Update
  • April JPB Board Meeting
  • Scope and Planning Process
  • Review Outreach to Stakeholders
  • Todays Presentation
  • Update on Public Meetings
  • Key Findings Recommendations
  • Next Steps
  • Release Draft Plan
  • Finalize Plan
  • Return to the Board in October

3
Caltrain Bicycle Master Plan
  • Federal Transit Administration Grant (2007)
  • Todays Operations Practice
  • Safety
  • Minimize trip time and dwell time
  • Maximize on-time performance
  • Maintain flexibility
  • Scope Focus
  • Get more people to bike to stations
  • Encourage people to park at stations
  • Innovative ideas to manage on-board demand

4
Context
  • Baby Bullet Service
  • Ridership increase by 17
  • June 2008 44,079 weekday boardings
  • Running out of capacity
  • Longer-term Planning
  • Increase service level
  • Improve access to system for all modes

5
Immediate Challenge
  • Bike Protocol
  • No peak-hour restriction
  • No surcharge
  • Bicyclists Travel Behavior
  • 6 of weekday passengers bring bikes on train
  • 2 of weekday passengers park bikes at stations
  • 2 of bicyclists get bumped (one time survey)
  • Bicyclists Needs
  • Bikes on board to complete end of trip and/or use
    multiple stations
  • Information about on-board bike capacity to plan
    trips
  • Safe and convenient access and parking options at
    stations
  • (27 of SF bike facility users used to bring
    bikes on board)

6
Timeline
We are here
7
Recommendations
8
Access and Parking Recommendations
XXX Strong Concern X Concern 0 No Co
ncern cited
9
Public Comments
  • Appreciation
  • Current bike protocol
  • Planning effort
  • Public outreach process
  • Frustration
  • Scope of study is limited
  • Most pressing problem is bikes getting bumped
  • Want immediate solutions to increase on-board
    bike capacity
  • Want on-board bike capacity information
  • Support
  • Access parking recommendations
  • Study innovative concepts

10
Proposed Next Steps
  • 2 parallel efforts
  • Build on public support
  • Finalize planning effort
  • Title as Access and Parking Plan
  • Focus on Implementation
  • Conduct Feasibility Studies
  • Address public frustration
  • How do we balance access needs of all riders?
  • Develop a comprehensive Access Policy
  • Provide operations and investment guidance

11
Finalize Plan
  • Release Draft Plan 8/11
  • Final Round of Comments Due 9/9
  • Final Plan to the Board 10/4

12