Title: MT' View 4092009 Thursday
1MT. View 4-09-2009 Thursday
Spring melt down has evolved and site is starting
to dry out
Next two photo are to show signs of partial
greening of grass?
2(No Transcript)
3(No Transcript)
4With air temps reaching into mid 50 F
rangegt made for a good day to apply caulking
around cafeteria windows
5closer views of caulking operation
outside caferteria
6On Drawing 8/A512 there is a detail of acoustical
diffusers that have been set in the auditorium
today this is a view of the western interior
elevation
7main frame photo is a view of the east wall of
the auditorium sound diffuser panel have been
hung on 2x4 cleats using adhesive
8main frame photo is to shows today progress on
librarians desk in room E117 detailed on
Drawings 8 thru 11/ A508
9Trico continues to apply bamboo paneling around
HS lobby stairway
10rubber flooring installation was completed in
Fitness room H220 today
11corridor leading to fitness room has
been prepared to flooring installation
CCSM continues to add things like wall grills and
diffuser panels
12QTZ flooring is being set in corridor H225
13stock materials are being shifted out of the
north end section of the cafeteria so to allow
for QTZ flooring to be installed
14parts of corridor H218 are in the process of
being clad with QTZ flooring
15elevator floors are being prepared for
finish floor application
16Johnson Jordan continues to terminate control
wires in MECH C205
17Northeast Control has been programming Radiant
Heat loops in the elementary wing today an
example would be seen above ceiling grid on south
end of corridor E118
18JCN electricians continue to run fire-alarm
wiring as seen inside Storage EM135
19SAT grid has been set in corridor EM100 today
20Painters are applying finish coats in
stairways like Stair S02
21Painters are applying finish coats in Band room
C1114
22Bathroom partition assembly in room E210 was also
part of todays work