Title: FY09 Tactical Plans for Information Systems
1FY09 Tactical Plans forInformation Systems
- Igor Mandrichenko
- 9/24/2008
2FY09 Tactical Plan for Information Systems
- Relevant Strategic Plan(s)
- Central Services Strategic Plan
- Databases and Applications Strategic Plan
- Tactical Plan Leader Matt Arena
- Organizational Unit home LSCS/DBI
3FY09 Tactical Plan Strategies and Goals
- Tactical Plan Strategies
- In cooperation with other groups and departments
of Computing Division, participate in development
and support of applications needed to improve the
efficiency of the Division while avoiding
duplication of functionality provided by other
parts of the Laboratory - Identify business processes bottlenecks and apply
focused effort to eliminate them - Implement ITIL practices into all stages of our
project lifecycle - Develop expertise in a set of software tools that
help end users with little or no programming
skills create simple applications. Provide
technical and consulting help to the users who
are developing their application using the tool
set. - Consistently apply common development approaches
and software tools to increase efficiency of
application development and support
4FY09 Tactical Plan Strategies and Goals
- Tactical Plan Goals
- Provide the Computing Division and the Laboratory
with automated procedures to reduce paperwork and
increase functionality though automated workflow - Provide application developers with methods
access infrastructure databases - Develop and support administrative applications
that support the scientific community - Introduce SharePoint or similar framework as
Labs information sharing and communication
platform.
5FY09 Tactical Plan Objectives
- Improvements of technology base
- Search for workflow application development
framework to replace AlphaFlow - Introduce SharePoint (or similar technology) as
an information exchange framework - Search and implement more efficient technologies
for web applications development
6FY09 Tactical Plan Objectives (continued)
- Provide support for Labwide business processes
- Assist in the effort to transition to ITIL and
ISO 20000 standards. Participate in
implementation of - Service Desk
- Asset Management
- Configuration Management Database
- Change Management
- Support the ESH Sections database applications
- Support the MISCOMP infrastructure database
applications - Support the efforts to automate Account
Management - Participate and facilitate development and
support of workflow applications such as eTravel,
New Hire.
7FY09 Tactical Plan Objectives (continued)
- Provide support for the Laboratorys scientific
activities - Provide support to maintain DocDB in its current
state - Search for alternative document/content
management systems that scale to the Laboratorys
and broader scientific user communitys
requirements. - Provide support and development for InDiCo
developed at CERN - Provide support and maintenance for the SPMS
conference management software.
8FY09 Tactical Plan Objectives (continued)
- Provide support for CDs existing infrastructure
database applications. - Re-design the CD Effort Reporting system to
interface with the Labs OTL system (FTL) - Migrate the Budget Input database to Oracle and
integrate it with the existing infrastructure
data.
9FY09 Tactical Plan Objectives (continued)
- Develop new applications and integrate existing
applications with Microsoft Office SharePoint
platform. - Train developers in SharePoint framework
- Provide interfaces for SharePoint portals to
access existing applications and databases. - Develop new applications in the SharePoint
framework. - Participate in design and development of Lab
Intranet Portal, project and personal pages - Improve the efficiency of the Divisions internal
business processes - Have project leaders complete ITIL training.
10FY09 Tactical Plan Past Action Items
- Workflow Aplications
- We had several meetings with potential
stakeholders for workflow projects - We identified several classes of workflow
applications which are needed by CD and the Lab - We developed strategic approach for workflow
management application development based on the
following principles - Develop expertise in one or more existing
workflow management software packages - Actively participate in development of complex
applications - Provide expert help and limited development
resources to end users who will be developing
simple applications mostly themselves
11Project Activity Microsoft Office SharePoint
Implementation
- Goals Related to this Activity from Tactical
Plan - 1. Increase efficiency and facilitate
collaboration and communication in the Lab as an
organization - New, High
- 2. Implement SharePoint as IT application
framework that supports Lab-wide information
management architecture - New, High
- 3. Improve efficiency of IT application
development, deployment and support and decrease
effort needed to deploy web-based applications - New, Medium
- 4. Empower and enable application development by
end users - New, Medium
- Key Milestones
- Implement SharePoint
- Design CD and Lab intranet portals
- Produce MyPage development guidelines and
documentation - Integrate several existing applications with
SharePoint - http//sharepoint.fnal.gov/cdprojects/SP_Project/d
efault.aspx - Metrics, if any applicable (may be none for some
Project Activities) - Issues and Risks (specific to this activity,
includes allocation impact) - Need buy-in from users community, new technology,
lack of pre-existing expertise
12Project Activity ITIL Implementation
- Goals Related to this Activity from Tactical
Plan - 1. Work with consultants on ITIL implementation
- New, High
- Key Milestones
- Implement Asset Management DB
- Implement or deploy Configuration Management DB
- Implement or deploy Change Management System
- Implement or deploy Service Desk
- Issues and Risks (specific to this activity,
includes allocation impact) - ITIL is not so familiar to our staff, and its
implementation will require adoption of different
practices and standards
13Project Activity Account Management
- Goals Related to this Activity from Tactical
Plan - 1. Design and develop comprehensive account
management system following ITIL standards - New, High
- Key Metrics
- Milestones, if any applicable (may be none for
some Service Activities) - Produce project scope document
- Collect requirements
- Design and develop account management system
- Issues and Risks (specific to this activity,
includes allocation impact) - Development must be done in close cooperation
with other organizations - Priorities and resource allocations must be in
sync
14Project Activity Workflow Applications
- Goals Related to this Activity from Tactical
Plan - 1. Search and adopt one or more Workflow
Management software tools - New, High
- 2. Participate in development and support of new
workflow applications, e.g. - eTravel
- New Hire
- New, High
- 3. If necessary, migrate some existing
applications to new framework(s) - New, High
- Key Milestones
- Find and adopt Workflow Management tools
- Develop expertise in the tools
- Metrics, if any applicable (may be none for some
Project Activities) - Issues and Risks (specific to this activity,
includes allocation impact) - Set of software tools should cover wide range of
relevant use cases - The tools must well integrate into IT
infrastructure (e.g. SharePoint)
15Project Activity Effort Reporting and Budget
Input Conversion
- Goals Related to this Activity from Tactical
Plan - 1. Integration of Effort Reporting system with
Fermilabs Time and Leave (FTL) system. - New, High
- 2. Continue support of Effort Reporting and
Budget Input processes - Existing, High
- Key Milestones
- Re-design of the database to meet the
requirements of integration with Fermilabs Time
and Leave (FTL) system. - Complete migration of the applications to Oracle
- Issues and Risks (specific to this activity,
includes allocation impact) - Conversion of Access-based application to Oracle
is tedious and non-trivial task - All project activities have to be closely
coordinated with financials group which works
according to well-defined and inflexible time
table
16Service Activity ESH Applications
- Goals Related to this Activity from Tactical
Plan - 1. Continue development and support of ESH
applications - Existing, Medium
- 2. Migrate applications to strong authentication
methods (KCA, LDAP) - Existing, High
- Key Metrics
- Application downtime
- Milestones, if any applicable (may be none for
some Service Activities) - Implementation of KCA or LDAP authentication
mechanisms - Issues and Risks (specific to this activity,
includes allocation impact) - Strong authentication methods have to be accepted
by users
17Service Activity MISCOMP Applications
- Goals Related to this Activity from Tactical
Plan - 1. Continue development and support of MISCOMP
applications - Existing, Medium
- 2. Implement ITIL structure components based on
MISCOMP, e.g. Asset Management DB, etc. - New, High
- 3. Implement strong authentication methods
- Existing, High
- Key Metrics
- Application downtime
- Milestones, if any applicable (may be none for
some Service Activities) - Implement Asset Management DB
- Implement strong authentication methods for
MISCOMP applications - Issues and Risks (specific to this activity,
includes allocation impact) - Support and users acceptance of strong
authentication infrastructure
18Service Activity DocDB
- Goals Related to this Activity from Tactical
Plan - 1. Continue support of DocDB software
- Existing, Medium
- Key Metrics
- Promptness of user support, bug fixes
- Issues and Risks (specific to this activity,
includes allocation impact) - Issue is that we are not authors of DocDB, and we
are not really familiar with the code
19Service Activity Content Management System
- Goals Related to this Activity from Tactical
Plan - 1. Find a replacement for Plone as a CMS
- New, High
- Key Metrics
- Milestones, if any applicable (may be none for
some Service Activities) - Search and propose CMS which would satisfy CD and
Lab needs - SharePoint seems to be very good candidate
- Issues and Risks (specific to this activity,
includes allocation impact) - CMS needs to integrate well into Lab and CD IT
infrastructure
20Service Activity InDiCo
- Goals Related to this Activity from Tactical
Plan - 1. Continue support of InDiCo in collaboration
with CERN - Existing, Medium
- Key Metrics
- Application downtimes, promptness of responses to
user requests - Issues and Risks (specific to this activity,
includes allocation impact) - Any bug fixes or new features have to be accepted
by CERN
21Service Activity SPMS
- Goals Related to this Activity from Tactical
Plan - 1. Continue support of SPMS
- Existing, Medium
- Key Metrics
- Application downtime, promptness of responses to
user requests
22Service Activity insert name(1 slide per
service activity in the Tactical Plan)
- Brief oral description to provide context.
- Goals Related to this Activity from Tactical
Plan - 1. Goal 1
- Identify if new or existing goal, and relative
priority. Indicate status or priority in separate
color/fonts. - 2. Goal 2
- Identify if new or existing goal, and relative
priority. Indicate status or priority in separate
color/fonts. - 3. Goal 3
- Identify if new or existing goal, and relative
priority. Indicate status or priority in separate
color/fonts.
- Key Metrics
- List metrics here
- What is it? (tickets clear per month, service
uptime, service request response time,) - Goal level planned vs actual. Impact high
or low, felt by whom, if level not met - URL of online presentation of metrics
- Milestones, if any applicable (may be none for
some Service Activities) - Issues and Risks (specific to this activity,
includes allocation impact) - List Issues and Risks
23Project Activity insert name(1 slide per
project activity in the Tactical Plan)
- Brief oral description to provide context.
- Goals Related to this Activity from Tactical
Plan - 1. Goal 1
- Identify if new or existing goal, and relative
priority. Indicate status or priority in separate
color/fonts. - 2. Goal 2
- Identify if new or existing goal, and relative
priority. Indicate status or priority in separate
color/fonts. - 3. Goal 3
- Identify if new or existing goal, and relative
priority. Indicate status or priority in separate
color/fonts.
- Key Milestones
- List key milestones and associated deliverables
here - What is it? When planned vs actual.
Impact high or low, felt by whom, if date not
met. - URL that shows project progress towards
milestones - Metrics, if any applicable (may be none for some
Project Activities) - Issues and Risks (specific to this activity,
includes allocation impact) - List Issues and Risks
24FY09 Resource Request, Preliminary Allocation
25Preliminary Allocation (explanation)
- ITIL Implementation
- Conferences, Work Shops, etc. 32000
- BMC Software Maintenance 53000
- Tel-Alert Annual Support 13552
- BMC ITSM Training 30000
- Workflow
- AgilePoint initial 85000
- Support 17000
- MISCOMP
- Decision One 36300
- Crystal Reports 21780
- Miscelleneous Software 44000
- Hardware replacement 25000
26Impact of Preliminary Allocation
27Template Guidance (not part of the presentation)
- Activity Activity Level 1 or lower explicitly
listed in Tactical Plan - Activities have been classified in Tactical Plans
as either being more Project-like or Service-like - Projects finite defined lifetime, defined
deliverable. Includes RD work. - A.k.a Upgrades,
- Services same operation or task repeatedly.
- A.k.a. Operations, Maintenance, Support,
- Whether an activity is a project or service
determines which format slide to use later. - Terminology
- Obligation Budget Allocated budget. This may
differ from the budget request. - YTD Obligations Fully incurred expenses. Does
not include RIPs, Req.s in CD, etc. - Current FY08 Forecast Estimate of all
obligations to be incurred by the end of FY08. - MS Equipment Operating. Operating includes
Travel, Material Purchases, Professional Services
(contractors), Maintenance (licenses), and Other. - RIP Requisitions in Progress