Description:

1998 Rite Aid commitment of $45,000. 2000 Phase-1 completion, Site deemed ... Rite-Aid money ... with Church, Rite-Aid, engineers, construction companies, ... – PowerPoint PPT presentation

Number of Views:45
Avg rating:3.0/5.0
Slides: 16
Provided by: f64
Category:
Tags: aid | avenue | gully | project | rite | waldo

less

Transcript and Presenter's Notes

Title: Waldo Avenue Gully Project


1
Waldo Avenue Gully Project
2
Project History Timeline
  • 1973 Waldo Avenue Landslide
  • 1996 Samoset Road Landslide
  • 1998 Rite Aid commitment of 45,000
  • 2000 Phase-1 completion, Site deemed attractive
    nuisance
  • 2000-2002 190,000 allocated to project from
    approved Ocean Properties TIF
  • 2002 203,000 MBNA grant applied for and denied
  • 2003 Project handed from church committee to
    church trustees
  • (I get involved)
  • 2003 Wendys helps out with other gully
  • 2004 Church measures interest and gets signatures
    at polls, latest estimates for 218,672, We ask
    council to put this in budget.
  • 2007 DEP permit renewed after expiring and for
    new plan
  • 2008 Bids received for spring work at under
    85,000

3
Waldo Avenue, Samoset Road landslides
4
Samoset Road landslide with 400' of horizontal
movement, April 1996
5
Landslide Risk Study
6
(No Transcript)
7
Wendy's helps stabilize other gully
8
Waldo Avenue Gully Project
2008 work area
Phase 1
1978 work
9
2008 work area
10
Church Involvement
  • Paid for Phase-1 with fundraising
  • Managed and invested Rite-Aid money
  • Stored materials at site despite attractive
    nuisance designation
  • Worked with City, Rite-Aid, engineers, and DEP
  • to produce and revise plans
  • Suggested smaller more affordable project
  • Cleared trees to reduce project costs

11
City Involvement
  • Undertook 1997 landslide study
  • Provided engineering for most activities
  • Managed and invested Rite-Aid money
  • Acquired rock from Denny's.
  • Worked with Church, Rite-Aid, engineers,
    construction companies, and DEP to produce and
    revise plans
  • Managed bidding processes estimates

12
Proponents
  • 2007-2008 City Council goals
  • DEP
  • Church Congregation
  • City
  • Neighbors
  • Waldo Ave users
  • Many voters as polled 2004
  • School at premises

13
Opponents
  • Time
  • Apathy
  • Weather

14
Desired result
  • City council to fund the remainder of the project
    for 26000 onetime expense.
  • This will end the project (and city involvement),
  • eliminate landslide risk in this area of Waldo
    Ave,
  • use large amount of materials stored at site,
  • provide space for pedestrians.

15
Project Scope Comparison
  • Trans-Alaska Pipeline
  • 8 years
  • 800 miles
  • 8 Billion
  • Waldo Avenue
  • 11 years
  • 150 feet (approx)
  • 26,000 needed