U.S. Green Building Council Cascadia Chapter - PowerPoint PPT Presentation

1 / 57
About This Presentation
Title:

U.S. Green Building Council Cascadia Chapter

Description:

Craig Hawkins, CHDS Commissioning and Engineering. Todd McGuire, Engineering Economics, Inc. ... LEED Commissioning - Craig. Case Studies - Todd. Company Profile ... – PowerPoint PPT presentation

Number of Views:85
Avg rating:3.0/5.0
Slides: 58
Provided by: bryanw
Category:

less

Transcript and Presenter's Notes

Title: U.S. Green Building Council Cascadia Chapter


1
U.S. Green Building CouncilCascadia Chapter
  • Presentation on Commissioning

Craig Hawkins, CHDS Commissioning and
Engineering Todd McGuire, Engineering Economics,
Inc. Bryan Welsh, Keithly Welsh Associates, Inc.
2
Outline
  • Introduction to Commissioning - Bryan
  • LEED Commissioning - Craig
  • Case Studies - Todd

3
Company Profile
  • Established in 1996, Exclusively Commissioning
    Services
  • Unique focus on the owners perspective.
  • Team with extensive facilities engineering,
    construction, maintenance and commissioning
    experience.
  • Over 100 commissioning projects of various sizes
    and types around the world including LEED and
    CHPS projects
  • Founding and active member of Building
    Commissioning Association
  • Member USGBC

4
Why Commissioning?
5
Design Related Issues
6
Ill take whats Behind Door 1
7
At least they wont mess with the thermostat.
8
No problem, let me get my saw..
9
Look, someone has a fire alarm pull station for
sale on the bulleting board.
10
I guess well assign old Slim to service that
unit.
6
11
Oh Shucks!
12
Construction Issues
13
Dirt Construction Debris
14
Equipment Without Lubrication
15
Missing Insulation Above Ceiling
16
Maintenance Access Prevented
17
Filter Access Problems
18
Actuators Missing or Fallen Off
19
Improper Condensate Drains
20
The Code Official Fallacy
  • 290K Sq. Ft. Facility
  • 162 Smoke and Fire/Smoke Dampers
  • 103 of them had problems
  • Fire sprinkler system had problems
  • System had been accepted by the Authority Having
    Jurisdiction (Fire Marshall)

21
Control System Problems
22
The Commissioning Continuum
Post Occupancy
Post Construction
Design
Construction
23
Design Intent
  • Speaks in terms of the Owners needs and desires
  • Contains the Basis of Design, which speaks more
    to numbers and design conditions
  • Quantifiable goals are important
  • Required by LEED
  • Responsibility of the design team and Owner,
    reviewed by Commissioning Consultant
  • Critical to the program and commissioning, yet
    often not fully developed

24
Commissioning Specifications
  • Outlines scope of commissioning
  • Roles and responsibilities
  • Methodology
  • Should be provided by Commissioning Consultant
  • Relates to Design Intent
  • Required by LEED

25
Monitoring and Verification
  • MV for extra LEED point
  • Can integrate with many of the building control
    systems
  • Should be included in commissioning plan

26
Cost of Cx Services
  • Oregon Office of Energy
  • 0.40 to 0.80 per square foot
  • USGBC LEED
  • 0.5 1.5 of total construction cost for
    whole-building commissioning
  • 1.5 2.5 of mechanical contract for mechanical
    only
  • 1.0 1.5 of electrical contract for electrical
    only
  • PECI
  • 2.5 of the mechanical contract
  • 1.5 of the electrical contract

27
Cost of CX Services
Depth Scope and Extent of Services
Cost
Breadth Extent of Systems to be Commissioned
28
Cx Lessons Learned
  • Get the commissioning consultant on-board early.
  • Inform the design team early that LEED is a goal
    and what the score card will look like.
  • The Owner needs a clear idea of the scope of
    commissioning work, desired and required, in
    terms of, depth, breadth and cost.
  • Put an emphasis on the Design Intent early.
  • Develop at least a rough MV plan early.

Early Involvement
29
The USGBCs Green Building Rating SystemL E E
DTMLEADERSHIP IN ENERGY ENVIRONMENTAL DESIGN
  • Requirements for Commissioning
  • to achieve a LEED Rating

Craig A. Hawkins
30
Presenter
  • Craig A. Hawkins,
  • President, CHDS Commissioning Engineering,
    Auburn, WA
  • Over 25 Years of Building Mechanical Systems
    experience, including
  • Manufacturing Engineering, 3 years
  • Design-Build Contracting, 8 years
  • Consulting Engineering, 14 years
  • Specializing in Whole Building Commissioning
    since 1993
  • Founding Member of the Building Commissioning
    Association (BCA)
  • Current Member of BCAs Board of Directors
  • Co-Authored BCAs Essential Attributes of
    Building Commissioning

31
LEED Prerequisite (1 of 7)
  • Fundamental Building Systems Commissioning

32
Fundamental Building Systems Commissioning
Implement ALL of the following six fundamental
best practice commissioning procedures
  • Engage a Commissioning Authority
  • Develop design intent and basis of design
    documentation
  • Include commissioning requirements in the
    construction documents
  • Develop and utilize a Commissioning Plan
  • Verify installation, functional performance,
    training and documentation
  • Complete a Commissioning Plan

33
1 Engage a Commissioning Authority
  • The project shall have a Commissioning Authority
    (CxA) designated as early as possible. The CxA
    should be an objective advocate of the Owner,
    independent from the design team, and should
    possess the following qualities
  • Qualified, professional firm regularly engaged in
    the performance of Building Commissioning
  • Experienced with providing
  • Managerial and organizational leadership
  • Excellent communication skills
  • Technical aspects of the particular projects
    systems, components, and elements
  • Construction management
  • Hands-on field experience with
  • Start-up Procedures
  • Testing
  • Troubleshooting
  • Operation Maintenance
  • Active member in related professional
    organization, such as the BCA

34
2 Collect and review design intent and basis of
design documentation
  • For all commissioned elements as well as those
    that significantly interact with commissioned
    elements
  • Identify the primary design assumptions in the
    basis of design
  • Occupancy
  • Space and process requirements
  • Codes, policies, standards
  • Load and climatic assumptions
  • Document the design intent that was considered to
    be important in the development of the design
  • Ideas
  • Concepts
  • Criteria
  • Review the design concepts narrative describing
    how the designer is planning to meet the design
    intent, using the basis of design information

35
3 Include commissioning requirements in the
construction documents
  • Drawings Include on cover sheet for each
    effected discipline
  • Cx Agents Name and contact information
  • List of systems/equipment to be commissioned
  • Reference Cx Plan and Cx Specification Section
  • Specifications Include a specific Commissioning
    Section (CSI Section 01810) including
  • Scope of Commissioning
  • List of systems/equipment to be commissioned
  • Detailed requirements for
  • Submittal Review
  • Construction Phase Observations
  • Start-Up and TAB
  • O M Documentation
  • Owner Training
  • Warranty Period Activities
  • Scope, Rigor and Schedule of all Functional
    Performance Testing

36
4 Develop and utilize a Commissioning Plan
  • A comprehensive document detailing all aspects of
    the commissioning effort for the project
  • Overview of the commissioning process
  • Roles and responsibilities of each team member
    involved with commissioning
  • Management and communications between all
    involved with commissioning
  • Procedures for
  • Submittal review
  • Construction Phase Observations
  • Pre-FPT and FPT Procedures with associated FPT
    Checklists
  • O M Review
  • Owner Training
  • Warranty Period Activities
  • Reporting Forms
  • Schedule of all commissioning events
  • The Cx Plan is written and maintained by the
    Commissioning Agent, ideally completed and
    published prior to the bid period. At a minimum,
    publish prior to installation of any commissioned
    element

37
5 Verify installation, functional performance,
training and documentation
  • Installation
  • Construction observations to ensure proper
    installation in compliance with Design Documents,
    Cx Plan, Mfg.'s installation instructions, and to
    ensure that other building systems and components
    are not compromising the efficacy of the element
  • Functional Performance
  • FPTs to ensure that commissioned element
    performs as intended under all sequences of
    operation (start-up, shutdown, reset, occupied,
    unoccupied, manual, automatic, modulation range,
    power failure, alarms, staging, redundant,
    interlock with other systems, sensor calibration,
    etc)
  • Appropriate sampling on numerous like units
  • Seasonally deferred testing (cooling system in
    summer, heating system in winter)
  • Owner Training
  • Documented verification that training by
    qualified individuals was provided to the
    projects operational staff for a sufficient
    duration to ensure that the staff has all the
    information needed to optimally operate, maintain
    and replace all the commissioned elements
  • OM Documentation
  • Documented verification that the OM materials
    for each commissioned element have been provided
    to the operational staff complete and clearly are
    accessible

38
6 Complete a Commissioning Report
  • Final report by the Cx Agent to the Owner at the
    end of all FPTs, except any seasonal deferred
    testing, including
  • List of all commissioned elements
  • Disposition of element (FPT results)
  • Design intent
  • Product specification
  • Installation data
  • OM documentation
  • Owner training documentation
  • List of all outstanding commissioning issues
    (such as any deferred testing)
  • All outstanding environmentally responsive
    feature deficiencies corrected and noted
  • All completed FPTs and associated FPT Checklists

39
Energy AtmosphereCredit 3
  • Additional Commissioning

40
Additional Commissioning
In addition to the Fundamental Building
Commissioning prerequisite, implement ALL of the
following five additional commissioning tasks
  • Conduct a focused review of the design prior to
    the construction documents phase
  • Conduct a focused review of the construction
    documents when close to completion
  • Conduct a selective review of contractor
    submittals of commissioned equipment
  • (Note The three items listed above must be
    performed by someone other than the projects
    designer)
  • Develop a system and energy management manual
  • Have a contract in place for near-warranty end or
    post occupancy review

41
1 Conduct a focused review of the design prior
to the construction documents phase
  • A qualified party (other than the design team)
    shall review the design prior to the release of
    the construction phase documents to ensure that
  • Each commissioned element meets the design
    intent relative to
  • Functionality
  • Energy Performance
  • Maintainability
  • Sustainability
  • System costs
  • IAQ issues
  • Local environmental impacts

42
2 Conduct a focused review of the construction
documents when close to completion
  • A qualified party (other than the design team)
    shall review the construction phase documents
    prior to release to ensure that
  • Commissioning is adequately specified
  • Each commissioned element can be commissioned
  • Each commissioned element meets the design
    intent relative to
  • Functionality
  • Energy Performance
  • Maintainability
  • Sustainability
  • System costs
  • IAQ issues
  • Local environmental impacts

43
3 Conduct a selective review of contractor
submittals of commissioned equipment
  • A qualified party (other than the design team)
    shall review the commissioned elements submittals
    for compliance with the commissioning
    requirements, including
  • Design intent
  • Environmentally responsive characteristics
  • Maintainability

44
4 Develop a System and Energy Management Manual
  • A comprehensive document (in addition to the
    OMs) delivered to the Owner along with the
    Final Cx Report, which includes
  • Description of each commissioned element
    including
  • Final design intent
  • System narrative
  • Sequence of operation
  • Seasonal normal start-up, shutdown and restart
    procedures
  • Control drawings
  • Description and rationale for energy savings
    features including
  • Operating Instructions
  • Caveats about functions
  • Maintenance relative to energy use
  • Recommendations and methodology for
    whole-building energy accounting (as applicable)
    including
  • Guidelines for establishing and tracking
    benchmarks for whole-building energy use
  • Guidelines for establishing and tracking
    benchmarks for primary plant equipment
    efficiencies
  • Schedule and procedures for continuous and/or
    re-commissioning of elements
  • Specific recommendations regarding seasonal
    operational issues
  • A list of all user adjustable setpoints that
    includes
  • Discussion regarding the purpose of each setpoint
  • Range of reasonable adjustments with energy
    implications

45
5 Have a contract in place for near-warranty
end or post occupancy review
  • Cx Agent shall return to project site at the 10th
    month of the first 12-month warranty period to
    review the following with the buildings
    operational staff
  • Review condition of all outstanding issues
    related to the original FPTs and deferred
    testing
  • Identify problems or concerns related to building
    operation
  • Assist staff in developing reports,
    documentation, and requests for services to
    remedy outstanding problems
  • Cx Agent to follow-up the return visit with a
    written report to the Owner that includes
  • Findings from the warranty period review with
    operational staff
  • Suggestions on problems identified during
    warranty period review with operational staff
  • Items that may be under warranty or appear to be
    construction related
  • Documentation that assists staff in requesting
    services to remedy outstanding problems

46
Case Studies
47
Company Profile
  • Established in 1984, 12 years Cx
  • 26 employees in 5 branches nationwide
  • Cxd 10,000,000 SF of space for 163 clients
  • 23 LEED projects, 18 by Seattle branch
  • Founding member of BCA
  • Member USGBC for 3 years

48
LEED Cx Case studies
  • Jean Vollum Natural Capital Center
  • LEED Cx Prerequisite
  • Renovation, historical bldg
  • Smaller bldg, simple systems
  • Seattle Central Library
  • LEED Cx Prerequisite Credit w/ MV
  • New construction (early LEED adoption)
  • Large bldg, complex systems

49
Ecotrust Natural Capital Center
LEED V2.0 Gold
70,000 SF
Completed Sept. 2001
Private sector
Rooftop gas fired packaged VAV units, occ sensors
Cx Authority Scope of Work
  • Energy Atmosphere Prerequisite 1 only
  • Cx Plan, Cx Report, letter of achievement
  • Energy Atmosphere Credit 5 MV
  • Measurement and Verification Plan

50
Ecotrust Natural Capital Center
Cx Challenges Rewards
  • Later adoption of LEED engagement of CA
  • Limited to Cx Prerequisite only
  • Extra work for design documentation awareness
    and requirements for contractor support of Cx

51
Ecotrust Natural Capital Center
Cx Challenges Rewards
  • Increased A/E and CM team awareness, support and
    interaction w/ Cx process
  • Reliance on Cx Plan, ECM documentation for MV
  • Design intent, Pre-functional documentation,
    Start-up and functional testing support

52
Ecotrust Natural Capital Center
Lessons Learned
  • Early decision on LEED Cx (budget, roles)
  • Full Cx scope more economical, early team
    awareness
  • Cx integration with design documents enhances
    achievement of energy and operational savings
  • Importance of CM team acceptance to LEED
  • CA/CM teaming is cost effective comprehensive
  • 3rd party, Owner based Quality Assurance
    enhances contractor Quality Control

53
Seattle Central Library
LEED V2.0 Silver
400,000 SF
Completion late 2003
Public building
Chillers, City steam, under floor air, atrium,
fire alarm, security, multi-site DDC
Cx Authority Scope of Work
  • Energy Atmosphere Prerequisite Credit Cx
  • DD CD Review, Re-CX Management Manual, broader
    scope of services
  • Energy Atmosphere Credit 5 MV
  • Measurement and Verification Plan

54
Seattle Central Library
Cx Challenges Rewards
  • Cx Review of Design
  • Timing, scope and budget
  • Design team support and documentation review
  • AHJs, smoke management and energy savings

55
Seattle Central Library
Cx Challenges Rewards
  • Design Development Assistance
  • OM advocacy and Value Engineering
  • IAQ Management Plan review, Fire Alarm and
    security system support

56
Seattle Central Library
Lessons Learned
  • Define level and role of CA involvement in
    design development process
  • Involve CA with operations advocacy and Value
    Engineering exercises
  • Enhance CA scope to address complex systems
    (life safety, low voltage, electrical)
  • Integrate Measurement and Verification early for
    best design support of MV capability

57
U.S. Green Building CouncilCascadia Chapter
  • Thank You
  • Questions?

Craig Hawkins, CHDS Commissioning and
Engineering Todd McGuire, Engineering Economics,
Inc. Bryan Welsh, Keithly Welsh Associates, Inc.
Write a Comment
User Comments (0)
About PowerShow.com