Title: A Complete Notification
1A Complete Notification
Created by Nathan Luedke Wisconsin Department
of Natural Resources Updated 8/05
- A guide to filing a complete notification form
4500-113
2Box 1
3Contractor Project Number
- For the contractors use only.
- DNR does not use Contractor Project Number and
does not record it.
4Box 2
5The Postmark
- The Notification must be Postmarked 10 working
days prior to the Project Start Date. - Working days include weekday holidays.
6Scheduling Example
Sunday
Monday
Tuesday
Wednesday
Thursday
Friday
Saturday
Because the waiting period is 10 working days,
prior to the start date, the total number of
calendar days will be 14 in most cases.
Postmark
Postmark
Start Date
Start Date
The exception is when a notification is
postmarked on a Monday.
7Boxes 3 and 4
8Date Received and DNR File
- Used for DNR organization and filing purposes.
- Specific projects can quickly be found by
referencing the DNR File Number.
9Box 5
Original
10Type of Notification Original
- First Notification for a Project.
- A Notification expires once the project end date
passes. - A new (original) notification must be filed if
the first notification expires. - This includes 10 working day waiting period and
fee submittal.
11Box 5
Revised
12Type of NotificationRevisions
- Notification must be revised if
- Project dates change.
- If earlier than the original start date, must
meet 10 working day requirement. - If later than the original start date, must be
revised prior to original start date. - Contractor, owner, or landfill change.
- RACM amounts change by at least 20.
- Please highlight the word revised.
13Box 5
Cancellation
14Type of Notification Cancellations
- Cancels project.
- An open notification (has not expired) can be
revised by a different entity. - Once the notification is canceled, it can not be
revised. - An original notification must be submitted along
with 10 working day requirement and fee submittal.
15Box 5
EmergencyDate/Hr. Notified
16Type of Notification Emergency
- Must include date and time of Emergency Notice.
17Box 5
Other
18Type of Notification Other
- Used for Courtesy Notifications, After-the-Fact
Notifications, etc.
19Box 6
Renovation/Abatement
20Renovation/Abatement
- Altering a facility or one or more facility
components in any way, including the stripping or
removal of asbestos from a facility component.
21Box 6
Emergency Renovation/Abatement
22 Emergency
- Emergency Notification is only for Renovation
Projects. - Must be a result of a sudden or unexpected event
that causes an unsafe condition, equipment
damage, or an unreasonable financial burden. - This DOES NOT include poor planning!
23Box 6
Planned Renovation/Abatement (Annual)
24Planned Renovation (Annual)
- Renovation projects involving individual,
nonscheduled renovation operations that affect a
combined amount of RACM which is regulated. - Small portions of a regulated amount being
removed over an extended period.
25Box 6
Demolition
26Demolition
- Wrecking or taking out of any load-supporting
structural member of a facility together with any
related handling operation or the intentional
burning of any facility.
27Box 6
Ordered Demolition
28Ordered Demolition
- A facility is being demolished under an order of
a state or local government agency issued because
the facility is structurally unsound and in
danger of imminent collapse. - Does not require 10 day waiting period.
- Must be notified as early as possible, but no
later than the working day following the start
date.
29Box 6
Fire Training Burn
30Fire Training Burn
- Demolition by the intentional burning of a
structure, used solely for live Fire Department
training. - The burning of a structure or building materials
as a method of waste reduction or disposal is
prohibited. - Fire Training must be conducted on an in-tact
structure and only by a Fire Department.
31Box 7
32Inspection Dates
- Box 7 requires the dates of the inspection to
ensure that the inspection is current and that it
has been done.
33Box 8
34Inspector Certification Information
- Box 8 identifies the Name of the inspector and
their Wisconsin Inspector Certification Number. - Ensures that the inspector is properly certified.
- Provides a contact for inspection information.
35Box 9
36Asbestos Abatement Dates
- States the dates which Asbestos Abatement will
take place. - Indicates which shift the asbestos abatement will
take place. - Allows the inspector to arrive during abatement
activity.
37Box 10
38Reno/Demo (Project) Dates
- States the time frame in which the project is
active. - Starting before or after the specified start date
is a violation. - Once the end date has passed, the notification
has expired. - In order to continue work, a new notification
must be filed complete with fee and 10 working
day waiting period.
39Box 11
40Abatement Contractor
- Lists the abatement contractor information.
- Must be completed for Renovation/Abatement
notifications or notice is deficient.
41Box 12
42Demolition Contractor
- Lists demolition contractor information.
- May also list the Fire Department for a Fire
Training Burn. - Must be completed on Demolition notifications or
notice is deficient.
43Box 13
44Facility Information
- Includes information such as Name and address of
the facility. - States which DNR region it is in.
- Also requires general information about the
structure. - Used to generate a picture of the project.
45Box 14
46Facility Owner
- General owner information and contacts.
47Box 15
48Waste Disposal Site/Transporter
- Name and location of the waste disposal site.
- Used to ensure that material is being disposed of
at licensed a landfill.
49Box 16
50Amount of Asbestos
- States Categories of material and whether they
will be removed. - Please provide total number of each type of
material. - Do not break out materials or write see
attached to include each individual material.
Use box 19 for this purpose. - Cat I or II being removed in a manner that would
cause it to become RACM should be listed as RACM.
51Box 17
52Fees
- Contains Fee Table.
- Fee structure has changed as of July 1, 2005.
53Suggested Fee Schedule
- Demolition with less than 160 s.f., 260 l.f. of
Regulated Asbestos Containing Material (RACM)
would increase to 75. - Demolition or Renovation with greater than 160
s.f., 260 l.f. of RACM, but less than 1000 feet
combined would increase to 225. - Demolition or Renovation with equal to or greater
than 1000 total feet, but less than 5000 total
feet of RACM would increase to 400. - Demolition or Renovation with equal to or greater
than 5000 total feet of RACM would be 750.
54Current Fees vs. New Fees
Previous Fees New Fees 50
75 150 225 335
400 New Category 750
55Box 18
56Inspection Methods
- Assumed materials?
- Polarized Light Microscopy (PLM)?
- Combination?
57Box 19
58Description of Asbestos
- State detailed information about the type of
material(s) and location(s). - If the list is long, providing a separate list
(see attached) is acceptable here.
59Box 20
60Description of Work
- Methods of renovation/abatement.
- Containment?
- Glove Bag?
- Wrap and Cut?
- Methods of Demolition.
- Back hoe?
- Fire Training Burn?
61Box 21
62ACM Emission Controls
- Practices and engineering control being used at
the site to prevent ACM emissions. - Adequate wetting.
- Sealed in leak tight containers.
- Negative Pressure containment.
63Box 22
64Discovery or Condition Change
- Explanation of the procedure to be used if
asbestos, previously unidentified, becomes
visible during work. - Also explanation of how previously non-friable
material will be handled if it becomes RACM. - Appropriate response in most cases is to stop
work and have the situation assessed to reduce
the risk of further contamination.
65Box 23
66Emergency Abatement Info
- Date, hour, and description of incident or
situation that caused the abatement to be an
emergency.
67Box 24
68Ordered Demolition
- Name, Authority, and Date from whom the Ordered
Demolition originated. - A copy of the order must be attached to the
notification to be complete.
69Box 25
70Authorized Representative
- Verifies that an authorized representative
trained in the provisions of NR 447 will be on
site during any work that disturbs RACM.
71Box 26
72Certification of Information
- Verifies that all information on the notification
is correct.
73Box 27
74Mailing Addresses
- If a renovation involves any amount of asbestos,
DHFS must be notified 1 business day before the
start date. - If a renovation has more than 160 square feet or
260 linear feet, it must be notified to the DNR
and DHFS. - The DNR notification must be postmarked 10
working days prior to the start date. - The DHFS notification must be postmarked 10
calendar days prior to the start date.
75Mailing Notifications
- If a demolition does not involve any asbestos
containing materials, only the DNR needs to
receive a 10 working day notice. - If the demolition does include asbestos
containing materials, DHFS also requires a
notification.
76Mailing Notifications
- All addresses are included on the notification.
- Please copy the South East Regional Office for
DNR regulated projects. - All fees go to the Central Office (asbestos
coordinator) address.
77Contacts
- Mark Davis (608) 266-3658
- (Asbestos Program, Madison)
- Nathan Luedke (608) 264-8892
- (Asbestos Program, Madison)
- www.dnr.state.wi.us
- Department of Health and Family Services
- (608) 261-6876 www.dhfs.state.wi.us
DNR website
Updated form 4500-113