Title: EXPANDED PUBLIC WORKS PROGRAMME
1EPWP Progress Report Public Works Select
Committee 23 February 2005
2BACKGROUND
- Wide range of programmes established post-1994
(eg Zibambele, Zivuseni, W f W, Gundo Lashu) - Code of Good Practice for Special PWPs gazetted
in 2002 - Cabinet review of Special Poverty Relief
Allocation in 2003
3DESIGN OF THE EPWP
- Must allow for wide diversity of programmes
- Expand best-practice existing programmes
- To be sustainable, the EPWP must not be
make-work must be economically efficient - Emphasis on labour-intensive delivery of
cost-effective quality services - To avoid displacement, the EPWP should take place
in growing sectors of the economy
4WHAT IS AN EPWP PROJECT?
- Deliberate attempt by the public sector body to
use its expenditure on goods and services to
create additional work opportunities for the
unemployed - Workers usually employed on a temporary basis
(either by government, by contractors, or by
other non-governmental organisations), under EPWP
or learnership employment conditions - Workers provided with a combination of work
experience and training - Public sector body attempts to define and
facilitate exit strategies for workers when they
leave the programme more potential for exit
strategies in some sectors than others
5FUNDING
- No special fund for EPWP projects
- Emphasis is on changing the way in which normal
expenditure occurs - Reduces opportunity costs
- EPWP projects are identified and prioritised
using standard processes - Mainstreaming labour intensity
- Government bodies do not get involved in poverty
relief projects outside their core functional
areas, BUT - National programme with highly decentralised
implementation creates challenges for
implementation
6Progress to date
- Institutional Structures are in place
- DG Steering Committee
- Sector Coordinating Committees
- EPWP Unit in DPW
- Provincial Steering Committees
- Communication committee with GCIS
7- Training programmes
- Training programme for workers being implemented
with Dept of Labour funding - Training of engineers and contractors for labour
intensive construction, with Construction SETA
(CETA) - Training of officials to implement the EPWP, with
Local Government and Construction SETAs - Contractor learnership programme with CETA and
Provinces/ Municipalities - Learnership programmes for social sector
programmes with relevant SETAs are being
finalised - Venture learnerships for economic sector
8Infrastructure Sector
- Funding for projects is provided via
infrastructure grants directly to provinces and
municipalities - Projects are identified planned and implemented
by provinces and municipalities in accordance
with their Integrated Development Plans (IDPs) - Role of Department of Public Works
- Set the conditions on the grants use EPWP Tender
and Design Guidelines - Training programmes for workers, officials,
contractors, engineers, supervisors - Lobby infrastructure players to participate
(provinces, municipalities, water
authorities,Transnet, Housing, Eskom, etc) - Support to municipalities and provinces
- Monitor, evaluate and report
9Infrastructure Sector Provinces
Department of Public Works
National Treasury
Support to province
Provinces report indicators
Equitable Share
Province
Other Provincial Expenditure
Provincial Infrastructure Grant earmarked for the
EPWP through the Division of Revenue Act and
Audited by the Auditor General
Infrastructure Budget from Equitable Share
Provincial Infrastructure Budget
10Infrastructure Sector Municipalities
National Treasury
Public Works
Reporting
DPLG
Support to municipality
Rates, Levies and Taxes
Municipality
Other municipal Expenditure
Municipal Infrastructure Grant earmarked for the
EPWP through the Division of Revenue Act and
Audited by the Auditor General
Infrastructure Budget from Rates, levies and Taxes
Municipal Infrastructure Budget
11Significance of EPWP Guidelines
- Use of EPWP Guidelines is a requirement in the
Division of Revenue Act when MIG or PIG funds
are used - Provide guidance and contract conditions for
municipalities to tender EPWP projects - Endorsed by SALGA, NT and DBSA
- Makes the use of labour intensive methods a
contractual obligation of contractors - Auditor General audits provinces and
municipalities to assess compliance - If municipalities and provinces do not use the
Guidelines, EPWP targets will not be reached
12(No Transcript)
13Use of EPWP Guidelines
- Provinces
- Audit of all provinces done and AG is compiling
report - Compliance is poor
- Many provinces are doing some labour intensive
work already, but EPWP is about intensifying this
- Municipalities
- Audit not yet started
- Compliance expected to be poor for 2004-2005.
This was compounded by introduction of MIG with
new procedures
14Labour Intensive Contractor Learnership Programme
- 1 contractor 2 supervisors
- Initial plan was for 500 learnerships
- Due to interest from public bodies was increased
to 750 - Application to from CETA to DOL-NSF to increase
the number further to 1500 - Current commitment stands at 950 learnerships and
increasing, approx 30 provincial departments and
municipalities participating
15LI CONTRACTOR DEVELOPMENT PROGRAMME ROLES AND
RESPONSIBILITIES
IDT
CETA
DPW
DOL
Mentors for training providers
Trainers of trainers
Programme Management support
Community Facilitation Support
Training providers for learnerships
Province / municipality
Mentors for learners
Training projects
Training providers for workers
Learner contractor 2 learner supervisors
Access to credit
ABSA
Unemployed EPWP beneficiaries
16- The learnership takes approximately 2 years, each
learner contractor employs approx 10 workers - Learners graduate with NQF qualifications, able
to tender for LI projects issued in terms of EPWP
tender and design guidelines - First group of learners in Ethekwini has
completed their first project - Ethekwini, Coega, Klipfontein, Nkangala and
Mpumalanga learners are on site
17Significance of Labour Intensive Contractor
Learnership Programme
- Aims to develop 500 sustainable contractors and
1000 highly skilled site supervisors, specialised
in labour intensive construction - As part of their learnerships they will implement
1500 EPWP Projects to the value of R1.5 billion - During the implementation of these projects they
will employ approximately 100 000 people - These 1500 individuals will continue to execute a
large share of EPWP projects after they complete
their learnerships, by winning tenders
18Relationships between Provinces and Municipalities
- Varies from Province to Province
- In Limpopo for instance the province has taken
the lead to mobilise all municipalities to
participate in the EPWP Contractor learnership
programme - However in provinces with large municipalities or
Metros they act independently - The Provincial Departments of Local Government
play a role in implementing the MIG and can
therefore also put pressure on municipalities to
implement EPWP through the EPWP Guidelines
19Other infrastructure bodies
- Housing
- Transnet
- Water Boards
- Mining companies
20Training
- Officials
- LGW SETA is funding training of local government
officials, DPW also carried out training of
officials
- Consulting Engineers
- Have responded well, with professional bodies
supporting the initiative. More than 500
engineers have been trained to date
- Contractors
- Major contractors have not responded well and are
being engaged through professional bodies - Emerging contractors are eager but lack funds.
DOL-NSF-CETA being approached to assist
21Training for beneficiaries
- Training programmes in place and training
providers appointed
- First training programmes have been implemented
on some EPWP projects , challenge is to have them
implemented on all projects
22Infrastructure Five Year Targets
- Provinces
- Total Provincial Infrastructure Grant Approx R
20 billion - Targeted expenditure on EPWP projects Approx R
6.7 billion - Targeted EPWP Job Creation Approx 335 000
- Municipalities
- Municipal Infrastructure Grant Approx R 25
billion - Targeted expenditure on EPWP projects Approx R
8.3 billion - Targeted EPWP Job Creation Approx 415 000
- Totals
- EPWP Expenditure R 15 billion
- Job Creation 750 000
23Infrastructure sector challenges
- Many public bodies do not believe they can
increase the amount of work they do labour
intensively beyond what they are already doing - Wide-spread prejudices against the use of
labour-intensive methods in infrastructure - Wide-spread implementation of the EPWP tender and
design guidelines would result in a huge increase
in employment creation, programme would exceed
targets -
24- Social sector
- Initial focus on ECD and HCBC
- Challenge is to create a framework to enable the
social sector to grow - Still largely in planning and preparatory phase
- Agreement on a common system of remuneration
- Improve programme management and reporting
systems - Put in place all the required unit standards,
qualifications and learnerships - Need convincing motivation for increased funding,
with implementation models and expansion plans - Need to mobilise for more rapid expansion
- Most highly labour intensive sector
- High potential for sustainable job creation (200
000 in ECD) - Emphasized in 2005 SONA
25Social Sector model
26Environment and Economic Sectors Progress
- Environmental sector performing well
- Challenge is to expand programme into new areas,
eg waste management at municipal level - Economic sector
- DTI working on economic sector plan
- DoL and DPW finalising venture learnerships with
Services SETA - DPW lobbying government bodies for roll out of
venture learnerships, based on models such as
Limpopo Sakhasonke
27Monitoring Results (2nd Quarter)
- Quantitative reports for the first two quarters
of 2004
Excludes social sector and municipalities due to
absence of reports
28(No Transcript)
29Progress involvement of business
- Business Trust providing support
- Funding of targeted assistance to national
departments - Funding of private sector field teams to support
and assist provinces and municipalities to
implement their projects in terms of the EPWP
30Challenges (1)
- Many public bodies do not believe they can
increase the amount of work they do labour
intensively beyond what they are already doing - Wide-spread implementation of the EPWP tender and
design guidelines would result in a huge increase
in employment creation
31Challenges (2)
- Challenge
- Audits indicate that not all provinces and
municipalities are complying with the Division of
Revenue Act conditions requiring that projects be
tendered as labour intensive projects according
to the EPWP Guidelines - Recommendation
- Provincial and municipal political leadership to
be mobilised to instruct officials to use the
EPWP guidelines when tendering suitable
infrastructure projects
32Challenges (3)
- Social sector
- Challenges
- Early Childhood Development (ECD) expansion
dependent on finalisation of overall ECD policy - More work required for finalisation of Home and
Community Based Care (HCBC) enabling framework - Existing budgets do not accommodate large-scale
expansion - Recommendations
- Priority to be given expanding these sectors as
stated by the President to address basic needs
and absorb large numbers of less skilled workers
33Conclusions
- Data for the first two quarters of 2004 indicate
that the EPWP will meet its published targets for
the year. - The EPWP will exceed its targets and expectations
if provinces and municipalities can be mobilised
to use the EPWP tendering guidelines for suitable
infrastructure projects, and if there is a large
scale expansion of ECD and HCBC programmes in the
social sector.