Regulatory Update - PowerPoint PPT Presentation

1 / 20
About This Presentation
Title:

Regulatory Update

Description:

Notify Sprint Nextel when channels in the new NPSPAC band need to be made available ... Sprint Nextel is required to pay expenses that are incurred after June ... – PowerPoint PPT presentation

Number of Views:41
Avg rating:3.0/5.0
Slides: 21
Provided by: davids49
Category:

less

Transcript and Presenter's Notes

Title: Regulatory Update


1
Regulatory Update
  • Bette Rinehart

2
700 MHz
  • October 10 Deadline for Public Safety Broadband
    Licensee applications
  • Public Safety Broadband Trust only applicant
  • October 23 Certification deadline
  • 35 certifications received
  • Auction 73 (700 MHz) Rules, deadlines established
  • Auction will begin on January 24, 2008
  • January 31, 2008 New Deadline to file revised
    700 MHz Regional Plans
  • Applies to Regions with granted or pending Plans
    as of July 2007

3
800 MHz
4
3rd Memorandum Opinion Order
  • Sprint Nextel failed to meet its 18 month
    benchmark obligation to clear first 20 regions
  • No penalties imposed
  • Although they cleared 26 regions, not all of Wave
    1 was cleared
  • FCC imposes additional benchmarks to ensure
    timely completion
  • SN must complete relocation of all 1-120
    channels in Waves 1, 2, 3 and non-border 4 by
    12/26/07
  • SN must file monthly progress reports on 1-120
    clearing
  • SN and SouthernLinc must be off 1-120 and
    interleaved by 6/26/08
  • For licensees requesting access to new NPSPAC
    channels in the interim
  • SN must clear within 90 days of request made
    prior to 1/1/08
  • SN must clear within 60 days of request made
    after 1/1/08
  • Waivers filed for extensions due to potential
    interference from broadcast channel 69 granted
  • Infrastructure retuning can be extended to 3/1/09
  • Incumbents should proceed with whatever planning
    or subscriber replacement possible
  • Any licensee impacted by Channel 69 must file own
    waiver, not a blanket decision

All non-Nextel / Non-SouthernLinc
5
Public Notice Supplemental Procedures and
Guidance
  • Completion of planning
  • FRA negotiations
  • Change notice process
  • Rebanding implementation
  • Regional implementation planning
  • Wave 4 border area planning
  • Licensee request for extension

6
Completion of Planning
  • Following TA approval, NPSPAC licensees must
    complete planning (either with or without a PFA)
    and submit a cost estimate as follows
  • 1 - 5,000 units within 90 days
  • 5,001 - 10,000 units within 100 days
  • Over 10,000 units within 110 days
  • NPSPAC licensees in Waves 1-3 that are already
    engaged in planning must complete planning and
    submit a cost estimate to Sprint as follows
  • Wave 1 by October 15, 2007
  • Wave 2 by November 15, 2007
  • Wave 3 by December 15, 2007
  • A NPSPAC licensee may request additional time for
    planning but must show why and provide detail on
    activities to date
  • During planning, NPSPAC licensees must provide
    the TA with biweekly status updates. The cost of
    the updates is recoverable from Sprint Nextel.

7
FRA Negotiations
  • Parties have 30 days to negotiate an FRA
    following submission of a cost estimate to Sprint
    by the licensee
  • TA mediators will monitor negotiations and track
    submittal dates
  • TA mediators will not participate in
    negotiations.
  • If the parties are unable to negotiate an FRA
    within 30 days, the parties shall participate in
    mediation for 20 days
  • Any remaining disputed issues will be referred to
    PSHSB within 10 days of the close of the
    mediation period

8
Change Notice Process
  • The negotiation and approval of Change Notice
    requests should take into account the overall
    goals of this proceeding, not just the issue of
    minimum cost.
  • Licensees cant use Change Notice to recover
    costs that were originally rejected or reasonably
    foreseeable during planning or FRA negotiations
  • Licensees complying with time limits may seek
    costs incurred that could not reasonably be
    anticipated within such time limits.
  • Licensees should submit Change Notice requests
    concurrently to Sprint and the TA.
  • Sprint shall respond to all Change Notices
    requests within 10 working days of receipt
  • Parties may request mediation from the TA and
    shall participate in mediation for 15 working
    days
  • Remaining disputes will be referred to PSHSB. TA
    must review all amendments within 10 working days
    from the date

9
Rebanding Implementation
  • Use the resources offered by the TA to prepare
    for and expedite system reconfiguration.
  • Use SED
  • Make sure contracts are compliant with FRA
    schedule and FCC requirements
  • Create and distribute lists of key licensee
    personnel and contacts, as well as contacts for
    vendors, consultants, Sprint, and the TA.
  • Maintain an inventory of all subscriber and
    infrastructure equipment affected by rebanding,
    and verify the receipt of all loaner and
    replacement equipment
  • Notify Sprint Nextel when channels in the new
    NPSPAC band need to be made available
  • Have a mutual aid plan in place during
    reconfiguration.
  • Notify the TA of unresolved issues that affects
    the implementation schedule.

10
Regional Implementation Planning
  • Licensees should be prepared to discuss all
    issues associated with reconfiguration of their
    systems
  • Do whatever activities are possible while
    implementation planning is under way
  • If a licensee has an executed FRA and does not
    require interoperability can reconfigure
  • Multiple licensees that propose to reconfigure as
    a coordinated group may present a single timeline
    and plan (even if they have separate FRAs).
  • For licensees in mediation with Sprint Nextel,
    discussions at regional planning sessions will
    not be treated as part of the official mediation
    record

11
Wave 4 Border Area
  • During this extended period, Wave 4 border area
    licensees are not required to engage in planning
    or negotiation prior to receipt of frequency
    designations from the TA.
  • Licensees should engage in such activities to the
    extent that they are not frequency-dependent and
    would not result in unnecessary duplication of
    costs.
  • If licensees choose to engage in such activities,
    Sprint shall pay licensees reasonable costs in
    accordance with the requirements of the
    Commissions orders in this proceeding.

12
Public Safety Licensee Requests for Extension of
36-Month Deadline
  • FCC discourages public safety licensees from
    filing extension requests at this time
  • Requests for extension will be subject to a high
    level of scrutiny
  • Sprint Nextel is required to pay expenses that
    are incurred after June 26, 2008
  • FCC directed TA to approve FRAs that will have
    costs incurred after June 26, 2008

13
Key Dates
14
FCC 12/20/06 Public Notice
  • Discussed use of STAs for interim use
  • During the freeze and post-freeze period, they
    will accept requests for STAs on pre-rebanding
    frequencies
  • The Regional Planning Committee must concur and
    the frequencies must be consistent with the
    Regional Plan
  • No permanent licenses will be granted on the
    pre-rebanding frequencies
  • Licensees must file a permanent application to
    operate on the new frequencies when they become
    available for licensing
  • When will that be?

15
STA Requirements
  • STA applications must contain complete details
    about the proposed operation and the
    circumstances that fully justify and necessitate
    the grant of STA
  • A successful application would clearly articulate
    why the facilities requested must be implemented
    before the end of band reconfiguration
  • Applications will be closely scrutinized as the
    date for completion of reconfiguration approaches

16
Who Pays to Reband?
  • Sprint Nextel is not required to pay for
    relocation of facilities authorized by STA on
    pre-rebanding frequencies after the freeze has
    ended,
  • Licensee can file a waiver requesting that Sprint
    Nextel be responsible for payment of relocation
    costs
  • Licensee must demonstrate that
  • The need for the facility could not reasonably
    have been anticipated before the end of the
    mandatory negotiation period and
  • Safety considerations dictate that the modified
    facilities must be activated before band
    reconfiguration is completed in the relevant
    NPSPAC region.  Reopened negotiations with Sprint
    should not commence until a waiver has been
    granted.

17
Avoiding Licensing Pitfalls
  • Coordinate implementation on NPSPAC channels with
    reconfiguration timeframe
  • Work with Regional Planning Committees and get
    concurrence
  • Contact Sprint Nextel regarding their use of
    new NPSPAC channels
  • If using STA, make sure you have back-up
    documentation

18
Canadian Border Proposals
  • FCC Released a FNPRM seeking comment on Canadian
    Band Plan proposals
  • Comments due December 3
  • Replies due December 18
  • Seeks to align Canadian border allocations as
    closely as possible to nationwide allocations

19
Overall Proposals
  • Move non-PS incumbents in the lowest part of the
    US allocation to frequencies higher in the band
  • NPSPAC systems will relocate from the top of the
    band to the lowest portion
  • Frequencies vacated by Sprint Nextel will be
    available to PS for the first 3 years
  • Mutual aid channels will match the mutual aid
    channels in the non-border NPSPAC band plan
  • Additional frequencies in the 866-869 band
    established for mutual aid btw US Canada will
    be maintained
  • No ESMR operations on those frequencies in border
    regions
  • Cut off between Regions 2 3 will be the PA/OH
    border
  • Ohio no longer part of 3 Canadian border regions
  • Cellular/non-cellular operations in the upper
    part of the band will be separated as much as
    possible
  • Some interleaving may be necessary
  • Comment sought on extent of interleaving and what
    technical rules needed to mitigate potential
    interference

20
Overall Proposals cont.
  • Existing non-NPSPAC PS systems will stay in the
    lowest part of the US allocation
  • Some may have to move to accommodate relocating
    NPSPAC systems
  • Means interleaving of non-NPSPAC systems
    operating on 25 kHz spaced channels and NPSPAC
    systems operations on 12.5 kHz spaced channels
  • Both NPSPAC and non-NPSPAC can operate at 25 kHz
    bandwidth
  • NPSPAC subject to tighter emission masks
  • FCC asks
  • Are special technical rules needed to mitigate
    potential interference between the two?
  • Should non-NPSPAC licensees be permitted to
    operate on NPSPAC channels if they meet the
    emission mask requirements?
Write a Comment
User Comments (0)
About PowerShow.com