme - Any delays should also be entered and the
programme re-analysed - Time analysis results may indicate critical delay
to completion date - Internal/External Progress Reporting
10Internal Progress Report Part I
- Internal Management Report Progress Review
Project XYZ PROJECT Project No.
11Internal Progress Report Part II
- Internal Management Report Progress Review
Project XYZ PROJECT Project No
Engineering The original scope is complete with
all drawings and calculations being approved.
D.O. are now working to clear additional
scope/change areas on hold or amended by the
Engineer/Employer. Fabrication A significant
increase in production has been promised with
delivery of steelwork now scheduled to be
complete during next week. The two later
deliveries incorporating variations will be in
accordance with the procurement priority list
issued this week. Site Lack of steelwork is
delaying site progress and continues to restrict
our ability to mitigate the current delay. The
second recovery programme that will incorporate
all additional work and delays caused by the
Employer is now ready for review and pricing. It
is hoped that this programme along with the
proposed recovery price will be ready for issue
to the Employer at next Tuesdays site meeting.
12Man Power Allocation
13Progress Review Questionnaire
14Overall Progress Curve
15Man Power Histogram
Planned Man Power
16Man Power Histogram
Planned v Actual Man Power
17- Cost Effective Project Controls
- Dont Need an army of Planning Engineer speaking
planning jargon that no one understands. - Three/Four or more Projects could be successfully
managed by one good planner using the correct
procedures. - Coordinated site visits and attending key
meetings. - Use of Questionnaires
- Progress Reporting Based on Standard Format
18Keeping Records
It is a basic requirement for any time/delay
analysis to be able to understand what work was
carried out and when it was carried out
- A. NoticesB. Drawing Approvals
- C. RFIs/PMIsD. Labour/Plant Allocation
- E. Variations
- F. Float Usage
19Key Performance Indicators
- Early warning of potential problems
- e.g. Variations
Project Month 4
Project Month 5
Define project revenue reporting rules to
identify risk. Consider only allowing pending
and approved variations to be included in project
forecast recovery figures.
20Benefits of Maintaining Good Planning Controls
- Perform Labour Productivity Analysis
- Accurate Forecasting
- Early Indication of Potential Problems
- Key Performance Indicators
- Prepare / Evaluate Claims more effectively
- Avoids Disputes
21