1
Linden Board of EducationFacility Projects
2005 - 2006
  • 09/21/05

2
SCHOOL 1
3
New exterior entrance to elevator (Rear of
Building)
4
New exterior entrance to elevator (Rear of
building)
5
New exterior entrance to elevator (Rear of
Building)
6
New connecting corridor to annex of
building (Rear of Building)
7
New connecting corridor to annex of
building (Rear of Building)
8
New corridors 4th floor
9
New classroom 4th floor
10
New classroom 4th floor
11
New classroom 4th floor
12
New bathroom 4th floor
13
New bathroom 4th floor
14
Painting of all corridors and stairwells (Main
Building)
15
New concrete walkway Main entrance
16
New concrete walkway Main entrance
17
SCHOOL 5
18
New main entrance driveway with parking area
19
New main entrance driveway with parking area
20
SCHOOL 6
21
Painting of all classrooms
22
Painting of all classrooms
23
Painting of all classrooms
24
SCHOOL 8
25
Installation of new fire escape at rear of
gymnasium
26
Installation of new fire escape at rear of
gymnasium
27
SCHOOL 9
28
Installation of new overhead garage door (boiler
room)
29
Installation of new classroom lighting
fixtures (BEFORE PICTURE)
30
Installation of new classroom lighting
fixtures (BEFORE PICTURE)
31
Installation of new classroom lighting
fixtures (AFTER PICTURE)
32
Installation of new classroom lighting
fixtures (AFTER PICTURE)
33
SCHOOL 10
34
Removal of existing carpet floor and installation
of new vinyl floor tile (Room 119)
35
Removal of existing carpet floor and installation
of new vinyl floor tile (Room 121)
36
MCMANUS
37
Removal of asbestos floor tile and installation
of new vinyl floor tile in all corridors
throughout building
38
Removal of asbestos floor tile and installation
of new vinyl floor tile in all corridors
throughout building
39
Installation of new lighting in gym locker rooms
and gym locker room bathrooms (boys and girls)
40
Painting of locker rooms and bathrooms (Gym)
41
Installation of new bathroom fixtures (sinks,
toilets ect.)
42
Cornice to be painted
Painting of exterior cornice (Before picture)
43
Painting of exterior cornice (Before picture)
44
Painting of exterior cornice (Before picture)
45
Painting of exterior cornice (Completed)
46
Painting of exterior cornice (Completed)
47
Painting of exterior cornice (Completed)
48
SOEHL
49
Repair of sidewalks and driveway apron
50
Installation of new exterior rubber playground
surface (behind gym)
51
Installation of new exterior rubber playground
surface (behind gym)
52
New A/C unit
Installation of new exterior rubber playground
surface (behind gym)
53
Installation of new air-conditioning system for
main office suite
54
New ceiling diffusers
Installation of new air-conditioning system for
main office suite
55
Painting of all corridor and stairwells
56
Painting of all corridors and stairwells
57
Painting of all corridors and stairwells
58
Painting of the Auditorium
59
Painting of the Auditorium
60
HIGH SCHOOL
61
Installation of new telephone system and (40)
forty telephones
62
Installation of new telephone system and (40)
forty telephones
63
Installation of new telephone system and (40)
forty telephones
64
Complete the installation of the new fitness
center
65
Complete the installation of the new fitness
center
66
Complete the installation of the new fitness
center
67
Complete the installation of the new fitness
center
68
ACADEMY
69
Installation of new lighting for the TV Studio
70
Installation of new lighting for the TV Studio
71
Installation of new vinyl floor tile in
instruction area of the ROTC Room
72
Installation of new vinyl floor tile in
instruction area of the ROTC Room
73
Installation of new roof over lower section of
building
74
Installation of new roof over lower section of
building
75
Installation of new roof over lower section of
building
76
Installation of new roof over lower section of
building
77
Installation of new roof over lower section of
building
78
Installation of new roof over lower section of
building
79
Concrete footings for new addition
80
Concrete footings for new addition
81
Concrete footings for new addition
82
Concrete footings for new addition
83
Concrete footings for new addition
84
Elevator piston
Concrete base and piston for new elevator
85
New electrical transformer
Electrical transformer for new addition
86
Electrical transformer for new addition
87
ATHLETIC FIELD
88
New retaining wall
89
New retaining wall
90
Long jump area
New retaining wall
91
Long jump area
New retaining wall
92
Long jump area
New entrance
New stairway entrance/exit to Gibbons Street
93
New entrance
Long jump area
New stairway entrance/exit to Gibbons Street
94
Pole vault area
New football field
95
New lighting
New football field
96
New football field
97
Long jump area
New football field
98
Long jump area
New football field turf
99
Long jump area
New football field turf
100
Long jump area
New football field turf
101
Long jump area
New football field turf
102
Long jump area
New football field turf
103
Long jump area
New football field turf
104
Long jump area
New football field turf
105
Long jump area
New football field turf
106
Long jump area
New football field turf
107
Long jump area
New football field turf
108
Long jump area
New football field turf
109
Long jump area
New tiger logo at midfield
110
Long jump area
New tiger logo at midfield
111
Long jump area
New tiger logo at midfield
112
ADMINISTRATION BUILDING
113
Ceiling mounted unit
New heating air-conditioning systems Superintend
ents, Assistant Superintendents Business
Administrators offices
114
New heating air-conditioning systems Superintend
ents, Assistant Superintendents Business
Administrators offices
115
New heating air-conditioning systems Superintend
ents, Assistant Superintendents Business
Administrators offices
116
Linden Public SchoolsLinden, New Jersey Joseph
E. MartinoSuperintendent of Schools Rocco
Tomazic, Ed.D.Assistant Superintendent of
Schools Kathleen A. GaylordBusiness
Administrator/Board Secretary Lawrence
MirandaMaintenance Supervisor
Write a Comment
User Comments (0)
About PowerShow.com