Title: Executive Summary 95 and98 Bond Construction Program
1Next Generation Middle School Prototype Hardy
Oak Site Electric Easement Alignment 2003 Bond
Program
Garrett J. Sullivan, Executive DirectorConstructi
on Management Engineering Department
July 11, 2005
2Hardy Oak MS Electric Utility Easement
- Six Options for the Hardy Oak MS Electric Utility
Service Easement have been formulated for
consideration after meeting with both HOAs. - Option 1 No Change to Current Electric Utility
Service Plan - Cost 0.00
- Option 2 Relocate Utility Poles (12 ft) Along
Remington Heights - Cost 12,000
- Option 3 Provide Underground Service Along
Remington Heights - Cost 40,975
- Option 4 Provide Overhead Service from Mesa
Vista (South) - Cost 25,500
- Option 5 Provide Overhead Service from Mesa
Vista (North) - Cost 17,500
- Option 6 Provide Underground Service from Mesa
Vista - Cost 35,955
3General Notes
- Note 1 Two of Six Utility Poles currently set
along Remington Heights/NEISD
Boundary are Temporary Only - Note 2 One Utility Pole will be required along
Mesa Vista however, per
discussion with CPS, Pole 50-B (45 ft high)
can be replaced with a 50 ft pole with
no additional utility poles added
along Mesa Vista/NEISD Utility Easement - Note 3 Current construction contract includes
150 ft of underground electric
utility service it can realigned in any
direction from transformer - Note 4 Underground trenching costs estimated at
61.50 / linear foot - Note 5 Clearing, Tree Trimming and removal
costs are construction estimates
CPS will direct final clearing based on
alignment selected - Note 6 NEISD will grant CPS Easement based on
Option Selected
4CPS Note on All 3 PlatsMesa Vista / Remington
Heights / NEISD
- The City of San Antonio as part of its electric
and gas system (City - Public Service Board) is hereby dedicated the
easements and - rights-of-way for electric and gas distribution
and service facilities - in the area designated on this plat as "Electric
Easement," "Gas - Easement," "Anchor Easement," "Service Easement,"
"Overhang Easement," - "Utility Easement," and "Transformer Easement,"
for the purpose of - installing, constructing, reconstructing,
maintaining, removing, - inspecting, patrolling and ERECTING POLES,
hanging or burying wires, - cables, conduits, pipelines or transformers, each
with its necessary - appurtenances together with the right of ingress
and egress over - grantor's adjacent land, the right to relocate
said facilities within - said easement and right-of-way areas, and the
right to remove from said - lands all trees or parts thereof, or other
obstructions which endanger - or may interfere with the efficiency of said
lines or appurtenances - thereto. It is agreed and understood that no
buildings, concrete slabs, - or walls will be placed within said easement
area.
5Hardy Oak MS Electric Easement Alignment
Remington Heights Subdivision
Mesa Vista Subdivision
6Hardy Oak MS Electric Easement Alignment
Current Conditions
Remington Heights Subdivision
Mesa Vista Subdivision
7(No Transcript)
8Hardy Oak MS Electric Easement AlignmentNo
Change to Current Electric Utility Service Plan
OPTION 1
Cost 0.00
9Hardy Oak MS Electric Easement
AlignmentRelocate Utility Poles (12 ft) Along
Remington Heights
OPTION 2
Cost 12,000
10Hardy Oak MS Electric Easement
AlignmentProvide Underground Service Along
Remington Heights
OPTION 3
Cost 40,975
11Hardy Oak MS Electric Easement
AlignmentProvide Overhead Service from Mesa
Vista (South)
Possible CPS Tree Clearing ( 13 ft Wide) Along
NEISD Electric Easement
OPTION 4
Cost 25,500
Mandatory CPS Tree Clearing ( 13 ft Wide) Along
NEISD Electric Easement
12Hardy Oak MS Electric Easement
AlignmentProvide Overhead Service from Mesa
Vista (North)
Possible CPS Tree Clearing ( 13 ft Wide) Along
NEISD Electric Easement
OPTION 5
Cost 17,500
Mandatory CPS Tree Clearing ( 13 ft Wide) Along
NEISD Electric Easement
13Hardy Oak MS Electric Easement
AlignmentProvide Underground Service from Mesa
Vista
Possible CPS Tree Clearing ( 13 ft Wide) Along
NEISD Electric Easement
OPTION 6
Cost 35,955
Mandatory CPS Tree Clearing ( 13 ft Wide) Along
NEISD Electric Easement
14Summary Presentation Hardy Oak Middle School
Electric Utility Easement
Questions?
15Hardy Oak MS Electric Easement
AlignmentRelocate Utility Poles (12 ft) Along
Remington Heights
OPTION 2A
Cost 16,000