Executive Summary 95 and98 Bond Construction Program - PowerPoint PPT Presentation

1 / 15
About This Presentation
Title:

Executive Summary 95 and98 Bond Construction Program

Description:

Note 1: Two of Six Utility Poles currently set along Remington ... Mesa Vista & part of Remington Heights. Hardy Oak MS Electric Easement Alignment ... – PowerPoint PPT presentation

Number of Views:53
Avg rating:3.0/5.0
Slides: 16
Provided by: Sull78
Category:

less

Transcript and Presenter's Notes

Title: Executive Summary 95 and98 Bond Construction Program


1
Next Generation Middle School Prototype Hardy
Oak Site Electric Easement Alignment 2003 Bond
Program
Garrett J. Sullivan, Executive DirectorConstructi
on Management Engineering Department
July 11, 2005
2
Hardy Oak MS Electric Utility Easement
  • Six Options for the Hardy Oak MS Electric Utility
    Service Easement have been formulated for
    consideration after meeting with both HOAs.
  • Option 1 No Change to Current Electric Utility
    Service Plan
  • Cost 0.00
  • Option 2 Relocate Utility Poles (12 ft) Along
    Remington Heights
  • Cost 12,000
  • Option 3 Provide Underground Service Along
    Remington Heights
  • Cost 40,975
  • Option 4 Provide Overhead Service from Mesa
    Vista (South)
  • Cost 25,500
  • Option 5 Provide Overhead Service from Mesa
    Vista (North)
  • Cost 17,500
  • Option 6 Provide Underground Service from Mesa
    Vista
  • Cost 35,955

3
General Notes
  • Note 1 Two of Six Utility Poles currently set
    along Remington Heights/NEISD
    Boundary are Temporary Only
  • Note 2 One Utility Pole will be required along
    Mesa Vista however, per
    discussion with CPS, Pole 50-B (45 ft high)
    can be replaced with a 50 ft pole with
    no additional utility poles added
    along Mesa Vista/NEISD Utility Easement
  • Note 3 Current construction contract includes
    150 ft of underground electric
    utility service it can realigned in any
    direction from transformer
  • Note 4 Underground trenching costs estimated at
    61.50 / linear foot
  • Note 5 Clearing, Tree Trimming and removal
    costs are construction estimates
    CPS will direct final clearing based on
    alignment selected
  • Note 6 NEISD will grant CPS Easement based on
    Option Selected

4
CPS Note on All 3 PlatsMesa Vista / Remington
Heights / NEISD
  • The City of San Antonio as part of its electric
    and gas system (City
  • Public Service Board) is hereby dedicated the
    easements and
  • rights-of-way for electric and gas distribution
    and service facilities
  • in the area designated on this plat as "Electric
    Easement," "Gas
  • Easement," "Anchor Easement," "Service Easement,"
    "Overhang Easement,"
  • "Utility Easement," and "Transformer Easement,"
    for the purpose of
  • installing, constructing, reconstructing,
    maintaining, removing,
  • inspecting, patrolling and ERECTING POLES,
    hanging or burying wires,
  • cables, conduits, pipelines or transformers, each
    with its necessary
  • appurtenances together with the right of ingress
    and egress over
  • grantor's adjacent land, the right to relocate
    said facilities within
  • said easement and right-of-way areas, and the
    right to remove from said
  • lands all trees or parts thereof, or other
    obstructions which endanger
  • or may interfere with the efficiency of said
    lines or appurtenances
  • thereto. It is agreed and understood that no
    buildings, concrete slabs,
  • or walls will be placed within said easement
    area.

5
Hardy Oak MS Electric Easement Alignment
Remington Heights Subdivision
Mesa Vista Subdivision
6
Hardy Oak MS Electric Easement Alignment
Current Conditions
Remington Heights Subdivision
Mesa Vista Subdivision
7
(No Transcript)
8
Hardy Oak MS Electric Easement AlignmentNo
Change to Current Electric Utility Service Plan
OPTION 1
Cost 0.00
9
Hardy Oak MS Electric Easement
AlignmentRelocate Utility Poles (12 ft) Along
Remington Heights
OPTION 2
Cost 12,000
10
Hardy Oak MS Electric Easement
AlignmentProvide Underground Service Along
Remington Heights
OPTION 3
Cost 40,975
11
Hardy Oak MS Electric Easement
AlignmentProvide Overhead Service from Mesa
Vista (South)
Possible CPS Tree Clearing ( 13 ft Wide) Along
NEISD Electric Easement
OPTION 4
Cost 25,500
Mandatory CPS Tree Clearing ( 13 ft Wide) Along
NEISD Electric Easement
12
Hardy Oak MS Electric Easement
AlignmentProvide Overhead Service from Mesa
Vista (North)
Possible CPS Tree Clearing ( 13 ft Wide) Along
NEISD Electric Easement
OPTION 5
Cost 17,500
Mandatory CPS Tree Clearing ( 13 ft Wide) Along
NEISD Electric Easement
13
Hardy Oak MS Electric Easement
AlignmentProvide Underground Service from Mesa
Vista
Possible CPS Tree Clearing ( 13 ft Wide) Along
NEISD Electric Easement
OPTION 6
Cost 35,955
Mandatory CPS Tree Clearing ( 13 ft Wide) Along
NEISD Electric Easement
14
Summary Presentation Hardy Oak Middle School
Electric Utility Easement
Questions?
15
Hardy Oak MS Electric Easement
AlignmentRelocate Utility Poles (12 ft) Along
Remington Heights
OPTION 2A
Cost 16,000
Write a Comment
User Comments (0)
About PowerShow.com