Title: ROOFS
1 Fort Atkinson School District Buildings and
Grounds Long Range Plan Five/Ten-Year
2This long range plan is an attempt to prioritize
needed repairs and/or replacements before they
become emergencies and negatively impact safety
and the rest of the building. This is a living
plan which can and will change. The major
building components that follow, I feel, can have
the biggest impact on a building. This is not to
minimize the importance of the many secondary
items, both listed and yet to be listed.
3ROOFS
- Over 500,000 square feet of roof surface.
- Continued diligence required to keep from falling
behind. Includes maintenance and replacement. - With cost of replacement and area we have it is
necessary to address minimum of one roof area per
year. - It will take 10 years to complete 5 schools
before having to start on High School. - For energy savings insulation is increased as
practical when replacements are done. - Roof types are considered to permit peel off as
opposed to total replacement.
4EXTERIOR MASONRY (BRICK WORK)
- Moisture getting behind and into bricks can
- Cause structural damage by deterioration of
steel. - Create health concerns by development of mold.
- Blow the face surface of bricks off leading to
further deterioration. - Causing bricks to fall from wall.
- Corrective action
- Caulking.
- Tuck pointing.
- Replacement of individual bricks or whole panels.
- Chimneys, whether abandoned (such as by geo) or
not must be maintained or removed. - Currently working on masonry assessment to detail
corrective action.
5HVAC
- In middle of geothermal projects.
- a) Replaced extremely old heating systems.
- b) Partially reduced need for frequent and
- expensive maintenance.
- c) Provided air conditioning where none
- existed before.
- Still have some old equipment that has a need for
more frequent maintenance and/or replacement.
6PLUMBING
- Much of the plumbing components are old with
corroded pipes and frozen valves. - Water heaters are liming up.
- Problems not always obvious until there is a
leak. - Valves are periodically replaced. Piping is spot
replaced when a problem is detected.
7ELECTRIC
- Recently all lamps and ballasts were replaced
with energy saving ones with a payback of
approximately four years. - Fire alarm systems and many electric panels are
antiquated. - During geo projects many fire alarms and electric
panels were partially upgraded. - For all switches and outlets should be labeled to
the circuits. - Light sensors need to be updated and installed
when none exist. - Additional outlets are being installed on an as
needed basis.
8ASBESTOS
- There are varying amounts of asbestos in all
buildings. - Asbestos is abated when it is impacted by any
type of construction, is damaged or at risk of
damage. - Geo project only abated asbestos that was at risk
during construction. - Additional amounts on abandoned equipment should
be abated to eliminate hazard. - Abatement/demo of abandoned boilers can make
space available for other purposes.
9ASPHALT
- We have large areas of asphalt for our parking
lots, drives and playgrounds. - Repairs are necessary to prevent admittance of
water and prevent break up. - All cracks have recently been routed and filled.
Necessary as cracks develop. - Seal coating is necessary to restore oils in
asphalt and extend life of the asphalt. - Paint striping is done annually.
10POSSIBLE FUTURE
- Geothermal for Luther Elementary/Admin.
- Deck over abandoned boiler rooms to provide
additional useable space. - Pursue other sources of energy efficiency.
- Wind
- Solar
- Photo-voltaic
- Burn refuse
- Conservation
11SECONDARY ITEMS
- These items are repaired or replaced as needed.
- Flooring
- Windows
- Doors and Hardware
- Concrete
- Ceilings