Title: White Pass Standard Gauge Conversion
1White Pass Standard Gauge Conversion
- Mark Taylor
- University of Alaska Fairbanks
- Spring 2002
2Outline
- Introduction
- Project History
- White Pass Assessment
- Conversion Considerations
- Construction Details
- Feasibility
- Closing
3Introduction
- House Bill 241 proposes the extension of the
Alaska Railroad from Fairbanks to Whitehorse,
Yukon - At Whitehorse, the proposed railroad would join
the existing White Pass and Yukon Route Railroad - White Pass track gauge is non-standard and
requires conversion - The process and feasibility of such
standardization are presented.
4(No Transcript)
5Introduction
- The conversion of an active railroad has never
taken place in modern times - It is difficult to compare historical practices
against todays technology
6Introduction
- Working knowledge of railroad operations,
maintenance, and construction - Worked seasonally as track surveyor, bridge
inspector, conductor/engineer, work train
foreman, project engineer - Authored White Pass manual of maintenance and
construction standards
7Project History
- Railroad development into Alaska and northern
Canada has a long history - First development was Alaska Railroad in 1923
- Further exploration prior to WWII
- State interest in 1970, 1980 produced route
surveys and environmental studies (HB 47) - Recent increase in interest over last decade
notably HB 241 and Sen. Murkowskis Rails to
Resources
8Project History
- The White Pass is included as an integral
component of proposed trans-Canada railroad - Provide a tidewater access 110 miles from
Whitehorse, YT
9HB 241 Testimony
- White Pass could be converted ahead of the
proposed corridor and serve as a supply route - A route simply from Fairbanks to Skagway via
Whitehorse would prove sufficiently valuable in
and of itself in addition to serving as a
building block to further southward expansion
10White Pass
- Built in 1898 as a transportation response to the
Klondike gold rush - Key transporter of freight and passengers to and
from the Yukon and Northern B.C. - Leased by the U.S. Army in WWII, valuable
construction supply route for the Alaska Hwy
11White Pass
- Major transporter of ore from the Yukon
- Following mine closures, unable to compete
against recently opened hwy traffic - Shutdown in the fall of 1982
- Reopened the spring of 1988
- Seasonal passenger operations moving over 300 000
/ yr
12White Pass
- White Pass was designed for narrow gauge but
constructed to standard gauge specifications - Current maintenance and construction meets
standard gauge operational requirements
13White Pass
- Current Track Maintenance
- Upgrading to heavy rail
- Installation of 8 ft. ties
- Higher capacity switches
- Standard ballast
- Wider clearances
- Higher load ratings bridges and docks
- Uniformity of heavy passenger trucks
14Conversion
- White Passs current maintenance program is
intended to ensure safe, reliable passenger
operations however such efforts greatly enhance
the efficiency of future conversion - The active passenger corridor receives the
heaviest maintenance and upgrades
15(No Transcript)
16Conversion
- Traffic interruption
- Revenue is generated through summer tourist
trains - To limit or restrict passenger operations is
unnecessary - Much of the railroad is unused and substantial
work can be accomplished without hindrance to
passenger operations
17Construction Outline
- Construction is expected to last two years
- Work performed through seven phases
- Starting in early January of Year One
- Ending mid-September of Year Two
18Construction Outline
- Year One
- Phase 1 Construction of rail-barge facility
- Phase 2 Upgrading of bridges
- Phase 3 Grade stabilization from Carcross
to Whitehorse - Phase 4, 5 Gauge widening from Carcross to
Bennett to Skagway - Phase 6 Equipment conversion
19Construction Outline
- Year Two
- Phase 6 (continued) Equipment Conversion
- Phase 7 Gauge widening from Carcross to
Whitehorse
20(No Transcript)
21(No Transcript)
22Phase One Rail Barge Facility
- Begins January of Year One
- Ends May of Year One
- Allow for construction material to be loaded by
the manufacturer and shipped directly via barge - Be the leading end of Skagways rail-barge
connection
23Phase One Rail Barge Facility
- Construction must be completed prior to the
cruise ship season - Wintertime port construction is common in Skagway
- All docks in Skagway have been designed or
adapted to accommodate passenger traffic
24Phase One Rail Barge Facility
- Two are immediately suitable for a rail barge
ramp construction - All are deepwater docks
- Skagway has 25 ft tides and the appropriate ramp
design would allow for four loading/offloading
windows per day at the 16 ft stage
25(No Transcript)
26Phase One Rail Barge Facility
- Railroad Dock
- designed and built to standard gauge rail
capacity - A third rail runs throughout its length
- No additional rail crossings would be required
- Additional rail traffic accessing the pier would
pose no significant threat increase to pedestrian
traffic
27(No Transcript)
28Phase One Rail Barge Facility
- Ore Dock
- The former ideal location for such a facility
- Alaska Marine Line operates a ramp here
- Land leases have severely restricted any
potential foot print for freight operations - Track geometry in the confined quarters would be
a design problem - Rail access would require additional grade
crossings through Skagway tourism district
29(No Transcript)
30Phase One Rail Barge Facility
- The City of Skagway exists in a confined valley
- Waterfront land is leased by White Pass from the
City - Much land has been subdivided and remaining
portions are not adequate for staging of railroad
freight
31Phase One Rail Barge Facility
- The best means of marshalling barge borne freight
is to remove it directly from the barge and stage
it north of town near railroad milepost 3
32(No Transcript)
33(No Transcript)
34Phase Two Bridges, Tunnels, and Clearances
- 23 Bridges over entire route
- 14 bridges within Alaska
- 3 bridges within British Columbia
- 6 bridges within Yukon
35Phase Two Bridges, Tunnels, and Clearances
- To handle the increase in axle loads from
standard gauge equipment, many bridges require
upgrading - The simplest method is the installation of
intermediate pony trusses at bridge mid-spans
36Phase Two Bridges, Tunnels, and Clearances
- Alaska Subdivision (MP 0.0 20.4)
- 5 bridges have been recently rebuilt to steel,
standard gauge capacity - 4 require intermediate bents
- Both short and shallow
- 2 require extensive upgrading
- 3 are adequate
37Phase Two Bridges, Tunnels, and Clearances
- British Columbia Subdivision (MP 20.4 53.2)
- 2 have recently been rebuilt to steel, standard
gauge capacity - One is due for rebuild by 2003
38Phase Two Bridges, Tunnels, and Clearances
- Yukon Subdivision (MP 53.2 110.0)
- 3 recently reconstructed to standard gauge
capacity - 3 require extensive reconstruction
- All short and shallow
39Phase Two Bridges, Tunnels, and Clearances
- Only two tunnels exist along the railroad
- Both in the Alaska Subdivision
40Phase Two Bridges, Tunnels, and Clearances
- MP 16 Tunnel
- Constructed in the winter of 1899
- 300 ft long
- Requires no upgrading
- Current dimensions allow for standard rail traffic
41(No Transcript)
42(No Transcript)
43Phase Two Bridges, Tunnels, and Clearances
- MP 18 Tunnel
- Built in 1969 to replace a bridge
- 700 ft long
- Built to American Railway Engineer Assoc
Standards (AREA) - However, the portals limit the interior
dimensions of the tunnel
44Bridge replaced with tunnel in 1969
45Phase Two Bridges, Tunnels, and Clearances
- Clearances
- No additional right-of-way widening is necessary
- An intensive maintenance program has actively
removed close clearances, widened cuts, deepened
shoulders, and removed rocky outcrops
46Phase Two Bridges, Tunnels, and Clearances
- Clearances
- Historically, White Pass has transported excess
dimension freight - White Pass transported 80 ft lengths of 60 in
diameter pipe in proof of concept test for
Foothills Pipeline - White Pass operates with some standard gauge
equipment
47(No Transcript)
48(No Transcript)
49(No Transcript)
50Phase ThreeRight-of-Way Stabilization
- Carcross (MP 65.7) to Whitehorse (MP 110.0)
- Little maintenance has occurred over this
northernmost section since 1982 - A dedicated crew will work six months beginning
May 1 of Year One - The crew will be comprised of one work train and
supporting heavy equipment
51Phase ThreeRight-of-Way Stabilization
- Primary focus of crew
- Restoring shoulder width
- Replacing wooden culverts with aluminum
- Widening cuts
52Phase ThreeRight-of-Way Stabilization
- It is expected that over 200 000 yds of material
will be removed or distributed along the
right-of-way - All of the material required is available from
natural sources within designated railroad land
rights
53Phase ThreeRight-of-Way Stabilization
- Existing track
- Much of the subgrade is a mixture of sand and
silt - Cleaned ballast was placed during 1960 overhaul
throughout much of this section - Rail, ties, and accompanying track hardware is
inadequate for standard gauge traffic and will be
addressed during Year Two
54Phase ThreeRight-of-Way Stabilization
- No rail operations are underway over this track
portion and construction crews can operate
unimpeded - Access to the track is available via the Klondike
Highway
55(No Transcript)
56(No Transcript)
57Phase FourGauge Widening Carcross to Bennett
- Carcross (MP 67.7) to Bennett (MP 40)
- This section of track follows the shore of
Bennett Lake passing light grades through fine
soil terrain near Carcross becoming rock near
Bennett - No operations are underway over this section
58Phase FourGauge Widening Carcross to Bennett
- Heavy reconstruction has taken place within the
past six years - Shore stabilization
- 100 long tie renewal
- Extensive surfacing
- Ballasting
- Much of the rail is new 100 lb/yd and adequate
for standard gauge traffic
59Phase FourGauge Widening Carcross to Bennett
- Track and right-of-way is in condition suitable
for straightforward gauge widening - No operations take place over this section
- Two crews, totaling thirty people, would be
required - Work will closely resemble the process of a rail
relay
60Phase FourGauge Widening Carcross to Bennett
- Two people will precede crew one removing spikes
and anchors on the west rail - The east rail will remain in place serving as a
gauge rail - The crew will proceed with a hydraulic gauging
machine moving the unspiked rail 10.25 in. and
gauge spike
61Phase FourGauge Widening Carcross to Bennett
- The next crew, in the same fashion, will move the
east rail 10.25. in and gauge spike - The bulk of the crew will complete all spiking,
anchoring, leveling, and lining - Standard gauge production rail laying equipment
will be used - The crew will leave behind standard gauge track
62Phase FourGauge Widening Carcross to Bennett
- The primary crews will ignore track
discontinuities to maintain momentum - Ie grade crossings, turnouts, yards
- A follow up crew will address these potentially
time consuming tasks
63(No Transcript)
64Phase FiveGauge Widening Bennett to Skagway
- Bennett (MP 40.4) to Skagway (0.0)
- At Bennett, crews will be entering the active
passenger corridor - Timing is important
- The construction crew should arrive Bennett near
the time Bennett Service is suspended - Expected around mid-August
65(No Transcript)
66Phase FiveGauge Widening Bennett to Skagway
- From Bennett, construction can proceed toward
Fraser - Crews should arrive Fraser near the time Fraser
service is suspended - Expected around mid-September
67(No Transcript)
68Phase FiveGauge Widening Bennett to Skagway
- From Fraser, construction can proceed toward the
summit - Crews should arrive at the summit near the time
total passenger services are suspended near late
September - After this date, crews have total access to the
passenger corridor
69(No Transcript)
70Phase FiveGauge Widening Bennett to Skagway
- In Skagway Yard, a crew of eight to ten will be
at work converting switches, road crossings, and
some short lengths of three-rail track - At the end of the summer of Year One, the
essential portions of the Skagway Yard will be
ready to accommodate standard gauge stock
71Phase FiveGauge Widening Bennett to Skagway
- By the Fall of Year One, the railroad will be
standard gauge from Skagway to Carcross
72(No Transcript)
73Phase Six Equipment Conversion
- The Skagway Facility can dedicate itself to
equipment conversion after the suspension of
passenger service - Nearly all of White Pass equipment in service is
historical passenger equipment - The process would proceed through the winter
ending before start of season Year Two
74Phase Six Equipment Conversion
- Only passenger equipment will be focused on for
conversion - Freight and work equipment can be easily replaced
with more efficient leased or purchased standard
gauge equipment brought in by barge
75Phase Six Equipment Conversion
- Nearly all of the passenger fleet has been
transitioned to a uniform, steel truck design
which can be easily converted to standard gauge - A stockpile of standard gauge components can be
on hand early via barge
76Phase Six Equipment Conversion
- The conversion of equipment would be a
straightforward - The car enters the shop
- Is jacked up
- Narrow gauge trucks and brake rigging removed
- Standard gauge trucks and rigging installed
77Phase Six Equipment Conversion
- White Pass locomotives are wholly obsolete with
their technology dating back to the 1950s - One modern, standard gauge locomotive would
easily replace four existing White Pass
locomotives - New locomotives could be purchased and/or leased
for a significantly lower cost
78(No Transcript)
79Phase Seven Gauge Widening Carcross to
Whitehorse
- Carcross (MP 67.5) to Whitehorse (MP 110.0)
- The existing track over this section would be
converted during the spring and summer of Year Two
80Phase Seven Gauge Widening Carcross to
Whitehorse
- All new track supplies could be brought to
Skagway via barge and taken directly to Carcross
on standard gauge cars - This will provide the most striking metamorphosis
- This will also be the most management intensive
part of construction
81Phase Seven Gauge Widening Carcross to
Whitehorse
- All new track supplies would be brought to
Skagway via barge and taken directly to Carcross
on standard gauge cars - First, a crew working north will widen gauge as
previously outlined - The track will be temporarily spiked on the
existing narrow gauge ties
82Phase Seven Gauge Widening Carcross to
Whitehorse
- Second, a standard gauge work train will proceed
north distributing new, 115 lb/yd rail and ties
at night - During the day, a crew will lay the new rail and
gauge spike, still using narrow ties
83Phase Seven Gauge Widening Carcross to
Whitehorse
- Third, a crew using standard gauge production
equipment will insert new ties and complete the
conversion - This is concluded with a ballast train and
surfacing crew - Work will progress at 3 miles per week
- Work is to be completed by mid-September
84Cost
- This cost assessment is a broad scope analysis of
projected costs
85Cost Phase One
86Cost Phase Two
87Cost Phase Three
88Cost Phase Four
89Cost Phase Five
90Cost Phase Six
91Cost Phase Seven
92Summary
93(No Transcript)
94(No Transcript)
95Questions