Title: CMS Submission to PPGC
1CMS Submission to PPGC
- UK Deliverables
- Status of CMS
- UK Progress Commissioning Plans
- Computing
- UK Physics Programme
- Summary
2The CMS Collaboration
3Compact Muon Solenoid
Total weight 12,500 t Overall diameter 15
m Overall length 21.6 m Magnetic field 4 T
4The UK in CMS
Imperial College
Bristol
Brunel
Leaf Card
Source Card
Electromagnetic Calorimeter Endcaps
Tracker Readout System
Global Calorimeter Trigger
Computing - Software - Simulation - Physics
5LHC Intersection Point 5
CMS is pre-assembled on the surface and lowered
in 17 sections weighing between 300 and 2000 tons
Surface Assembly Hall
Experiment Cavern
Service Cavern(Readout, Trigger, P/S)
6Surface Assembly
Yoke Endcap (YE1)installation done
Muon Barrel Drift-Tube/RPC installation well
advanced 10 sectors in wheels 0,1,2. 2 sectors
in wheels -1,-2.
Magnet complete, coil cold
HCAL being inserted into solenoid
7CMS Schedule Key Dates
- Magnet closed May 06
- Magnet test/cosmic ray challenge June-Aug 06
- ECAL 1st half-barrel (EB) installation Aug 06
SX5 - Service Cavern ready for crates
April-May 06 - HF lowering July 06
- Experiment Cavern ready for crates Jul 06
- First connection to Service Cavern Aug-Sep 06
- Central Yoke SectionCoil (YB0) lowering Nov
06 - ECAL 2nd half-barrel (EB-) installation Oct 06
SX5(Jan-May 07 UXC) Tracker installation
Jan-Feb 07 - ECAL/Tracker cabling complete Apr-May 07
- Heavy lowering complete Feb-Mar 07
- Initial CMS ready for beam 30 Jun 07
- ECAL Endcaps, Pixels installation Dec 07
March 08 - Schedule is tight, with no master contingency
- Options to recover 2 months after Tracker
installation under consideration
8CMS ECAL Endcap (EE)
UK has led EE project from inception - Monte
Carlo simulations - Performance optimisation -
Vacuum Photo-Triode (VPT) RD - Prototype beam
tests at CERN Deliverables - Overall mechanical
design - On-det. electronic design(CERN) -
VPTs (pay 50, test 100) - Mechanical
structures(Russia) - Assembly (with Russia,
CERN)
- Vacuum phototriodes
- - Single stage pmt
- Gain 8 -10 at B 4 T
- Radiation resistant (UV glass window)
- - Q.E. 20 at 420 nm
9EE Status
Electronic noise performance verified with a
detector module (25 channels) mounted on a
Dee (3800 e/channel)
Alignment test of 2 Dees and Ring Flange mounted
on HCAL
Mechanics All major components delivered CMS
Gold Award to TM Engineers (UK)
10EE Future Work
2006 ? On detector electronics production ?
Assembly jigs and tooling completed ? Launch EE
crystal productionSIC (China) ? Assembly of
Dee1 from July 2007 ? Launch EE crystal
productionBTCP (RF) ? Assembly of Dees ?
Installation of Dees 1 2 2008 ? Installation of
Dees 3 4
Delivery of EE crystals is on the critical
pathAssembly schedule tight? Parallel work to
minimise assembly latency Long term UK
commitments - Maintaining and operating the EE -
Maintaining the associated databases -
Understanding and calibrating the detector -
Estimated EID effort 0.25 FTE in 08/09 09/10
EE Commissioning will only START in earnest AFTER
end of Ring Fence
11CMS Tracker
- Two main sub-systems - Silicon Strip Tracker
and Pixel Detector - Silicon Strip Tracker comprises - Outer
Barrel (TOB) - Inner Barrel and Disks
(TIB-TID) - End-Cap (TEC) - 107 Channels, 220m2 Silicon
TIB Layer 2, after burn-in
Cosmics in TEC
TOB
TOB
TEC
TEC
TIB
TID
TIB
TID
PD
PD
12Tracker Electronic System
- UK Deliverables
- Development of readout control system
- Delivery of APV APVMUX ASICs ( 100,000
die, inc spares) - Procurement of Front End Driver (500
modules)
- Status
- APV Project Complete On time, within budget
- FED Procurement underway
- (eXception received a Gold Award)
- Analogue readout
- No on-detector zero suppression
- Optical analogue data transfer
Input Rate 1.2 TBytes/sec Output rate 50
GBytes/sec
13Tracker Future Work
- 2006 Final assembly and integration in TIF
- Four large systems to be assembled and operated
- Test complete tracker in up to 25 units
- Delivery within budget requires staff from
institutes - 2007 Commissioning at Point 5
- Lower, insert, cable, power,
- Commission off-detector electronics first
running - 2008 Operations
- Calibrate and tune performance
- Optimise S/N, cluster finding in firmware
- APV, APV emulator, FED, DAQ, Online Software are
key elements for Tracker to deliver good data - All require UK expertise
- System of 500 complex boards
- ? 1 FTE EID needed long term for maintenance
14Global Calorimeter Trigger
- Vital Role in CMS Trigger
- Electron/? triggers
- Jet Triggers
- Transverse Energy Triggers
- RCT Readout System
- Luminosity Monitoring
Original GCT design was technically challenging
- required very high speed (3GB/s) data
transfer between many boards ? major revision Jan
2006 - Large, powerful FPGAs concentrate algorith
m processing in few locations - Optical links
bring large number of input signals to
processing boards New design to be delivered by
July 07 - UK led with CERN engineering effort
15The New GCT Design
- There are four different types of card
- Source Card (54 needed)
- Translates electrical signals from RCT to optical
- Leaf Card (8 1(m) needed)
- Main algorithm card of the GCT
- Electron and jet finding and sorting, all ET
calculations - Proven design from a satellite project (LANL)
- Concentrator Card (11(m) needed)
- Communicates with rest of Trigger and upstream
DAQ - Wheel Card (2 needed)
- Supports Leaf Cards, performs final jet-finder
calcs
Software Simulation (efficiencies) Testing
and Commissioning Online Monitoring Online
Control
16GCT Future Work
Electron data from ½ RCT
New design can be scaled and commissioned in
stages
- 2006 Development and integration phase
- Aug Integration of Source Card Leaf Card
- Oct Integration Source Leaf Concentrator
- 2007 Commissioning phase
- Jan Commissioning Electron Triggers
- Jul Commissioning Jet Triggers
- 2008 Operations phase
- Respond to actual CMS conditions
- Calibrate, evaluate tune trigger performance
- Trigger must operate with 100 availability ?
- 1 FTE EID needed long term for maintenance
Leaf Cards
Wheel Cards
Concentrator Card
Electron data from ½ RCT
Electron data from ½ RCT
17Computing status
- Major milestones in last two years
- CMS Computing Model fully defined, documented in
Computing TDR - Operational prototypes of all infrastructural
software in place - Major UK contributions to data and workflow
management systems - Integration with Grid systems (WLCG) now well
advanced - Decision taken to adopt new application framework
in May 2006 - Upcoming milestones before 2008
- CSA2006 (computing, software, analysis) 25
scale test of full computing system, October 2006 - Full computing system readiness by April 2007
- Factor-of-two final resource ramp up before April
2008 - CMSUK Deliverables 2006 - 8
- Delivery and support of software components for
CMS - Ramp-up and operation of Tier-1 and Tier-2
computing centres - Maintenance and support of computing system for
UK analysis
18UK Computing Project
- Project organisation
- Organised as single coherent project, covering
GridPP, e-science, centre operations, service
challenge effort - Project currently limited by available manpower
- Further physicist / e-science effort will become
available in 2007 - Vital to retain our expert GridPP / e-science
personnel - Project plan is fully tied to CMS global
milestones - Work areas
- Infrastructural software deliverables (key for
CMS) 2 FTE - PhEDEx manages all offline data BOSS user
interface to the Grid - Computing system ramp-up and support 1.75 FTE
- Software installation and maintainance DB
management - Data challenge activities integration with new
RAL CASTOR system - Physics ops data handling, reconstruction, MC
prod 2 FTE - Documentation, user support for analysis 1 FTE
19Computing Plans Challenges
- Major UK milestones 2006 8
- Jul 06 All UK centres take part in new
framework MC productionnew user support
resources (web-based) in place - Sep Oct 06 Full UK participation in CSA2006
at 25 scale - Dec 06 RAL CASTOR system fully integrated with
CMS system - Apr 07 UK systems ready to take data final
versions of PhEDEx, BOSS funded plan for ramp-up
to full system scale - Apr 08 Ready for full scale data taking
- Key challenges
- Retention of expert staff systems are highly
complex, will require constant tuning in 2007
8 - Scale of Tier-1 hardware resources
- CMS extremely short of Tier-1 storage and CPU
UK is the smallest contributor, despite high
profile on CMS - CMS Computing Model may be compromised in light
of the shortfall - Critical factor for effective physics output in
UK and Europe
20UK Physics Strategy
- Build on existing expertise
- - Tracker
- - ECAL
- - Test beam analyses
- - Simulation studies
- Plan smooth transition from detector/reconstructi
on studies to physics - Emphasise preparations for leading involvement
in early analyses - But balance with developing tools to achieve
longer term physics goals - Develop close working collaboration with
theorists to gain an edge - Work cohesively with the wider world of CMS
- Organisation
- 2 Physics Co-ordinators(One at CERN, One in
UK) - Regular programme of meetings
- UK provides Convenors for 3 of the 8 CMS PRS
Groups (Physics, Reconstruction, Software) - ECAL- e/g
- Tracker- b/t
- Higgs
21CMS Physics TDR
- CMS physics activities are focused on Physics TDR
- Volume 1 Published December 2005
- - Validation of detector simulation
- - Development of reconstruction algorithms
- - Techniques for Calibration, alignment,
synchronisation - Volume 2 To be published May 2006
- - Complete analyses (backgrounds,
misalignment, miscalibration) - - Demonstration of physics capability with 10
fb-1, 30 fb-1 (low luminosity L21033) - Volume 3 Due January 2007
- - Commissioning
- - Start-up procedures
- - First physics
- - Timing of High Level Trigger processing
22UK Contributions to Physics TDR
- Defining content and work, final editing,
detailed contributions
Physics TDR Volume I Detector Performance and
Software
ECAL Intercalibration using W?e?
ECAL Test Beam analysis
Super Module
Beam
23UK Contributions to Physics TDR
Physics TDR Volume II Physics Performance
qqH, H ? tt ? l jet
MSSM bbH/A,H/A ?tt ?2 jet
WW, ZZ Fusion
24First Physics
- Exciting results possible with fb-1 of data
- Concentrate initial analysis efforts on early
discoveries - Exploit connections between detector
understanding, reconstruction selection
algorithms and physics - Focus on e, t, energy-flow, and then g
- eg Study W ? e?, Z ? ee, leading to W' ? e?,
Z' ? ee, (and eventually, H ? ZZ ? eell ) - eg Study W jets, Z jets, Z ? tt, leading
to b-jet tagging, H ? tt searches
25Higgs Physics
- As luminosity increases, concentrate
progressively on Higgs searches - Strong UK interest demonstrated by range of
studies already underway
26Direct g ,Triple Gauge Couplings
- UK leads studies of gluon structure function of
g through prompt g production - Useful results with 1-3 fb-1
- Analysis will provide valuable input for
development of H??? searches - UK also leads TGC study for Physics TDR
- Responsible for Wg, Zg channels
backgrounds - TGC sensitivity requires high L
- If no smoking gun Anomalous TGC could provide
vital signature of BSM
Wjet background to W?
27Summary of CMS Request
28Summary
- CMS assembly is proceeding without significant
technical problems - Solenoid is cold Magnet test and Cosmic
Challenge start in June - Schedule is tight for Ready-for-Beam in July 07
- UK Tracker Readout deliverables on schedule
- ECAL Endcap completion limited by crystal
delivery Install Spring 08 - Revised GCT design is advancing rapidly
- UK-CMS has provided key tools for CMS Computing
(PhEDEX, BOSS) - There are concerns about the CMS Tier-1 capacity
- Continuation of posts currently supported by
GridPP/e-Science is vital - UK is making strong contributions to CMS Physics
TDR - A coherent UK physics programme is underway
29Back-ups
30Tier-1 Issue
- Role of Tier-1 centres
- Long-term storage (curation) of raw data
- Bulk reprocessing of data for reco, skimming,
calibration, analysis - Serving data to Tier-2 centres (all data comes
through Tier-1) - Stores full copy of AOD
- Resource situation for CMS
- European Tier-1 contributors do not have large
CMS fractions - WLCG pledge system results in major shortfall
in Tier-1 resources - This is emergent behaviour funding formulae
may locally make sense in each country, but do
not address the global problem - Individual Tier-1 centres are well-run, but far
below critical mass - Only US, Italian centres approach nominal
Tier-1 size - Strategy
- Funding system must be examined - LHCC asks for
CMS input - Must look at new ways to make maximally efficient
use of resources - Potential danger if redundancy robustness
traded against resources - The CMS computing model may be compromised (in
Europe) - Urgent need for adequate and realistic Tier-1
resources in UK
31WLCG Computing Resources (2008)
32Deployment of effort
33Exclusive diff. Higgs prod. pp? p H p