EXPANDED PUBLIC WORKS PROGRAMME - PowerPoint PPT Presentation

About This Presentation
Title:

EXPANDED PUBLIC WORKS PROGRAMME

Description:

Application to from CETA to DOL-NSF to increase the number further to 1500 ... Challenge is to expand programme into new areas, eg waste management at municipal level ... – PowerPoint PPT presentation

Number of Views:83
Avg rating:3.0/5.0
Slides: 34
Provided by: pmg8
Category:

less

Transcript and Presenter's Notes

Title: EXPANDED PUBLIC WORKS PROGRAMME


1
EPWP Progress Report Public Works Select
Committee 23 February 2005
2
BACKGROUND
  • Wide range of programmes established post-1994
    (eg Zibambele, Zivuseni, W f W, Gundo Lashu)
  • Code of Good Practice for Special PWPs gazetted
    in 2002
  • Cabinet review of Special Poverty Relief
    Allocation in 2003

3
DESIGN OF THE EPWP
  • Must allow for wide diversity of programmes
  • Expand best-practice existing programmes
  • To be sustainable, the EPWP must not be
    make-work must be economically efficient
  • Emphasis on labour-intensive delivery of
    cost-effective quality services
  • To avoid displacement, the EPWP should take place
    in growing sectors of the economy

4
WHAT IS AN EPWP PROJECT?
  • Deliberate attempt by the public sector body to
    use its expenditure on goods and services to
    create additional work opportunities for the
    unemployed
  • Workers usually employed on a temporary basis
    (either by government, by contractors, or by
    other non-governmental organisations), under EPWP
    or learnership employment conditions
  • Workers provided with a combination of work
    experience and training
  • Public sector body attempts to define and
    facilitate exit strategies for workers when they
    leave the programme more potential for exit
    strategies in some sectors than others

5
FUNDING
  • No special fund for EPWP projects
  • Emphasis is on changing the way in which normal
    expenditure occurs
  • Reduces opportunity costs
  • EPWP projects are identified and prioritised
    using standard processes
  • Mainstreaming labour intensity
  • Government bodies do not get involved in poverty
    relief projects outside their core functional
    areas, BUT
  • National programme with highly decentralised
    implementation creates challenges for
    implementation

6
Progress to date
  • Institutional Structures are in place
  • DG Steering Committee
  • Sector Coordinating Committees
  • EPWP Unit in DPW
  • Provincial Steering Committees
  • Communication committee with GCIS

7
  • Training programmes
  • Training programme for workers being implemented
    with Dept of Labour funding
  • Training of engineers and contractors for labour
    intensive construction, with Construction SETA
    (CETA)
  • Training of officials to implement the EPWP, with
    Local Government and Construction SETAs
  • Contractor learnership programme with CETA and
    Provinces/ Municipalities
  • Learnership programmes for social sector
    programmes with relevant SETAs are being
    finalised
  • Venture learnerships for economic sector

8
Infrastructure Sector
  • Funding for projects is provided via
    infrastructure grants directly to provinces and
    municipalities
  • Projects are identified planned and implemented
    by provinces and municipalities in accordance
    with their Integrated Development Plans (IDPs)
  • Role of Department of Public Works
  • Set the conditions on the grants use EPWP Tender
    and Design Guidelines
  • Training programmes for workers, officials,
    contractors, engineers, supervisors
  • Lobby infrastructure players to participate
    (provinces, municipalities, water
    authorities,Transnet, Housing, Eskom, etc)
  • Support to municipalities and provinces
  • Monitor, evaluate and report

9
Infrastructure Sector Provinces
Department of Public Works
National Treasury
Support to province
Provinces report indicators
Equitable Share
Province
Other Provincial Expenditure
Provincial Infrastructure Grant earmarked for the
EPWP through the Division of Revenue Act and
Audited by the Auditor General
Infrastructure Budget from Equitable Share
Provincial Infrastructure Budget
10
Infrastructure Sector Municipalities
National Treasury
Public Works
Reporting
DPLG
Support to municipality
Rates, Levies and Taxes
Municipality
Other municipal Expenditure
Municipal Infrastructure Grant earmarked for the
EPWP through the Division of Revenue Act and
Audited by the Auditor General
Infrastructure Budget from Rates, levies and Taxes
Municipal Infrastructure Budget
11
Significance of EPWP Guidelines
  • Use of EPWP Guidelines is a requirement in the
    Division of Revenue Act when MIG or PIG funds
    are used
  • Provide guidance and contract conditions for
    municipalities to tender EPWP projects
  • Endorsed by SALGA, NT and DBSA
  • Makes the use of labour intensive methods a
    contractual obligation of contractors
  • Auditor General audits provinces and
    municipalities to assess compliance
  • If municipalities and provinces do not use the
    Guidelines, EPWP targets will not be reached

12
(No Transcript)
13
Use of EPWP Guidelines
  • Provinces
  • Audit of all provinces done and AG is compiling
    report
  • Compliance is poor
  • Many provinces are doing some labour intensive
    work already, but EPWP is about intensifying this
  • Municipalities
  • Audit not yet started
  • Compliance expected to be poor for 2004-2005.
    This was compounded by introduction of MIG with
    new procedures

14
Labour Intensive Contractor Learnership Programme
  • 1 contractor 2 supervisors
  • Initial plan was for 500 learnerships
  • Due to interest from public bodies was increased
    to 750
  • Application to from CETA to DOL-NSF to increase
    the number further to 1500
  • Current commitment stands at 950 learnerships and
    increasing, approx 30 provincial departments and
    municipalities participating

15
LI CONTRACTOR DEVELOPMENT PROGRAMME ROLES AND
RESPONSIBILITIES
IDT
CETA
DPW
DOL
Mentors for training providers
Trainers of trainers
Programme Management support
Community Facilitation Support
Training providers for learnerships
Province / municipality
Mentors for learners
Training projects
Training providers for workers
Learner contractor 2 learner supervisors
Access to credit
ABSA
Unemployed EPWP beneficiaries
16
  • The learnership takes approximately 2 years, each
    learner contractor employs approx 10 workers
  • Learners graduate with NQF qualifications, able
    to tender for LI projects issued in terms of EPWP
    tender and design guidelines
  • First group of learners in Ethekwini has
    completed their first project
  • Ethekwini, Coega, Klipfontein, Nkangala and
    Mpumalanga learners are on site

17
Significance of Labour Intensive Contractor
Learnership Programme
  • Aims to develop 500 sustainable contractors and
    1000 highly skilled site supervisors, specialised
    in labour intensive construction
  • As part of their learnerships they will implement
    1500 EPWP Projects to the value of R1.5 billion
  • During the implementation of these projects they
    will employ approximately 100 000 people
  • These 1500 individuals will continue to execute a
    large share of EPWP projects after they complete
    their learnerships, by winning tenders

18
Relationships between Provinces and Municipalities
  • Varies from Province to Province
  • In Limpopo for instance the province has taken
    the lead to mobilise all municipalities to
    participate in the EPWP Contractor learnership
    programme
  • However in provinces with large municipalities or
    Metros they act independently
  • The Provincial Departments of Local Government
    play a role in implementing the MIG and can
    therefore also put pressure on municipalities to
    implement EPWP through the EPWP Guidelines

19
Other infrastructure bodies
  • Housing
  • Transnet
  • Water Boards
  • Mining companies

20
Training
  • Officials
  • LGW SETA is funding training of local government
    officials, DPW also carried out training of
    officials
  • Consulting Engineers
  • Have responded well, with professional bodies
    supporting the initiative. More than 500
    engineers have been trained to date
  • Contractors
  • Major contractors have not responded well and are
    being engaged through professional bodies
  • Emerging contractors are eager but lack funds.
    DOL-NSF-CETA being approached to assist

21
Training for beneficiaries
  • Training programmes in place and training
    providers appointed
  • First training programmes have been implemented
    on some EPWP projects , challenge is to have them
    implemented on all projects

22
Infrastructure Five Year Targets
  • Provinces
  • Total Provincial Infrastructure Grant Approx R
    20 billion
  • Targeted expenditure on EPWP projects Approx R
    6.7 billion
  • Targeted EPWP Job Creation Approx 335 000
  • Municipalities
  • Municipal Infrastructure Grant Approx R 25
    billion
  • Targeted expenditure on EPWP projects Approx R
    8.3 billion
  • Targeted EPWP Job Creation Approx 415 000
  • Totals
  • EPWP Expenditure R 15 billion
  • Job Creation 750 000

23
Infrastructure sector challenges
  • Many public bodies do not believe they can
    increase the amount of work they do labour
    intensively beyond what they are already doing
  • Wide-spread prejudices against the use of
    labour-intensive methods in infrastructure
  • Wide-spread implementation of the EPWP tender and
    design guidelines would result in a huge increase
    in employment creation, programme would exceed
    targets

24
  • Social sector
  • Initial focus on ECD and HCBC
  • Challenge is to create a framework to enable the
    social sector to grow
  • Still largely in planning and preparatory phase
  • Agreement on a common system of remuneration
  • Improve programme management and reporting
    systems
  • Put in place all the required unit standards,
    qualifications and learnerships
  • Need convincing motivation for increased funding,
    with implementation models and expansion plans
  • Need to mobilise for more rapid expansion
  • Most highly labour intensive sector
  • High potential for sustainable job creation (200
    000 in ECD)
  • Emphasized in 2005 SONA

25
Social Sector model
26
Environment and Economic Sectors Progress
  • Environmental sector performing well
  • Challenge is to expand programme into new areas,
    eg waste management at municipal level
  • Economic sector
  • DTI working on economic sector plan
  • DoL and DPW finalising venture learnerships with
    Services SETA
  • DPW lobbying government bodies for roll out of
    venture learnerships, based on models such as
    Limpopo Sakhasonke

27
Monitoring Results (2nd Quarter)
  • Quantitative reports for the first two quarters
    of 2004

Excludes social sector and municipalities due to
absence of reports
28
(No Transcript)
29
Progress involvement of business
  • Business Trust providing support
  • Funding of targeted assistance to national
    departments
  • Funding of private sector field teams to support
    and assist provinces and municipalities to
    implement their projects in terms of the EPWP

30
Challenges (1)
  • Many public bodies do not believe they can
    increase the amount of work they do labour
    intensively beyond what they are already doing
  • Wide-spread implementation of the EPWP tender and
    design guidelines would result in a huge increase
    in employment creation

31
Challenges (2)
  • Challenge
  • Audits indicate that not all provinces and
    municipalities are complying with the Division of
    Revenue Act conditions requiring that projects be
    tendered as labour intensive projects according
    to the EPWP Guidelines
  • Recommendation
  • Provincial and municipal political leadership to
    be mobilised to instruct officials to use the
    EPWP guidelines when tendering suitable
    infrastructure projects

32
Challenges (3)
  • Social sector
  • Challenges
  • Early Childhood Development (ECD) expansion
    dependent on finalisation of overall ECD policy
  • More work required for finalisation of Home and
    Community Based Care (HCBC) enabling framework
  • Existing budgets do not accommodate large-scale
    expansion
  • Recommendations
  • Priority to be given expanding these sectors as
    stated by the President to address basic needs
    and absorb large numbers of less skilled workers

33
Conclusions
  • Data for the first two quarters of 2004 indicate
    that the EPWP will meet its published targets for
    the year.
  • The EPWP will exceed its targets and expectations
    if provinces and municipalities can be mobilised
    to use the EPWP tendering guidelines for suitable
    infrastructure projects, and if there is a large
    scale expansion of ECD and HCBC programmes in the
    social sector.
Write a Comment
User Comments (0)
About PowerShow.com