White Pass Standard Gauge Conversion - PowerPoint PPT Presentation

1 / 95
About This Presentation
Title:

White Pass Standard Gauge Conversion

Description:

White Pass track gauge is non-standard and requires conversion ... White Pass could be converted ahead of the proposed corridor and serve as a supply route ... – PowerPoint PPT presentation

Number of Views:118
Avg rating:3.0/5.0
Slides: 96
Provided by: marklt4
Category:

less

Transcript and Presenter's Notes

Title: White Pass Standard Gauge Conversion


1
White Pass Standard Gauge Conversion
  • Mark Taylor
  • University of Alaska Fairbanks
  • Spring 2002

2
Outline
  • Introduction
  • Project History
  • White Pass Assessment
  • Conversion Considerations
  • Construction Details
  • Feasibility
  • Closing

3
Introduction
  • House Bill 241 proposes the extension of the
    Alaska Railroad from Fairbanks to Whitehorse,
    Yukon
  • At Whitehorse, the proposed railroad would join
    the existing White Pass and Yukon Route Railroad
  • White Pass track gauge is non-standard and
    requires conversion
  • The process and feasibility of such
    standardization are presented.

4
(No Transcript)
5
Introduction
  • The conversion of an active railroad has never
    taken place in modern times
  • It is difficult to compare historical practices
    against todays technology

6
Introduction
  • Working knowledge of railroad operations,
    maintenance, and construction
  • Worked seasonally as track surveyor, bridge
    inspector, conductor/engineer, work train
    foreman, project engineer
  • Authored White Pass manual of maintenance and
    construction standards

7
Project History
  • Railroad development into Alaska and northern
    Canada has a long history
  • First development was Alaska Railroad in 1923
  • Further exploration prior to WWII
  • State interest in 1970, 1980 produced route
    surveys and environmental studies (HB 47)
  • Recent increase in interest over last decade
    notably HB 241 and Sen. Murkowskis Rails to
    Resources

8
Project History
  • The White Pass is included as an integral
    component of proposed trans-Canada railroad
  • Provide a tidewater access 110 miles from
    Whitehorse, YT

9
HB 241 Testimony
  • White Pass could be converted ahead of the
    proposed corridor and serve as a supply route
  • A route simply from Fairbanks to Skagway via
    Whitehorse would prove sufficiently valuable in
    and of itself in addition to serving as a
    building block to further southward expansion

10
White Pass
  • Built in 1898 as a transportation response to the
    Klondike gold rush
  • Key transporter of freight and passengers to and
    from the Yukon and Northern B.C.
  • Leased by the U.S. Army in WWII, valuable
    construction supply route for the Alaska Hwy

11
White Pass
  • Major transporter of ore from the Yukon
  • Following mine closures, unable to compete
    against recently opened hwy traffic
  • Shutdown in the fall of 1982
  • Reopened the spring of 1988
  • Seasonal passenger operations moving over 300 000
    / yr

12
White Pass
  • White Pass was designed for narrow gauge but
    constructed to standard gauge specifications
  • Current maintenance and construction meets
    standard gauge operational requirements

13
White Pass
  • Current Track Maintenance
  • Upgrading to heavy rail
  • Installation of 8 ft. ties
  • Higher capacity switches
  • Standard ballast
  • Wider clearances
  • Higher load ratings bridges and docks
  • Uniformity of heavy passenger trucks

14
Conversion
  • White Passs current maintenance program is
    intended to ensure safe, reliable passenger
    operations however such efforts greatly enhance
    the efficiency of future conversion
  • The active passenger corridor receives the
    heaviest maintenance and upgrades

15
(No Transcript)
16
Conversion
  • Traffic interruption
  • Revenue is generated through summer tourist
    trains
  • To limit or restrict passenger operations is
    unnecessary
  • Much of the railroad is unused and substantial
    work can be accomplished without hindrance to
    passenger operations

17
Construction Outline
  • Construction is expected to last two years
  • Work performed through seven phases
  • Starting in early January of Year One
  • Ending mid-September of Year Two

18
Construction Outline
  • Year One
  • Phase 1 Construction of rail-barge facility
  • Phase 2 Upgrading of bridges
  • Phase 3 Grade stabilization from Carcross
    to Whitehorse
  • Phase 4, 5 Gauge widening from Carcross to
    Bennett to Skagway
  • Phase 6 Equipment conversion

19
Construction Outline
  • Year Two
  • Phase 6 (continued) Equipment Conversion
  • Phase 7 Gauge widening from Carcross to
    Whitehorse

20
(No Transcript)
21
(No Transcript)
22
Phase One Rail Barge Facility
  • Begins January of Year One
  • Ends May of Year One
  • Allow for construction material to be loaded by
    the manufacturer and shipped directly via barge
  • Be the leading end of Skagways rail-barge
    connection

23
Phase One Rail Barge Facility
  • Construction must be completed prior to the
    cruise ship season
  • Wintertime port construction is common in Skagway
  • All docks in Skagway have been designed or
    adapted to accommodate passenger traffic

24
Phase One Rail Barge Facility
  • Two are immediately suitable for a rail barge
    ramp construction
  • All are deepwater docks
  • Skagway has 25 ft tides and the appropriate ramp
    design would allow for four loading/offloading
    windows per day at the 16 ft stage

25
(No Transcript)
26
Phase One Rail Barge Facility
  • Railroad Dock
  • designed and built to standard gauge rail
    capacity
  • A third rail runs throughout its length
  • No additional rail crossings would be required
  • Additional rail traffic accessing the pier would
    pose no significant threat increase to pedestrian
    traffic

27
(No Transcript)
28
Phase One Rail Barge Facility
  • Ore Dock
  • The former ideal location for such a facility
  • Alaska Marine Line operates a ramp here
  • Land leases have severely restricted any
    potential foot print for freight operations
  • Track geometry in the confined quarters would be
    a design problem
  • Rail access would require additional grade
    crossings through Skagway tourism district

29
(No Transcript)
30
Phase One Rail Barge Facility
  • The City of Skagway exists in a confined valley
  • Waterfront land is leased by White Pass from the
    City
  • Much land has been subdivided and remaining
    portions are not adequate for staging of railroad
    freight

31
Phase One Rail Barge Facility
  • The best means of marshalling barge borne freight
    is to remove it directly from the barge and stage
    it north of town near railroad milepost 3

32
(No Transcript)
33
(No Transcript)
34
Phase Two Bridges, Tunnels, and Clearances
  • 23 Bridges over entire route
  • 14 bridges within Alaska
  • 3 bridges within British Columbia
  • 6 bridges within Yukon

35
Phase Two Bridges, Tunnels, and Clearances
  • To handle the increase in axle loads from
    standard gauge equipment, many bridges require
    upgrading
  • The simplest method is the installation of
    intermediate pony trusses at bridge mid-spans

36
Phase Two Bridges, Tunnels, and Clearances
  • Alaska Subdivision (MP 0.0 20.4)
  • 5 bridges have been recently rebuilt to steel,
    standard gauge capacity
  • 4 require intermediate bents
  • Both short and shallow
  • 2 require extensive upgrading
  • 3 are adequate

37
Phase Two Bridges, Tunnels, and Clearances
  • British Columbia Subdivision (MP 20.4 53.2)
  • 2 have recently been rebuilt to steel, standard
    gauge capacity
  • One is due for rebuild by 2003

38
Phase Two Bridges, Tunnels, and Clearances
  • Yukon Subdivision (MP 53.2 110.0)
  • 3 recently reconstructed to standard gauge
    capacity
  • 3 require extensive reconstruction
  • All short and shallow

39
Phase Two Bridges, Tunnels, and Clearances
  • Only two tunnels exist along the railroad
  • Both in the Alaska Subdivision

40
Phase Two Bridges, Tunnels, and Clearances
  • MP 16 Tunnel
  • Constructed in the winter of 1899
  • 300 ft long
  • Requires no upgrading
  • Current dimensions allow for standard rail traffic

41
(No Transcript)
42
(No Transcript)
43
Phase Two Bridges, Tunnels, and Clearances
  • MP 18 Tunnel
  • Built in 1969 to replace a bridge
  • 700 ft long
  • Built to American Railway Engineer Assoc
    Standards (AREA)
  • However, the portals limit the interior
    dimensions of the tunnel

44
Bridge replaced with tunnel in 1969
45
Phase Two Bridges, Tunnels, and Clearances
  • Clearances
  • No additional right-of-way widening is necessary
  • An intensive maintenance program has actively
    removed close clearances, widened cuts, deepened
    shoulders, and removed rocky outcrops

46
Phase Two Bridges, Tunnels, and Clearances
  • Clearances
  • Historically, White Pass has transported excess
    dimension freight
  • White Pass transported 80 ft lengths of 60 in
    diameter pipe in proof of concept test for
    Foothills Pipeline
  • White Pass operates with some standard gauge
    equipment

47
(No Transcript)
48
(No Transcript)
49
(No Transcript)
50
Phase ThreeRight-of-Way Stabilization
  • Carcross (MP 65.7) to Whitehorse (MP 110.0)
  • Little maintenance has occurred over this
    northernmost section since 1982
  • A dedicated crew will work six months beginning
    May 1 of Year One
  • The crew will be comprised of one work train and
    supporting heavy equipment

51
Phase ThreeRight-of-Way Stabilization
  • Primary focus of crew
  • Restoring shoulder width
  • Replacing wooden culverts with aluminum
  • Widening cuts

52
Phase ThreeRight-of-Way Stabilization
  • It is expected that over 200 000 yds of material
    will be removed or distributed along the
    right-of-way
  • All of the material required is available from
    natural sources within designated railroad land
    rights

53
Phase ThreeRight-of-Way Stabilization
  • Existing track
  • Much of the subgrade is a mixture of sand and
    silt
  • Cleaned ballast was placed during 1960 overhaul
    throughout much of this section
  • Rail, ties, and accompanying track hardware is
    inadequate for standard gauge traffic and will be
    addressed during Year Two

54
Phase ThreeRight-of-Way Stabilization
  • No rail operations are underway over this track
    portion and construction crews can operate
    unimpeded
  • Access to the track is available via the Klondike
    Highway

55
(No Transcript)
56
(No Transcript)
57
Phase FourGauge Widening Carcross to Bennett
  • Carcross (MP 67.7) to Bennett (MP 40)
  • This section of track follows the shore of
    Bennett Lake passing light grades through fine
    soil terrain near Carcross becoming rock near
    Bennett
  • No operations are underway over this section

58
Phase FourGauge Widening Carcross to Bennett
  • Heavy reconstruction has taken place within the
    past six years
  • Shore stabilization
  • 100 long tie renewal
  • Extensive surfacing
  • Ballasting
  • Much of the rail is new 100 lb/yd and adequate
    for standard gauge traffic

59
Phase FourGauge Widening Carcross to Bennett
  • Track and right-of-way is in condition suitable
    for straightforward gauge widening
  • No operations take place over this section
  • Two crews, totaling thirty people, would be
    required
  • Work will closely resemble the process of a rail
    relay

60
Phase FourGauge Widening Carcross to Bennett
  • Two people will precede crew one removing spikes
    and anchors on the west rail
  • The east rail will remain in place serving as a
    gauge rail
  • The crew will proceed with a hydraulic gauging
    machine moving the unspiked rail 10.25 in. and
    gauge spike

61
Phase FourGauge Widening Carcross to Bennett
  • The next crew, in the same fashion, will move the
    east rail 10.25. in and gauge spike
  • The bulk of the crew will complete all spiking,
    anchoring, leveling, and lining
  • Standard gauge production rail laying equipment
    will be used
  • The crew will leave behind standard gauge track

62
Phase FourGauge Widening Carcross to Bennett
  • The primary crews will ignore track
    discontinuities to maintain momentum
  • Ie grade crossings, turnouts, yards
  • A follow up crew will address these potentially
    time consuming tasks

63
(No Transcript)
64
Phase FiveGauge Widening Bennett to Skagway
  • Bennett (MP 40.4) to Skagway (0.0)
  • At Bennett, crews will be entering the active
    passenger corridor
  • Timing is important
  • The construction crew should arrive Bennett near
    the time Bennett Service is suspended
  • Expected around mid-August

65
(No Transcript)
66
Phase FiveGauge Widening Bennett to Skagway
  • From Bennett, construction can proceed toward
    Fraser
  • Crews should arrive Fraser near the time Fraser
    service is suspended
  • Expected around mid-September

67
(No Transcript)
68
Phase FiveGauge Widening Bennett to Skagway
  • From Fraser, construction can proceed toward the
    summit
  • Crews should arrive at the summit near the time
    total passenger services are suspended near late
    September
  • After this date, crews have total access to the
    passenger corridor

69
(No Transcript)
70
Phase FiveGauge Widening Bennett to Skagway
  • In Skagway Yard, a crew of eight to ten will be
    at work converting switches, road crossings, and
    some short lengths of three-rail track
  • At the end of the summer of Year One, the
    essential portions of the Skagway Yard will be
    ready to accommodate standard gauge stock

71
Phase FiveGauge Widening Bennett to Skagway
  • By the Fall of Year One, the railroad will be
    standard gauge from Skagway to Carcross

72
(No Transcript)
73
Phase Six Equipment Conversion
  • The Skagway Facility can dedicate itself to
    equipment conversion after the suspension of
    passenger service
  • Nearly all of White Pass equipment in service is
    historical passenger equipment
  • The process would proceed through the winter
    ending before start of season Year Two

74
Phase Six Equipment Conversion
  • Only passenger equipment will be focused on for
    conversion
  • Freight and work equipment can be easily replaced
    with more efficient leased or purchased standard
    gauge equipment brought in by barge

75
Phase Six Equipment Conversion
  • Nearly all of the passenger fleet has been
    transitioned to a uniform, steel truck design
    which can be easily converted to standard gauge
  • A stockpile of standard gauge components can be
    on hand early via barge

76
Phase Six Equipment Conversion
  • The conversion of equipment would be a
    straightforward
  • The car enters the shop
  • Is jacked up
  • Narrow gauge trucks and brake rigging removed
  • Standard gauge trucks and rigging installed

77
Phase Six Equipment Conversion
  • White Pass locomotives are wholly obsolete with
    their technology dating back to the 1950s
  • One modern, standard gauge locomotive would
    easily replace four existing White Pass
    locomotives
  • New locomotives could be purchased and/or leased
    for a significantly lower cost

78
(No Transcript)
79
Phase Seven Gauge Widening Carcross to
Whitehorse
  • Carcross (MP 67.5) to Whitehorse (MP 110.0)
  • The existing track over this section would be
    converted during the spring and summer of Year Two

80
Phase Seven Gauge Widening Carcross to
Whitehorse
  • All new track supplies could be brought to
    Skagway via barge and taken directly to Carcross
    on standard gauge cars
  • This will provide the most striking metamorphosis
  • This will also be the most management intensive
    part of construction

81
Phase Seven Gauge Widening Carcross to
Whitehorse
  • All new track supplies would be brought to
    Skagway via barge and taken directly to Carcross
    on standard gauge cars
  • First, a crew working north will widen gauge as
    previously outlined
  • The track will be temporarily spiked on the
    existing narrow gauge ties

82
Phase Seven Gauge Widening Carcross to
Whitehorse
  • Second, a standard gauge work train will proceed
    north distributing new, 115 lb/yd rail and ties
    at night
  • During the day, a crew will lay the new rail and
    gauge spike, still using narrow ties

83
Phase Seven Gauge Widening Carcross to
Whitehorse
  • Third, a crew using standard gauge production
    equipment will insert new ties and complete the
    conversion
  • This is concluded with a ballast train and
    surfacing crew
  • Work will progress at 3 miles per week
  • Work is to be completed by mid-September

84
Cost
  • This cost assessment is a broad scope analysis of
    projected costs

85
Cost Phase One
86
Cost Phase Two
87
Cost Phase Three
88
Cost Phase Four
89
Cost Phase Five
90
Cost Phase Six
91
Cost Phase Seven
92
Summary
93
(No Transcript)
94
(No Transcript)
95
Questions
Write a Comment
User Comments (0)
About PowerShow.com