Title: Facilities Improvements and Bond Construction Update Facilities Advisory Committee
1Facilities Improvements and Bond Construction
UpdateFacilities Advisory Committee
- Long Beach Community College District
- December 2, 2008
EDUCATE ? ENGAGE ? EMPOWER
2Agenda
- Completed Construction Projects
- PCC Learning Resource Center
- LAC Central Plant
- Current Upcoming Construction Projects
- LAC South Quad Complex
- LAC Learning Resource Center
- LAC Building A, Student Services Retrofit
- LAC Math Technology Building
- LAC Parking Structure
- LAC Infrastructure Improvements Phase 3
- PCC Central Plant
- PCC Industrial Tech Phase 1
- PCC MDAB (Multi-Disciplinary Academic Building)
- PCC Building C Retrofit
- District Wide Building Needs Assessment Projects
- Toilet Improvement Projects
- Quick-Start Projects
- ADA Projects
- Lighting Projects
3Completed Construction Projects
PCC Learning Resource Center Measure E 2002
- Construction Complete
- Modern Facility with Computer Lab and Multimedia
- Stand alone Data Center. Provides District IT
redundancy - Bridge to building E
- Design elements move towards energy efficiencies
- Ribbon cutting held 9/17/08
4Completed Construction Projects
LAC Central Plant Measure E 2002
- Central Plant equipment, Public Safety, Field
House for Athletics - Final FFE installation underway
- Plant ready for operation and awaiting completion
of LRC SQC - Construction Complete
- Anticipated startup 12/05/08
5Current and UpcomingConstruction Projects
South Quad Complex Measure E 2002
- Construction approx. 89 Complete
- Space includes
- Approx. 68,000 ASF
- 32 modern classrooms and labs
- 38 faculty offices
- Executive office
- Multipurpose room
- State of the art Board Room
- Substantial completion anticipated 1/09
6Current and UpcomingConstruction Projects
LAC/Learning Resource Center Measure E 2002
- Construction 91 Complete
- Adds 10,000 ASF to existing building
- Substantial Completion Anticipated January 2009
7Current and UpcomingConstruction Projects
LAC Building A Student Services
Retrofit Measure E 2008
- Design Development to be submitted this month
- Adds 4,000 ASF to existing building
- Will house AR, Counseling, Health Services,
Cashier, Transfer Ctr., etc. - Estimated start of construction 7/09
8Current and UpcomingConstruction Projects
LAC Math Technology Building Measure E 2008
- Completed Schematic Design (June 2008)
- Currently in Design Development phase
- Will house Math and Culinary Arts instructional
program as well as Reprographics - Estimated start of construction 2011
9Current and UpcomingConstruction Projects
LAC Parking Structure Measure E 2008
- Planning initiated for approximately 900 Vehicles
- To be procured under Design Build Delivery
method - To be located Southeast corner of Lot J adjacent
to the Verizon building - Photovoltaic Electrical Generation Array on top
level of structure - Anticipated start of construction 2009
Proposed Math Technology Bldg.
Lot J
Proposed Parking Structure Loc.
Verizon Bldg.
10Current and UpcomingConstruction Projects
- LAC Infrastructure Improvements Phase 3
- Measure E 2008
- Planning underway with engineers
- Completes chilled water lines to North side of
campus - Includes other major utility upgrades Reclaimed
Water, Domestic Water, Data, etc. - Existing building HVAC systems to be upgraded in
synch with infrastructure improvements - Coordinated with modernization and quick start
projects
11Current and UpcomingConstruction Projects
PCC Central Plant Measure E 2002
- Houses Central Plant equipment and Maintenance
and Operations facility - Construction Approximately 99 Complete
- Currently provides chilled water to the PCC LRC
12Current and UpcomingConstruction Projects
PCC Industrial Technology Center Phase 1 Measure
E 2002
- Modern facility houses Welding Department and
other trade programs - Construction is 45 complete
- Replaces existing antiquated structures
- New Northern face of the campus
- Completion anticipated summer 2009
13Current and UpcomingConstruction Projects
PCC MDAB (Multi-Disciplinary Academic Building)
Measure E 2002
- 90 construction documents submitted
- Swing space planning completed 9/2008,
construction of swing space starts Spring 2009 - Anticipated start of MDAB construction Summer
2009 - To be completed in two phases
14Current and UpcomingConstruction Projects
PCC Building C Retrofit - Measure E 2008
- To be designed by Hill Partnership Architects
- Houses the Fitness Center, Gymnasium, Weight
Room, and Faculty and Staff Offices - Swing space to be located on PCC Campus (TBD)
- To be completed concurrently with MDAB project
- Anticipated start of construction Spring 2010
15Current and UpcomingConstruction Projects
District Wide Building Needs Assessment
Project Measure E 2008
- Toilet Improvement Projects
- Quick-Start Projects
- ADA Projects
16Current and UpcomingConstruction Projects
District Wide Building Needs Assessment
Projects Measure E 2008
- Lighting Projects
- Classroom Improvement Projects
17Recently Completed Facilities Improvements
Building B and E Boiler Replacement
- Replaced existing boilers, pumps, expansion tanks
and common flue with new equipment via helicopter
lift. - A newly upgraded design reflecting a mechanical
engineered system was installed improving the
efficiency of the boilers. - Completed 10/2008
18Recently Completed Facilities Improvements
Additional Facilities Improvements
- LAC upgrades
- Veterans Stadium scoreboard and PA system
upgrade - Building K upgrades Exterior door paint, room
111 floor refinishing - PCC upgrades
- Building AA Built wall for information desk,
installed carpet, and power upgrades - Building BB Carpet and window blind
installation - Building CC Installed fans in gym
- Building DD Carpet and window blind
installation - Building EE Window blind installation
- Building MM Exterior paint, replaced doors and
awnings, re-glazed windows, and replaced fascia
boards
19Important Ongoing Initiatives
LBCCD Coming Advancements
- Master Landscape Project
- District Wide Energy Efficiency Improvements
- Electronic Marquee Signage
- Wayfaring and Building Signage
- Campus Lighting Improvements
20Planned Phasing of Future Projects
Currently Planned Schedule
- 2008-09
- Parking Structure Design/Build concept
- Anticipate awarding bid Spring 2009
- Moving Warehouse from PCC to Alteon Building at
LAC TBD - Moving LAC Building A into Swing Space Spring
2009 - Install portables at PCC for Swing Space Spring
2009 - LAC/PCC Building Needs Assessment Projects
- Bathroom Improvement Projects
- Quick-Start Projects
- Lighting Projects
- Classroom Improvement Projects
- Infrastructure Projects
- Submit FPP for M/N Project at LAC and MM Project
at PCC and submit IPP for P Building at LAC - Finalize Master Landscaping and Signage plans
- Marquee signage anticipated to be installed March
2009
21Planned Phasing of Future Projects
Currently Planned Schedule
- 2009-10
- Begin construction of Building A at LAC
- Anticipating July 2009 start
- Begin construction of Buildings CC, DD, and EE at
PCC - Anticipating July/August 2009 start
- Begin Schematic Design for Buildings C and F at
LAC - Submit plans to DSA no later than March 2010
- Begin Master Landscaping and Signage Initiatives
- Continue District Wide Energy Efficiency
Improvements - Phase IIA
- Lighting Upgrades, HVAC Upgrades, Control
upgrades, Pool Cover, Roof replacement, etc - Phase IIB
- Upcoming advancements include connecting current
buildings to Central Plant infrastructure
22Planned Phasing of Future Projects
Currently Planned Schedule
- 2010-11
- Anticipated Construction completion of Building A
at LAC January 2011 - Submit plans to DSA for Math/Technology Building
at LAC - Move Buildings C and F programs into Swing Space
(M/N Building) and begin construction Spring
2011 - Construction completion of Buildings CC, DD and
EE at PCC - Begin construction of Buildings AA and BB at PCC
- Anticipating January/February 2011 start
23Planned Phasing of Future Projects
Currently Planned Schedule
- 2011-12
- Begin construction of Math/Technology Building at
LAC - Submit plans to DSA for M/N Building at LAC
- 2012-13
- Anticipated Construction completion of Buildings
C and F at LAC December 2012 - Anticipated Construction completion of
Math/Technology Building at LAC December 2012 - Begin construction of Buildings M/N at LAC
January 2013 - Anticipated Construction completion of Buildings
AA and BB at PCC June 2013
24QUESTIONS ANSWERS
EDUCATE ? ENGAGE ? EMPOWER