Title: GLAST Proposal Review
1GLAST Large Area Telescope I T Input to LAT
Planning Meeting July 17th and 18th Elliott
Bloom SU-SLAC Subsystem Manager Brian
Grist SU-SLAC Subsystem Engineer elliott_at_slac.sta
nford.edu, bgrist_at_slac.stanford.edu 650-926-2469
650-926-2998
2Key Milestone List to Delivery (Not Necessarily
in Current PMCS)
- EM Plan, Procedures, EGSE and MGSE
Complete 07/31/03 - Receive CAL EM 08/08/03
- Receive TKR mini-tower 08/22/03
- EM Tower functional tests Complete 09/18/03
- EM Tower Available for use by Flight
Software 09/18/03 - EM Calibration Complete 10/12/03
- EM mechanical fit check using 1X4 Grid, TKR Mech
tower, CAL 10/13/03 - CAL EM at NRL Loading Doc TKR mini-tower in
Italian Customs 10/17/03 - Support GSI Beam Test (CAL and TKR
mini-tower) 11/14/03 - All IT Flight Techs on Staff (Mechanical and
Electrical) 12/15/03 - Flight Integration Training MGSE
Ready 01/15/04 - All Flight Integration Procedures
Complete 02/15/04 - All Flight Integration MGSE Complete with
SDP 03/01/04 - LAT Assembly Configuration EGSE Ready For
Use 03/01/04 - Integration Readiness Review 03/15/04
- TKR A/B Available RFI 04/15/04
- Grid Available RFI 05/20/04
- CAL A/B Available RFI 05/20/04
3Multi-Tower EGSE (9/15/03)
TDF System (LAT)
EGSE
EGSE Crate
ACD or Sensor Simulator
CPU
LCB
WAN
GASU
28 V Supply
Central Database
EBM
VME
AEM
GEM
Online Workstation
TEMs
Firewall
CAL, TKR or Sensor Simulator
SLAC
4Single Tower EGSE Configuration (GSI test)
Electronics/Online
-
- Online
- Workstation
- Test Exec
- Configuration
- Commanding
- Telemetry
- Event Processing
- Monitoring
- Visualization
- Data base
- Message logger
- Alerts
- Electronic log
Subsystem/simulator
Back door debug RS-232
Subsystem (or simulator)
Central Database
VME Chassis
- CPU
- Commanding
- Telemetry
- Monitoring
- Hardware Drivers
AEM/TEM
WAN
Ethernet
Main Dataflow Ethernet
- LAT-COMM
- External Trigger
Ethernet Router and Firewall
DC Power
External Hardware
5Key Milestone List to Delivery After Start of
Flight IT (Not in Current PMCS)
- Start Tower A/B Installation/Test 05/20/04
- Start Tower 1/2 Installation/Test 07/01/04
- Start Tower 13/14 Installation/Test 10/28/04
- Finish Tower Installation/Test 11/11/04
- Finish Installation of ACD/ELEX/X-LAT 12/23/04
- Flight Configuration Ready for System
Test 12/23/04 - Complete System Test 04/21/05
- LAT Shipped for Environmental Testing 07/21/05
- Environmental Testing Complete 11/03/05
- LAT RFI 12/01/05
6LAT Assembly Configuration (3/1/04)
LAT
EGSE
Spacecraft simulator
SIU
ACD or Sensor Simulator
CPU
Discretes
1553
1553
WAN
LCB
GASU
Central Database
EBM
AEM
SSR
3 EPUs
GEM
CPU
Online Workstation
LCB
TEMs
Firewall
EGSE Crate
Test Point on LAT EMI Skirt
CAL, TKR or Sensor Simulator
CPU
LCB
SLAC
7Complete Flight Unit Configuration CU (12/24/04)
LAT
EGSE
SIU
ACD
CPU
1553
WAN
LCB
GASU
Central Database
EBM
AEM
3 EPUs
GEM
CPU
Online Workstation
LCB
TEMs
Firewall
EGSE Crate
Test Point on LAT EMI Skirt
CAL, TKR
CPU
LCB
SLAC
8Interdependencies
- Dependent on deliveries from all subsystems to be
able to do the core of our work. - EM CAL TKR mini-tower deliveries.
- EM GASU and flight software support from ELX.
- All Flight Hardware and Software.
- MGSE FEM Analysis
- Budget for IT Flight Electronic Techs and the
hiring of those techs (4 full time people
starting 12/15/03) is currently the
responsibility of ELX. IT will schedule the work
for these Techs. - System engineering test plans are required as
input to IT test plans and resulting procedures. - Mission level EGSE decisions can impact IT EGSE
schedule and budget.
9Flight Hardware Procurements
- No flight hardware procured by IT. All flight
components come from a subsystem.
10Flight Hardware Manufacturing Plan Status
- LAT-MD-01376 LAT Integration Test Plan In
Work - LAT-MD-01137 LAT EM Test Plan In signoff
- LAT-MD-01533 EGSE Plan In revision
- LAT-MD-00446 SVAC Plan Released
- LAT-MD-01587 SVAC Test Plan Released
- LAT-MD-01598 LAT Weight and CG Test
Plan Released - LAT-MD-01462 MGSE Development Plan In signoff
- LAT-MD-01836 LAT Dynamics Test Performance Plan
Draft in Cyberdocs - LAT-MD-01837 LAT Thermal Test Performance Plan
Draft in Cyberdocs - LAT-MD-01838 LAT EMI Test Performance Plan
Draft in Cyberdocs - LAT-MD-00676 LAT Assembly Sequence In revision
- LAT-MD-01386 LAT Facilities Plan Released
- LAT-MD-01586 LAT Survey Alignment Performance
Plan In signoff - LAT-MD-01055 LAT Electrical Test Performance
plan Released - LAT-MD-00440 LAT Particle Test Plan In
signoff
11Engineering Model Testing Closure Status
- IT Tests of the TKR mini-tower were done and the
results reported to the Engineering meeting at
June 10 Engineering Meeting. Data is still being
worked. - EM tower (CAL EM and TKR mini-tower) due in
August to IT - Complete EM Tower functional test by September
18th and then make available to Flight Software. - Complete EM Calibration by October 12th.
- Need 1x4 Grid and TRK EM Mechanical tower a week
before Mechanical fit check to assemble TRK EM
into grid. - Perform a mechanical fit check using 1x4 Grid,
TKR Mechanical Tower, and EM CAL on October 13th. - CAL EM on the NRL loading dock and the TKR
mini-tower in Italian Customs by October 17th. - Support the GSI Beam Test, including the CAL and
the TKR mini-tower (run Carbon in the daytime)
November 14th 24th.
12Open Flight Design Issues/ Status Trades
- CAL-Grid interface design, impacts IT MGSE,
assembly, processes, and procedures. Design not
completed. - Grid EMI Skirt design impacts IT assembly,
processes and procedures. Design not completed. - X-LAT plate design impacts IT MGSE, assembly,
processes and procedures. Design not completed. - Radiator interface and MGSE design impact IT,
assembly, processes and procedures. Design not
completed. - Environmental test sensor requirements impact IT
assembly, processes and procedures. Requirements
have not been finalized. - LAT pointing knowledge requirements are under
review by the project. IT test plans cannot be
finalized until we know the final requirements.
13Cost/Schedule Status (May Month End)
Cost Variance GREEN Schedule Variance YELLOW
Beam test change request has been approved and
has been incorporated for the June Report.
The monthly Cost and Schedule Variances are
trending negative
14Issues/Concerns/Suggestions/Risks
- Late delivery to IT of EM parts and EGSE
software test scripts. - Late delivery has delayed preparations for LAT,
particularly in areas of IFCT and SVAC. Possible
impact on EGSE. - Part of EGSE/MGSE verification strategy depends
on IT EM program. - Finalization of all LAT test plan requirements is
not complete post CDR. This is resulting in
compressed schedule and potential increased cost
for IT. Current estimates are September for
completing all test plans from the Design Team. - Delivery of flight hardware to IT may be late.
- IT EGSE is proceeding with in-house developed
test executive software. Change to another system
for Observatory and/or IOC will require major
cost change request. - Spacecraft interface detail uncertainty.
- Environmental test fixtures.
- EGSE interface.
- MGSE handling fixtures.
- SIIS fidelity uncertainty.
- Delivery of flight hardware to IT may be late.
- When will a decision be made about where to go
for Environmental Testing? This will impact
preparations and design of Vib and T/V fixtures.