Title: Development Schedule


1
Development Schedule
  • 1st Sprint 3.5 weeks May 28(Wed) - June 20(Fri)
  • June 20(Fri) Demo and Install the tool
  • Release documents outline
  • June 23(Mon) Review 1st Sprint and define
    features for 2nd Sprint
  • 2nd Sprint 3.5 weeks June 23(Mon) - July
    16(Wed)
  • July 16(Wed) Demo and update the tool
  • July 22(Mon) Review 2nd Sprint and define
    features for 3rd Sprint
  • 3rd Sprint 2 weeks July 17(Thu) - July 28(Mon)
  • July 29(Tue) Acceptance Test
  • Release documents
  • Aug 1 (Fri) Release EDA Tool
  • Documents
  • - Test specification
  • - Users Manual
  • - Maintenance Manual

2
Feature set for each Sprint (1/2)
  • Key features for 1st Sprint (675hrs)
  • Create/Modify/Delete QAS, AS data
  • Create/Delete Analysis Project
  • Visualize utility curve, cost/benefit graph
  • Dynamic update
  • CBAM Steps
  • Key features for 2nd Sprint (641hrs)
  • Import/Export QAS, AS, Analysis result to/from
    Excel file
  • Analysis Data Validation / Data field protection
  • CBAM Sensitivity Analysis
  • Multiple Analysis Run
  • Data sharing among Analysis Project

3
Feature set for each Sprint (2/2)
  • Key features for 3rd Sprint (724hrs)
  • One level Undo
  • CBAM probability table
  • Sensitivity Analysis overlay data
  • Import/Export QAS, AS, Analysis result to/from
    XML file
  • Analysis Report
  • Print QAS/AS/Analysis Report
  • Help function
  • Support AHP/Conjoint Analysis/QRAM
  • Note
  • -Over budgeted by 500hrs
  • -Need Prioritization