Title: MT' View 4092009 Thursday


1
MT. View 4-09-2009 Thursday
Spring melt down has evolved and site is starting
to dry out
Next two photo are to show signs of partial
greening of grass?
2
(No Transcript)
3
(No Transcript)
4
With air temps reaching into mid 50 F
rangegt made for a good day to apply caulking
around cafeteria windows
5
closer views of caulking operation
outside caferteria
6
On Drawing 8/A512 there is a detail of acoustical
diffusers that have been set in the auditorium
today this is a view of the western interior
elevation
7
main frame photo is a view of the east wall of
the auditorium sound diffuser panel have been
hung on 2x4 cleats using adhesive
8
main frame photo is to shows today progress on
librarians desk in room E117 detailed on
Drawings 8 thru 11/ A508
9
Trico continues to apply bamboo paneling around
HS lobby stairway
10
rubber flooring installation was completed in
Fitness room H220 today
11
corridor leading to fitness room has
been prepared to flooring installation
CCSM continues to add things like wall grills and
diffuser panels
12
QTZ flooring is being set in corridor H225
13
stock materials are being shifted out of the
north end section of the cafeteria so to allow
for QTZ flooring to be installed
14
parts of corridor H218 are in the process of
being clad with QTZ flooring
15
elevator floors are being prepared for
finish floor application
16
Johnson Jordan continues to terminate control
wires in MECH C205
17
Northeast Control has been programming Radiant
Heat loops in the elementary wing today an
example would be seen above ceiling grid on south
end of corridor E118
18
JCN electricians continue to run fire-alarm
wiring as seen inside Storage EM135
19
SAT grid has been set in corridor EM100 today
20
Painters are applying finish coats in
stairways like Stair S02
21
Painters are applying finish coats in Band room
C1114
22
Bathroom partition assembly in room E210 was also
part of todays work