Title: U.S. Green Building Council Cascadia Chapter
1U.S. Green Building CouncilCascadia Chapter
- Presentation on Commissioning
Craig Hawkins, CHDS Commissioning and
Engineering Todd McGuire, Engineering Economics,
Inc. Bryan Welsh, Keithly Welsh Associates, Inc.
2Outline
- Introduction to Commissioning - Bryan
- LEED Commissioning - Craig
- Case Studies - Todd
3 Company Profile
- Established in 1996, Exclusively Commissioning
Services - Unique focus on the owners perspective.
- Team with extensive facilities engineering,
construction, maintenance and commissioning
experience. - Over 100 commissioning projects of various sizes
and types around the world including LEED and
CHPS projects - Founding and active member of Building
Commissioning Association - Member USGBC
4Why Commissioning?
5Design Related Issues
6Ill take whats Behind Door 1
7At least they wont mess with the thermostat.
8No problem, let me get my saw..
9Look, someone has a fire alarm pull station for
sale on the bulleting board.
10I guess well assign old Slim to service that
unit.
6
11Oh Shucks!
12Construction Issues
13Dirt Construction Debris
14Equipment Without Lubrication
15Missing Insulation Above Ceiling
16Maintenance Access Prevented
17Filter Access Problems
18Actuators Missing or Fallen Off
19Improper Condensate Drains
20The Code Official Fallacy
- 290K Sq. Ft. Facility
- 162 Smoke and Fire/Smoke Dampers
- 103 of them had problems
- Fire sprinkler system had problems
- System had been accepted by the Authority Having
Jurisdiction (Fire Marshall)
21Control System Problems
22The Commissioning Continuum
Post Occupancy
Post Construction
Design
Construction
23Design Intent
- Speaks in terms of the Owners needs and desires
- Contains the Basis of Design, which speaks more
to numbers and design conditions - Quantifiable goals are important
- Required by LEED
- Responsibility of the design team and Owner,
reviewed by Commissioning Consultant - Critical to the program and commissioning, yet
often not fully developed
24Commissioning Specifications
- Outlines scope of commissioning
- Roles and responsibilities
- Methodology
- Should be provided by Commissioning Consultant
- Relates to Design Intent
- Required by LEED
25Monitoring and Verification
- MV for extra LEED point
- Can integrate with many of the building control
systems - Should be included in commissioning plan
26Cost of Cx Services
- Oregon Office of Energy
- 0.40 to 0.80 per square foot
- USGBC LEED
- 0.5 1.5 of total construction cost for
whole-building commissioning - 1.5 2.5 of mechanical contract for mechanical
only - 1.0 1.5 of electrical contract for electrical
only - PECI
- 2.5 of the mechanical contract
- 1.5 of the electrical contract
27Cost of CX Services
Depth Scope and Extent of Services
Cost
Breadth Extent of Systems to be Commissioned
28Cx Lessons Learned
- Get the commissioning consultant on-board early.
- Inform the design team early that LEED is a goal
and what the score card will look like. - The Owner needs a clear idea of the scope of
commissioning work, desired and required, in
terms of, depth, breadth and cost. - Put an emphasis on the Design Intent early.
- Develop at least a rough MV plan early.
Early Involvement
29The USGBCs Green Building Rating SystemL E E
DTMLEADERSHIP IN ENERGY ENVIRONMENTAL DESIGN
- Requirements for Commissioning
- to achieve a LEED Rating
Craig A. Hawkins
30Presenter
- Craig A. Hawkins,
- President, CHDS Commissioning Engineering,
Auburn, WA - Over 25 Years of Building Mechanical Systems
experience, including - Manufacturing Engineering, 3 years
- Design-Build Contracting, 8 years
- Consulting Engineering, 14 years
- Specializing in Whole Building Commissioning
since 1993 - Founding Member of the Building Commissioning
Association (BCA) - Current Member of BCAs Board of Directors
- Co-Authored BCAs Essential Attributes of
Building Commissioning
31LEED Prerequisite (1 of 7)
- Fundamental Building Systems Commissioning
32Fundamental Building Systems Commissioning
Implement ALL of the following six fundamental
best practice commissioning procedures
- Engage a Commissioning Authority
- Develop design intent and basis of design
documentation - Include commissioning requirements in the
construction documents - Develop and utilize a Commissioning Plan
- Verify installation, functional performance,
training and documentation - Complete a Commissioning Plan
331 Engage a Commissioning Authority
- The project shall have a Commissioning Authority
(CxA) designated as early as possible. The CxA
should be an objective advocate of the Owner,
independent from the design team, and should
possess the following qualities - Qualified, professional firm regularly engaged in
the performance of Building Commissioning - Experienced with providing
- Managerial and organizational leadership
- Excellent communication skills
- Technical aspects of the particular projects
systems, components, and elements - Construction management
- Hands-on field experience with
- Start-up Procedures
- Testing
- Troubleshooting
- Operation Maintenance
- Active member in related professional
organization, such as the BCA
342 Collect and review design intent and basis of
design documentation
- For all commissioned elements as well as those
that significantly interact with commissioned
elements - Identify the primary design assumptions in the
basis of design - Occupancy
- Space and process requirements
- Codes, policies, standards
- Load and climatic assumptions
- Document the design intent that was considered to
be important in the development of the design - Ideas
- Concepts
- Criteria
- Review the design concepts narrative describing
how the designer is planning to meet the design
intent, using the basis of design information
353 Include commissioning requirements in the
construction documents
- Drawings Include on cover sheet for each
effected discipline - Cx Agents Name and contact information
- List of systems/equipment to be commissioned
- Reference Cx Plan and Cx Specification Section
- Specifications Include a specific Commissioning
Section (CSI Section 01810) including - Scope of Commissioning
- List of systems/equipment to be commissioned
- Detailed requirements for
- Submittal Review
- Construction Phase Observations
- Start-Up and TAB
- O M Documentation
- Owner Training
- Warranty Period Activities
- Scope, Rigor and Schedule of all Functional
Performance Testing
364 Develop and utilize a Commissioning Plan
- A comprehensive document detailing all aspects of
the commissioning effort for the project - Overview of the commissioning process
- Roles and responsibilities of each team member
involved with commissioning - Management and communications between all
involved with commissioning - Procedures for
- Submittal review
- Construction Phase Observations
- Pre-FPT and FPT Procedures with associated FPT
Checklists - O M Review
- Owner Training
- Warranty Period Activities
- Reporting Forms
- Schedule of all commissioning events
- The Cx Plan is written and maintained by the
Commissioning Agent, ideally completed and
published prior to the bid period. At a minimum,
publish prior to installation of any commissioned
element
375 Verify installation, functional performance,
training and documentation
- Installation
- Construction observations to ensure proper
installation in compliance with Design Documents,
Cx Plan, Mfg.'s installation instructions, and to
ensure that other building systems and components
are not compromising the efficacy of the element - Functional Performance
- FPTs to ensure that commissioned element
performs as intended under all sequences of
operation (start-up, shutdown, reset, occupied,
unoccupied, manual, automatic, modulation range,
power failure, alarms, staging, redundant,
interlock with other systems, sensor calibration,
etc) - Appropriate sampling on numerous like units
- Seasonally deferred testing (cooling system in
summer, heating system in winter) - Owner Training
- Documented verification that training by
qualified individuals was provided to the
projects operational staff for a sufficient
duration to ensure that the staff has all the
information needed to optimally operate, maintain
and replace all the commissioned elements - OM Documentation
- Documented verification that the OM materials
for each commissioned element have been provided
to the operational staff complete and clearly are
accessible
386 Complete a Commissioning Report
- Final report by the Cx Agent to the Owner at the
end of all FPTs, except any seasonal deferred
testing, including - List of all commissioned elements
- Disposition of element (FPT results)
- Design intent
- Product specification
- Installation data
- OM documentation
- Owner training documentation
- List of all outstanding commissioning issues
(such as any deferred testing) - All outstanding environmentally responsive
feature deficiencies corrected and noted - All completed FPTs and associated FPT Checklists
39Energy AtmosphereCredit 3
40Additional Commissioning
In addition to the Fundamental Building
Commissioning prerequisite, implement ALL of the
following five additional commissioning tasks
- Conduct a focused review of the design prior to
the construction documents phase - Conduct a focused review of the construction
documents when close to completion - Conduct a selective review of contractor
submittals of commissioned equipment - (Note The three items listed above must be
performed by someone other than the projects
designer) - Develop a system and energy management manual
- Have a contract in place for near-warranty end or
post occupancy review
411 Conduct a focused review of the design prior
to the construction documents phase
- A qualified party (other than the design team)
shall review the design prior to the release of
the construction phase documents to ensure that - Each commissioned element meets the design
intent relative to - Functionality
- Energy Performance
- Maintainability
- Sustainability
- System costs
- IAQ issues
- Local environmental impacts
422 Conduct a focused review of the construction
documents when close to completion
- A qualified party (other than the design team)
shall review the construction phase documents
prior to release to ensure that - Commissioning is adequately specified
- Each commissioned element can be commissioned
- Each commissioned element meets the design
intent relative to - Functionality
- Energy Performance
- Maintainability
- Sustainability
- System costs
- IAQ issues
- Local environmental impacts
433 Conduct a selective review of contractor
submittals of commissioned equipment
- A qualified party (other than the design team)
shall review the commissioned elements submittals
for compliance with the commissioning
requirements, including - Design intent
- Environmentally responsive characteristics
- Maintainability
444 Develop a System and Energy Management Manual
- A comprehensive document (in addition to the
OMs) delivered to the Owner along with the
Final Cx Report, which includes - Description of each commissioned element
including - Final design intent
- System narrative
- Sequence of operation
- Seasonal normal start-up, shutdown and restart
procedures - Control drawings
- Description and rationale for energy savings
features including - Operating Instructions
- Caveats about functions
- Maintenance relative to energy use
- Recommendations and methodology for
whole-building energy accounting (as applicable)
including - Guidelines for establishing and tracking
benchmarks for whole-building energy use - Guidelines for establishing and tracking
benchmarks for primary plant equipment
efficiencies - Schedule and procedures for continuous and/or
re-commissioning of elements - Specific recommendations regarding seasonal
operational issues - A list of all user adjustable setpoints that
includes - Discussion regarding the purpose of each setpoint
- Range of reasonable adjustments with energy
implications
455 Have a contract in place for near-warranty
end or post occupancy review
- Cx Agent shall return to project site at the 10th
month of the first 12-month warranty period to
review the following with the buildings
operational staff - Review condition of all outstanding issues
related to the original FPTs and deferred
testing - Identify problems or concerns related to building
operation - Assist staff in developing reports,
documentation, and requests for services to
remedy outstanding problems - Cx Agent to follow-up the return visit with a
written report to the Owner that includes - Findings from the warranty period review with
operational staff - Suggestions on problems identified during
warranty period review with operational staff - Items that may be under warranty or appear to be
construction related - Documentation that assists staff in requesting
services to remedy outstanding problems
46Case Studies
47 Company Profile
- Established in 1984, 12 years Cx
- 26 employees in 5 branches nationwide
- Cxd 10,000,000 SF of space for 163 clients
- 23 LEED projects, 18 by Seattle branch
48 LEED Cx Case studies
- Jean Vollum Natural Capital Center
- Renovation, historical bldg
- Smaller bldg, simple systems
- LEED Cx Prerequisite Credit w/ MV
- New construction (early LEED adoption)
- Large bldg, complex systems
49Ecotrust Natural Capital Center
LEED V2.0 Gold
70,000 SF
Completed Sept. 2001
Private sector
Rooftop gas fired packaged VAV units, occ sensors
Cx Authority Scope of Work
- Energy Atmosphere Prerequisite 1 only
- Cx Plan, Cx Report, letter of achievement
- Energy Atmosphere Credit 5 MV
- Measurement and Verification Plan
50Ecotrust Natural Capital Center
Cx Challenges Rewards
- Later adoption of LEED engagement of CA
- Limited to Cx Prerequisite only
- Extra work for design documentation awareness
and requirements for contractor support of Cx
51Ecotrust Natural Capital Center
Cx Challenges Rewards
- Increased A/E and CM team awareness, support and
interaction w/ Cx process
- Reliance on Cx Plan, ECM documentation for MV
- Design intent, Pre-functional documentation,
Start-up and functional testing support
52Ecotrust Natural Capital Center
Lessons Learned
- Early decision on LEED Cx (budget, roles)
- Full Cx scope more economical, early team
awareness
- Cx integration with design documents enhances
achievement of energy and operational savings
- Importance of CM team acceptance to LEED
- CA/CM teaming is cost effective comprehensive
- 3rd party, Owner based Quality Assurance
enhances contractor Quality Control
53Seattle Central Library
LEED V2.0 Silver
400,000 SF
Completion late 2003
Public building
Chillers, City steam, under floor air, atrium,
fire alarm, security, multi-site DDC
Cx Authority Scope of Work
- Energy Atmosphere Prerequisite Credit Cx
- DD CD Review, Re-CX Management Manual, broader
scope of services
- Energy Atmosphere Credit 5 MV
- Measurement and Verification Plan
54Seattle Central Library
Cx Challenges Rewards
- Design team support and documentation review
- AHJs, smoke management and energy savings
55Seattle Central Library
Cx Challenges Rewards
- Design Development Assistance
- OM advocacy and Value Engineering
- IAQ Management Plan review, Fire Alarm and
security system support
56Seattle Central Library
Lessons Learned
- Define level and role of CA involvement in
design development process
- Involve CA with operations advocacy and Value
Engineering exercises
- Enhance CA scope to address complex systems
(life safety, low voltage, electrical)
- Integrate Measurement and Verification early for
best design support of MV capability
57U.S. Green Building CouncilCascadia Chapter
Craig Hawkins, CHDS Commissioning and
Engineering Todd McGuire, Engineering Economics,
Inc. Bryan Welsh, Keithly Welsh Associates, Inc.