St Francis Bay Beach Trust

1 / 49
About This Presentation
Title:

St Francis Bay Beach Trust

Description:

St Francis Bay Beach Trust. Presentation to the Minister of ... One between Anne Avenue and Grannies Pool. The second between Anne Avenue and Umzumawethu ... – PowerPoint PPT presentation

Number of Views:85
Avg rating:3.0/5.0
Slides: 50
Provided by: Ala788

less

Transcript and Presenter's Notes

Title: St Francis Bay Beach Trust


1
St Francis Bay Beach Trust
  • Presentation to the Minister of Environmental
    Affairs Tourism Pretoria - 19 April, 2006

2
St Francis Bay Using Innovation in Ensuring a
Sustainable Future within an Integrated
Community
  • Beach Restoration Using the Best Available
    Environmental Approaches to Secure Long Term
    Sustainability Economic Growth

3
The St Francis Bay Key Issues
  • A Brief History of St Francis Bay
  • SFB was established in the early 1950s as a
    holiday village which included the first Marina
    in South Africa
  • It was developed using a strict building code
    with white houses and black roofs.
  • Many of those who bought properties in the
    Village were also environmentally aware and were
    keen to preserve the special aspects present in
    the area.
  • 50 years on St Francis Bay is one of the premier
    holiday destinations in the Eastern Cape and
    still retains many of its original Special
    Aspects.

4
The St Francis Bay Key Issues
  • The Opportunities and Threats
  • SFB as a holiday destination is heavily reliant
    on tourism and its beach for its continued growth
  • The Beach has been disappearing over the last 20
    years at an average rate of 2 3 meters per year
  • 2005 saw major problems including severe erosion
    of the Beach, prompting questions on the
    long-term economic viability and future of the
    Village
  • As a result of previous lack of success the SFB
    Beach Trust was established to not only Save Our
    Beach but also to secure our local economy for
    all residents.

5
SFB Beach Erosion 11/2005
6
SFB Beach Erosion 11/2005
7
The St Francis Bay Key Issues
  • The Opportunities and Threats
  • There are 48 houses situated directly on the
    beach front. Many of these homeowners have been
    forced to construct rock revetments to secure
    their homes from the sea which has only been
    partially effective.
  • The majority of these beachfront homes are valued
    upwards of R 5.0 million each. This gives a
    total value for these properties of R 240
    million.
  • If this erosion of the beach continues both the
    tourist potential and properties are threatened.
    We need to Save Our Beach to protect the local
    economy and many existing/future jobs in St
    Francis Bay.

8
The St Francis Bay Key Issues
  • The Opportunities and Threats
  • SFB also has over 45 tourist establishments
    offering visitors differing levels of
    accommodation ranging from 5 Star Guest Lodges to
    basic Bed Breakfasts.
  • The various tourist accommodation and restaurants
    provide employment for well over 250 individuals
    with varying levels of skills.
  • In addition, SFB is also seen as a favored
    location for holiday homes as well as a
    multi-million Golf Estate.
  • This also provides significant additional
    employment in both the construction and tourism
    industry as well as for on-going skills
    development initiatives.

9
The St Francis Bay Key Issues
  • The Opportunities and Threats
  • Sea Vista is an integral part of St Francis Bay
    yet it suffers from years of neglect by the local
    council.
  • It is estimated that up to 2 500 people live in
    Sea Vista. This community is fragmented and
    disfunctional.
  • There is a settled, largely coloured community,
    as well as recent new arrivals, mainly from the
    old Ciskei Homeland area, who live under
    appalling conditions.
  • In addition, a significant component of the
    community are involved in the fishing industry
    which is transient.
  • If St Francis is to succeed then Greater St
    Francis must also prosper. In addition, it will
    be possible to improve the Quality of Life for
    all residents.

10
The St Francis Bay Key Issues
  • The Opportunities and Threats
  • The Eastern Cape suffers from high unemployment
    rates and urgently needs to preserve jobs.
  • For every person employed in St Francis Bay,
    there are at least another 5 to 9 family members
    reliant on that worker, including many in the
    rural areas.
  • As SFB grows there will be further job
    opportunities created, mainly in the tourism
    sector.
  • In addition, the Beach Rehabilitation Project
    will create the opportunity for BEE Initiatives
    linked to the environmental aspects of Saving
    Our Beach. .

11
The St Francis Bay Key Issues
  • The Opportunities and Threats
  • There is a need to secure the long term future of
    the Village which now has over 3 500 permanent
    residents throughout the year, including Sea
    Vista.
  • During the Christmas / New Year Holiday Season
    the population of the Village grows to /- 20
    000.
  • All new SFB developments advertise the beach as a
    major drawcard for both the Village and the wider
    Kouga community/area.
  • The SFB Beach Trust is at this stage fully funded
    by the SFB community which has raised R 1 million
    to complete the initial beach investigation /
    research.

12
Vision 2020 Options for the Future
  • Kouga Municipality Priority Weightings for
    Development Projects 2006
  • Basic Needs/Essential Services 10
  • Job Creation 10
  • Economic Development 8
  • Sustainability 6 Community Well
    Being/Quality of Life 6
  • Income Advantage to Council 6
  • Environmental advantage/sustainability 4
  • Agenda Special Council Meeting 24 February, 2006
  • SFB Beach Project meets all of the above
    criteria

13
The History of SFB Beach
  • An initiative was started in 2001 in an attempt
    to resolve the SFB beach erosion issue.
  • The initiative was an exercise by the Kouga
    Disaster Management Beach Committee. The
    consultants prepared proposals which were
    inconclusive, partly due to lack of adequate
    funding being available from the Kouga Council.
  • In addition, the EIA was not fully funded by the
    Kouga Municipality and as a result was not at all
    comprehensive.
  • The estimated cost of the proposals varied from
    between R 32 m to R 80 m which was not affordable
    or practical.
  • These proposals were not acceptable to the
    community as they were not considered
    environmentally appropriate.

14
Comparative Beach Costs
  • Task Description
  • Feasibility Studies
  • Offshore Wave Data
  • Data Search
  • Inshore Wave Data
  • Beach Profiles
  • Offshore Bathymetry
  • Offshore Sediment
  • Aerial Photography
  • Contingencies
  • Grand Total (Rand)
  • KDMBC SFBBT
  • 300k 230k
  • 420k Incl
  • 30k Incl
  • 58k 25k
  • 30k Incl
  • 120k 25k
  • 50k 15k
  • 5k Incl
  • 200k 50k
  • R 1.21m R 345k (28.5)

15
What Has Already Been Done?
  • The SFB Beach Trust was set up in December 2005
    to raise funds for the Saving Our Beach
    Project.
  • During Christmas 2005 / New Year 2006 over R 250k
    was collected from SFB residents plus pledges
    still to come.
  • ASR Limited from New Zealand, the international
    experts on submerged reefs, were contracted by
    the SFB Beach Trust to investigate what possibly
    could be done
  • Dr Shaw Mead from ASR visited SFB in February,
    2006
  • Data has been collected over the period February
    to April, 2006. This phase will be complete by
    May, 2006
  • ASR are due to present their Draft Report in May,
    2006

16
(No Transcript)
17
ASRs International Client Base
  • ASR have a wide client base in the following
    countries
  • Australia Extensive client list
  • Bahrain
  • Canada
  • Fiji
  • India Includes sustainable development projects
  • Indonesia
  • Malaysia
  • New Zealand Extensive client list
  • United Kingdom Wide variety of clients
  • United States Both East and West Coast
  • ASR are specialists in this type of project

18
Beach Project Budget Revised 04/06
  • Costing - Investigation Design Phases
  • Equipment ASR Fees
  • ASR Fees
  • Investigation 240k
  • Design 340k 580k
  • Local Costs (Estimate)
  • SA Fees/Accom 75k
  • Boat Charter 45k
  • Insurance 5k
  • Computer 10k 135k
  • Contingencies 75k
  • GRAND TOTAL R 780k

19
SFB Overall Beach Costs 2006/7
  • Description
  • ASR Investigation
  • ASR Design
  • Total
  • Grand Total
  • Construction Phase
  • Phase 1 (Reefs)
  • Phase 2 (Beach)
  • Phase 3 (Dunes)
  • Phase 1 Phase 2
  • R 350k
  • 430k
  • R 350k 430k
  • R 780k
  • R 6.5 R 13.0 m (est)
  • Still being researched
  • Not yet available

20
Beach Project Progress Report
  • Since concluding the formal contract with ASR the
    following have been completed
  • A full bathymetric survey of the Bay has been
    completed with over 42 500 readings being
    collected.
  • The Aquadopp Profiler has been installed in the
    Bay to measure the inshore waves and currents.
    The first and second data sets (4 weeks each)
    have already been sent to ASR in New Zealand for
    analysis
  • A full sediment sampling exercise of both the Bay
    and Kromme River Estuary has been completed with
    the results also having been sent on to ASR for
    analysis
  • The SFB Beach Trust has been formally constituted
    and registered with the first Trustees being
    Antony Ball, Pat Kelly and Emlyn Horne.

21
Beach Project Initial Visit Report
  • Following the visit from Dr Shaw Mead during
    February, 2006 we have received a copy of his
    initial visit report.
  • In this report Dr Mead concludes that all the
    indications are that submerged reefs are both a
    viable and cost effective option for the St
    Francis Bay beach.
  • In addition the initial indications are that
    three reefs will in all probability be required.
  • One between Anne Avenue and Grannies Pool
  • The second between Anne Avenue and Umzumawethu
  • A third between Umzumawethu and the Kromme River
    mouth
  • These preliminary findings will be confirmed once
    all the data has been collected and analyzed by
    ASR

22
(No Transcript)
23
SFB Beach Project Update
24
Beach Project Report Back
  • Dr Shaw Mead will be visiting St Francis Bay from
    15 to 17 May, 2006 to provide full details on the
    ASR recommendations
  • The SFB Beach Trust will be considering the ASR
    proposals as well as holding a Public Meeting
    while Shaw Mead is in SFB.
  • Following the visit and depending on the formal
    ASR recommendations it is likely that the design
    phase will commence in June/July, 2006
  • The anticipated design phase will be completed in
    time for the SFBRA AGM in December, 2006. This
    will include estimated costs of the construction
    phase

25
Beach Project Phase 2 Design
  • It is estimated that this stage will take 5 6
    months to complete including
  • Detailed Design Impact Assessment 12
    weeks
  • Physical Modeling 4 6 weeks
  • Construction Drawings Specifications 3 4
    weeks
  • Reporting 2 weeks
  • Presentation of Study Findings 2 days
  • It has been agreed that Dylan Anderson will
    assist ASR in New Zealand during this part of the
    Beach Project
  • We anticipate that this phase of the project
    should be completed by December, 2006 for the
    SFBRA AGM

26
Beach Project Construction Phase 3
  • At this stage it is too early to cost the
    construction phase which includes
  • The development of tender requests that conform
    to the methods and materials identified in Phases
    1 2
  • Selection of competent contractors
  • Development of Approved Contracts
  • Site Preparation
  • Reef Fabrication, Deployment Filling
  • Early ESTIMATES based on past experience would
    seem to indicate a cost in the vicinity of
    between NZ 1.5 and NZ 3.0 (SAR 6.5 SAR 13.0
    m) This has been calculated at an exchange rate
    of NZ 1 to SAR 4.4

27
Beach Project Construction Phase 3
  • Reef construction cost estimates will be
    available in December, 2006 with a start date for
    Phase 1 of the construction part of the project
    planned for early 2007.
  • The construction phase will require innovative
    funding from a variety of possible sources
    including
  • National Government (Dept of the Environment
    Tourism).
  • Provincial and Local Government major funding
    constraints
  • DBSA plus other sources including the SFB
    Community.
  • In looking at the ASR website it is considered
    that the SFB Trust Fund approach is the best for
    this type of community project (similar to other
    global projects of this type).

28
Beach Project Overview
  • It is estimated that the various stages will be
    spread over the following broad time frame
  • Investigative Phase to be Completed June, 2006
  • Design (including Cost Estimates) Dec. 2006
  • Construction/Tender Process ASR Jan/Feb 2007
  • Reef Construction to Commence April/May 2007
  • Depending on the costing and phasing of the reef
    construction this may extend through to 2008/9
  • During the reef construction phase the whole
    question of Beach Re-nourishment and Dune
    Sculpting/Re-vegetation will be extensively
    considered and costed in detail.

29
SFB Overall Beach Estimates 2006/9
  • Equipment Required
  • Dredger
  • Pump House
  • Pumps Equipment
  • Piping
  • Grand Total
  • Construction Phase
  • Phase 1 (Reefs)
  • Phase 2 (Beach)
  • Phase 3 (Dunes)
  • Grand Total
  • NZ SA Rand
  • 300k R 1.32m
  • 250k Available
  • 250k R 1.10 m
  • 750 R 3.30 m
  • 1.55m R 5.72 m
  • R 6.5 R 13.0 m (est)
  • R 5.72 m (est)
  • Not yet available
  • R 18.72 m (est)

30
Beach Project Adding Value
  • ASR statistics show that for every /Rand 1 spent
    on a project such as the SFB Beach Project, a
    minimum of /Rand 20 flows into the community
    as a direct result of this investment. This will
    provide major spin-off to SFB
  • We are looking at the SFB Beach Project as a
    fully integrated sustainable development project
    in our wider community in order to secure the
    future of the Village.
  • One of the direct spin-offs of the project will
    be an increase in tourism opportunities in
    Greater St Francis
  • As a result of the growth in tourism, there will
    be a direct increase in employment opportunities
    and skills development for the wider SFB
    community.

31
Beach Project Adding Value
  • It is interesting to note that following the SFB
    initiative with ASR, the Nelson Mandela Metro
    have also entered into a contract with ASR on a
    similar project for both Pollock and St Georges
    Beaches in Port Elizabeth.
  • In addition, we have been approached to assist in
    the PE bathymetric survey. This will depend on
    the availability of our team working on the SFB
    Beach Project.
  • PE also believe that one of the direct spin-offs
    of the project will be an increase in tourism
    opportunities.
  • This initiative is part of the advance
    preparations by the Nelson Mandela Metro for the
    2010 World Cup.

32
Beach Project The Future
  • A comparative situation was experienced at
    Saldahna Bay in the Western Cape some years ago
    where a number of houses fell into the sea due to
    similar coastal erosion.
  • In this case Government made funds available in
    order to rectify the situation. We believe R 39m
    was allocated.
  • St Francis Bay deserves at least equal
    consideration and attention as the Village relies
    almost exclusively on eco-tourism for the bulk of
    its income.
  • We would appreciate the urgent attention of
    National Government to assist in resolving this
    issue with the SFB Beach Trust. It is in the best
    interests of the Greater St Francis community
    that a firm action plan with funding be put in
    place in order to Save Our Beach.

33
Beach Project The Future
  • We would like to see the following steps put in
    place as part of the on-going process
  • We would like to see a Senior Official from the
    National Department of the Environment Tourism
    be nominated to act as a link between the
    Department and SFB Beach Trust.
  • During the visit to St Francis Bay during May,
    2006 by Dr Shaw Mead we would appreciate the
    nominated official being available for detailed
    discussions on the ASR Proposals.
  • We would also appreciate the urgent attention of
    the Minister on how this issue can be best
    resolved. It is in the interests of the whole St
    Francis community that a detailed action plan be
    agreed to Save Our Beach.

34
SFB Beach Trust Contact Details
  • Trustees
  • Antony Ball 011 507 1000 (Office)
  • Pat Kelly 012 4608084 (Office)
  • Emlyn Horne 042 294 1047 (Residence)
  • SFB Beach Trust Sponsor Co-ordinator
  • Alan Tonkin 082 777 1519 (Mobile)
  • Alternatively e-mail info_at_stfrancisbay.org

35
St Francis Bay Beach Trust
  • Rehabilitating the St Francis Bay Beach by the
    Use of Sustainable Development through the
    Environment Tourism

36
St Francis Bay Beach Trust
  • Rehabilitating the St Francis Bay Beach
    Additional Information on Progress

37
Beach Project Phases 1a 1b
38
Beach Project Phase 1a - Completed
  • Mapping of sea bed completed for the Bay from
    Port St Francis to past Kromme River mouth and 2
    nautical miles offshore (December, 2005)
  • Over 42 500 GPS soundings recorded of the sea
    floor which are now being plotted on a chart to
    compare the existing bathymetry of the ocean
    floor with the existing naval survey data (1952)
  • Data sent to ASR in New Zealand for further
    analysis and computer modeling

39
Beach Project Phase 1b 2006
  • Wave and current data being measured using
    inshore data collection methods and modeling
  • Information to be supplied to ASR Limited for
    further analysis and modeling (Wave Watch 3)
  • Proposals to be supplied by ASR regarding the
    design and construction of an artificial reef(s)
  • Costs to this stage to be covered by the SFB
    community. Costs of reef construction to be
    raised from the community and other sources such
    as the DBSA and National Government.

40
Beach Project Original Budget 12/05
  • Costing - Investigation Design Phases
  • Equipment ASR Fees
  • Current Profiler 140k
  • ASR Fees
  • Investigation 250k
  • Design 340k 590k
  • Local Overhead Costs (Estimate)
  • SA Fees/Accom 100k
  • Boat Charter 45k
  • Insurance 15k
  • Computer 10k 170k
  • Contingencies 100k
  • GRAND TOTAL R 1 000k

41
Beach Project for Phase 1 ASR Proposal Updated
April, 2006
  • Site Visit including
  • Diving Video Survey
  • Consultation
  • Construction Investigation 7 days
  • Instrument Deployment 12 weeks
  • Existing Data Review 5 days
  • Numerical Modelling 4 weeks
  • Reporting 2 weeks
  • Presentation of Findings 2 days
  • The above are to be conducted in conjunction with
    the SFB Beach Trust over a period of 4/5 months
    (to end June, 2006)
  • Partially complete/completed

42
SFB Beach Project Update
43
St Francis Bay Using Innovation in Ensuring a
Sustainable Future within an Integrated
Community
  • Beach Restoration Using the Best Available
    Environmental Approaches to Secure Long Term
    Sustainability Economic Growth

44
Our Products
  • We have a number of special SFB Beach Trust items
    for sale to support the Saving our Beach
    initiative
  • Golf Shirts 100 Cotton
  • Beige/Black White/Black _at_ R 175 each
  • T-shirts 100 Cotton
  • Beige Blue _at_ R 125 each
  • Caps
  • Beige/Black Underpeak _at_ R 85 each

45
Our Products SFB Beach Trust
  • We have a number of special SFB Beach Trust items
    for sale to support the Saving our Beach
    initiative
  • We have stock of all the clothing items available
    for sale following the Meeting
  • Please contact our Committee Members who will be
    pleased to assist you with your purchases.
  • All profits go directly into the SFB Beach Trust
    Fund so please support us in this important
    effort
  • In addition all donations to the SFB Beach Trust
    make a difference in Saving our Beach

46
SFB Beach Trust Clothing
47
Our Banking Details
  • Our Banking Details are as follows
  • St Francis Bay Beach Trust
  • Bank Standard Bank Humansdorp
  • Account 281 391 688 Branch Code 050-015
  • St Francis Bay Residents Association
  • Bank Standard Bank Humansdorp
  • Account 082 499 276 Branch Code 050-015

48
St Francis Bay Using Innovation in Ensuring a
Sustainable Future within an Integrated
Community
  • Beach Restoration Using the Best Available
    Environmental Approaches to Secure Long Term
    Sustainability Economic Growth

49
St Francis Bay Beach Trust
  • Rehabilitating the St Francis Bay Beach by the
    Use of Sustainable Development through the
    Environment Tourism
Write a Comment
User Comments (0)