Title: Pixel Support Tube and Related
1Pixel Support Tube and Related
- November 9, 2001
- Pixel Day
- E. Anderssen, LBNL
2Overview
- Status of Work, technical and other
- PST and Supports
- Pixel Supports
- Service/Beampipe Supports
- Immediate plans
- Prototyping in 02
- Discrepancies
- All along the way
3Chain of Support for PST to Cryostat
Side C
Side A
ID Flat Rail
View from topall Tube Supports are Horizontal
and Co-planar
TRT
SCT
PIXEL
SUPPORT
TUBE
Support Positions are shown, But constraint
conditions are Not indicated here.
ID Vee Rail
Properties TBD
Constraint TBD
4Support Conditions of Beampipe
- Beampipe Cruciform Supports align with Stiffest
part of PSTthe end flanges - All support planes on frame are wires allowing
longitudinal (axial) float - One Z-Fixture is foreseen to take up ATLAS
Access/Opening loads
5Pixel Support Tube Mockup
- Mockup in three pieces to simulate independent
parts of tube - Goal is for full length of entire tube to
simulate all installation scenarios - Detector rails are removable, should modification
be necessary - Intend to run installation tests in 02
6Rail Design in Support Tube
Vee and Flat rails were chosen to provide
pseudo-kinematic support for the detector during
delivery to the support points Rails are used
only for delivery, not support
mockup
7PST Important Features
10
45
End Support
30
Hoop Hat Stiffeners (section view)
Bolt flanges
End Supports
Sct mount pads
End Plugs (1 mm equiv. carbon sheet)
8Support Flange Bonded Assembly
Old design - now gone for independent thermal
barrier
Flange Face (machined layup)
Stiffeners (layups)
T-nuts (bonded)
Flange base (Layup)
9Slider design - materials testing
- Friction Tester nearing completion
- Applies variable pressure
- Measures angular acceleration
- Slides sample against interchangeable disk of
given material
Mass provides normal force
position is movable along arm
M
arm hinge
turntable (carbon disk)
slider to be tested
Encoder on shaft measures acceleration
M
10Gravity Sag Calculations
Carbon
Glass
Â
DY .57 mm
DY 1.6 mm
Whole Tube Sags at ends during operationit is
intended to remove this sag when Reattaching
supports after installation of Forward ID ? Note
Sag is with Package in placemuch less without
11Reaction Loads On SCT
Vertical Bending Both Ends
Horizontal Bending
12Flexure Block interface to SCT Penetration
SCT Thermal Barrier Penetration
This interface must take same loads as applied to
FlexureWill know them well after Joint Model is
run
?Will look at simple feasibility with current
(infinite stiffness) loads ?Will iterate size if
indicated by ROM calculation
13Flange Envelope
May change By 5mm to 806?new structure added
Interlink
796?800
785?792
811
775?780
806
SCT BARREL 3
765
SCT Forward Envelope
261
260
257?259.5
251
248
requested Changes
245?246
242
244
240
Barrel Mount Flange
Pixel Support Tube (Barrel Region)
Pixel Support Tube (forward)
795?799
700
Dimensions from 11 ID Layout May 01
14Flange Envelope
Interlink
800
811
806
792
SCT BARREL 3
780
765
SCT Forward Envelope
261
260
255
252
251
shim
254
246
shim
242
244
240
Barrel Mount Flange
Pixel Support Tube (Barrel Region)
Pixel Support Tube (forward)
799
700
New Proposed Envelopesnot yet agreed
15Z-Flexure (Side A)
View Direction
Thermal Barrier squeezed in here
Metal Insert Bonded in
Cut Plane
Access hole Thru Service Rail
Dowel pins have line fit
Insulator (G10) or Al203
Gap filled After picture
Support Tube Mount Pad M55J
16Pixel Supports
17Pixel Package Assembly
Mockup Pixel Frame shown
18Tension/Compression Transmission through
structures not services
Clips register to Buttons on Frame and
Service/Beampipe support structure Gaps allow
Phi offsets of up to /- 1mm while only 0.25mm
longitudinally
19Wire Planes supported by Pulleys
Wires not modeled, beampipe not shown
20Tubes route cables to BarrelSeparate blocks at
Forward end
21Services Supported By Framework
22Service quarter panels supported by framework
23Need to adjust length of Tube or Support Plane
location of VI
24Outside view of patch Panel
25Section View of patch Panel
26Barrel End of Support Structure
27PST Prototyping Plans
- Short Mandrel
- 1 foot long - 1 for glass, 1 for carbon
aluminum or steel - Dry-run in autoclave to determine thermal
response - Determine final diameters from test layups
- Full Size Mandrel (forward length)
- Quotes already received
- Approximately 14,000 to 20,000 USD
- 8 Weeks delivery
- Plans to Fabricate forward prototype in glass
- All flanges and rail features
- Use for production forwards if diameters are
correct - Implications of Glass Forwards/Carbon Barrel on
prototyping plans must be more fully assessed - Insertion Testing
28PST Prototypes in ETC 02
- Includes
- Friction Testing
- Material Test Panels
- Foot Long prototypes
- End-Plug Prototype estimated as ½ production
total - Gray area
- Calling first Forward Tube a prototypeProduction
monies all in FY03, but need to order tooling
and start fab in 02 - Missing prototype flexure mounts (as noted in
1.1.1.1.3.5) - Prototype End Plate buried in Frame estimate,
but included Pixel mounts (5k 01, 10k 02) - Monies for assembly testing of Insertion mockup
spread over a few efforts and called testing
hard to track if appropriate levels have been
assigned
29Service Support Prototypes 02
- Now includes Beam Vacuum Support Structure
- Prototype in 02 already includes bond
fixtureneed to increase cost some to account for
additional scope of VI support, but this saves
overall by not having entire extra fixture for VI
support - Intention for 02 to build 1 quarter panel
support and 2 service panelsstill valid - Need to build Full VI support for both
installation testing and to support services - Needs to be real for use in case pixels are
late - Needs to have real rail interface (unless
replaceable interface) - Need to add cost to this section of WBS, or make
new WBS for Beam pipe support
30Recent Changes and Estimate of Impact
- Change of Forwards to Quartz fiber 30k
- Additional Shell tool 14-20k
- Additional Hat stiffeners 120-160 Man hours
M-tech - Introduction of Independent SCT Thermal Barrier
35k - Throw away 3-4 man months LBL/Junior Eng Design
time - Accrue additional 2-3 man months re-design of
Flange/Flexures - Increase in scope to include Beam Vacuum Supports
110k - Design time not assessed
- Attempt to use/re-use as much fixture costs as
possible - Estimate 25k Material/200hr Shop/300hr M-tech
(REAL) 03 - Estimate 10k Material/200hr Shop/300hr M-tech
(prototype) 02 - (Est. based on cost of End Plug and fixturing,
using same tool as service panel support
structure - PST End Support (former Beam Vacuum Support) not
included in cost estimates yet. - PPI/Endplug Thermal barrier increase in
Complexity - Current Estimate based on segmented flat panel.
Cost will increase if tool is needed to make
other than a flat shape.