The Big Dig - PowerPoint PPT Presentation

1 / 20
About This Presentation
Title:

The Big Dig

Description:

... Ted Williams Tunnel, the Zakim Bunker Hill Bridge, and the Rose Kennedy Greenway. ... Ramp D connects the Ted Williams Tunnel westbound to Interstate 93 ... – PowerPoint PPT presentation

Number of Views:1250
Avg rating:3.0/5.0
Slides: 21
Provided by: informatio125
Category:
Tags: dig | kennedy | ted

less

Transcript and Presenter's Notes

Title: The Big Dig


1
The Big Dig
  • Tunnel Failure in Boston, Massachusetts

2
Outline for our Presentation
  • What is the Big Dig and some other general facts
    about it
  • Planning for the project and what it took to
    start it
  • The construction and various problems it had

3
What is the Big Dig?
  • The Central Artery/ Tunnel Project (unofficially
    known as the Big Dig) was a huge project that was
    designed to reroute Interstate 93 (The main
    highway in Boston) into a 3.5 mile tunnel under
    the city.

4
More Facts About the Tunnel
  • This project is the single most expensive high
    project ever done in America.
  • The project was estimated to cost 2.5 billion
    dollars in 1985 but to the day the U.S. has spent
    over 14.6 billion dollars on the project.
  • Along with the tunnel the project also included
    the Ted Williams Tunnel, the Zakim Bunker Hill
    Bridge, and the Rose Kennedy Greenway.

5
The Start of the Big Dig
  • The idea for the Big Dig was first thought of in
    the 1970s though planning for it did not start
    until 1982.
  • It was not until 1987 that the bill was passed by
    the U.S. congress to give sufficient funds for
    the project.
  • The tunnel was proposed because of the
    constantly congested streets in Boston.
  • The tunnel was proposed to replace the six lane
    central artery that runs through there.

6
The Central Artery
  • The is what the dig
  • looked like during its
  • construction heading
  • South bound.

7
Planning
  • 1983- Environmental impact studies began,
    approved in 1985
  • 1987- U.S. Congress passes bill for Federal
    Funding allocating 755M for the project.
    President Regan initially vetoed the project but
    was overrode by Congress.
  • 1991- Ground was first broken for Big Dig

8
Breaking Ground
  • In addition to political and financial
    difficulties, the project faced several
    environmental and engineering obstacles.
  • Constructions area was largely landfill, and
    included existing subway lines as well as many
    pipes and utility lines that would have to be
    replaced or moved.
  • Many unexpected geological and archaeological
    obstacles were found, ranging from glacial
    remains to foundations of buried houses and a
    number of sunken ships lying within the
    construction area.
  • More concerns included release of toxins by the
    excavation and the possibility of disrupting the
    homes of millions of rats, causing them to roam
    the streets of Boston in search of new housing.

9
Construction Stages
  • Engineers had to use high-tech and expensive
    construction techniques in order to allow traffic
    to flow with out restriction.
  • In order to support the existing freeway above
    the city streets, engineers built 120 ft.-deep
    concrete walls upon which the highway could rest.
  • The Charles River crossing was one of the most
    controversial aspects of the project, as it was
    difficult to find a cost effective way to cross
    the River. The Zakim bridge was the final
    decision, which is the worlds widest cable
    stayed bridge.

10
(No Transcript)
11
Finishing Touches
  • Two major companies, dozens of sub-projects, and
    over 5,000 workers worked to finish the project.
  • Boston Began opening various section of the
    underground highway as early as January of 2003
    and was fully open January 13th 2006.
  • In 2004 the elevated Central Artery (I-93) was
    dismantled.

12
Big Dig Problems
  • The project was estimated at 2.5 billion in
    1985, but total expenses eventually surpassed 15
    billion.
  • On July 11, 2006, the I-90 connector tunnel was
    closed indefinitely as twelve tons of ceiling
    concrete in the tunnel collapsed on a car killing
    a woman and injuring others.
  • After doing several experiments, engineers
    determined that substandard materials were used,
    that may have caused several leaks in the ceiling
    as well as the collapse.

13
(No Transcript)
14
(No Transcript)
15
(No Transcript)
16
Romney Takes Action
  • Romney hired an Illinois consulting firm to do a
    stem to stern inspection of the site
  • Ordered July 14th (4 days after incident)
  • Roads were found to be, fundamentally safe
  • Many Problems found throughout the site

17
Problems
  • Bend in a bracket holding a cable that supports 1
    million pounds of pressure
  • Bolt-Epoxy system failed
  • Concrete cracks in the support
  • Fire Alarm and Detection System need improvement
  • Ventilation System

18
Green- Viaduct Orange-
Transition Yellow- At Grade Blue-
Tunnel
http//www.massturnpike.com/img/big_dig/multimedia
/maps/completion_lg.jpg
19
Ted Williams Tunnel
  • Ramp from South Boston to Ted Williams Tunnel
    opened in August (Eastbound Lanes).
  • Ramp D opened last Wednesday Nov 22nd
  • Ramp D connects the Ted Williams Tunnel westbound
    to Interstate 93
  • The reopened ramp represents only about 10
    percent of the total area of the Big Dig tunnels
    and ramps that have been shut down. Other
    sections could take months to inspect and reopen,
    Romney said.

20
Bibliography
  • http//www.masspike.com/bigdig/index.html
  • http//en.wikipedia.org/wiki/Big_Dig
  • http//www.boston.com/news/specials/big_dig_ceilin
    g_collapse/
  • http//www.thebostonchannel.com/news/10382277/deta
    il.html
Write a Comment
User Comments (0)
About PowerShow.com