Title: Geotechnical Investigation Report
1Geotechnical InvestigationReport
- July 2008
- Hadi J. Yap, PhD, PE, GE
2Table of Contents
- 1.0 Introduction
- 2.0 Scope of Services
- 3.0 Field Investigation
- 4.0 Laboratory Testing
- 5.0 Geology and Seismicity
- 5.1 regional geology
- 5.2 regional seismicity and faulting
- 5.3 geologic hazards
- 6.0 Site Conditions
- 6.1 site conditions
- 6.2 subsurface conditions
- 7.0 Discussions and Conclusions
- 7.1 foundation support
- 7.2 groundwater
- 7.3 excavation
- 7.4 dewatering
- 7.5 shoring and underpinning
- 8.0 Recommendations
- 8.1 mat foundation
- 8.2 pile foundation
- 8.3 below-grade walls
- 8.4 basement floors
- 8.5 seismic design
- 8.6 site preparation
- 8.7 excavation
- 8.8 dewatering
- 8.9 shoring
- 8.10 earthwork
- 8.11 utilities
- 8.12 construction monitoring
- 8.13 site drainage
- 9.0 Additional Geotechnical
- Services
- 10.0 Limitations
3Introduction
- Present our understanding of the project
- Site location, size, conditions
- building type, number of stories and basements,
column loads - Site grading/fill to be placed
- additional elements of the project (retaining
walls, parking areas, etc.)
4Scope of Services
- Field exploration
- Laboratory testing
- Engineering analysis
- Develop conclusions and recommendations
regarding - soil and groundwater conditions at the site
- the most appropriate foundation type(s) for the
structure - estimates of foundation settlement
- lateral earth pressures for the design of
permanent and temporary below-grade walls - site seismicity and seismic hazards, including
ground rupture, liquefaction, lateral spreading
and differential compaction - San Francisco Building Code seismic design
parameters - subgrade preparation
- criteria for fill, quality, placement and
compaction - pavement design
- construction considerations
5Field Investigation
- Evaluate existing data
- TR database
- city records
- geologic maps
- historic maps
- Perform site reconnaissance
- Develop field investigation program
- test pits
- dynamic cone penetrometer tests
- test borings
- Cone Penetration Tests (CPTs)
6United States Coast Survey Map - February 1852
7(No Transcript)
8Laboratory Testing
- Geotechnical parameters
- index testing for classification
- shear strength
- compressibility
- R-value (for pavement design)
- Corrosivity
9Site Conditions
- Describe site history, if known
- reclamation history
- past development
- previous grading
- Describe existing conditions
- surface conditions
- existing site use
- known obstructions
10Subsurface Conditions
- Describe soil encountered
- thickness
- density/strength
- compressibility
- Groundwater conditions
11Typical Stratigraphic Layers
- Fill
- Dune Sand
- Bay Mud
- Colma Formation
- Old Bay Clay
- Franciscan Complex Bedrock
12(No Transcript)
13Typical Stratigraphic Layers
- Fill
- Heterogeneous soil consisting of sands, clays,
silts, gravels, construction debris - Engineered fill or not?
- If not-engineered fill, can not be relied upon
for foundation support
14Typical Stratigraphic Layers
- Dune Sand
- clean fine-grained sand, wind-blown deposit
- covers the majority of San Francisco
- Typically loose in upper 10
- Typically medium dense, 10 to 30
- Typically dense below 30
15Typical Stratigraphic Layers
- Bay Mud
- consists of clay and silt with occasional sand
lenses and organic material - relatively low strength material
- relatively compressible material
- If underlain by new fill, it could settle,
causing downdrag on piles
16Typical Stratigraphic Layers
- Colma Formation
- consists predominantly of sands with occasional
clay lenses - typically contains between 0 to 20 silt/clay
- relatively strong material
- relatively incompressible material
- excellent foundation support
17Typical Stratigraphic Layers
- Old Bay Clay
- consists of stiff to hard overconsolidated clay
- may contain sand and gravel lenses
- relatively strong
- moderately compressible
18Typical Stratigraphic Layers
- Franciscan Complex bedrock
- deformed bedding planes and shear zones due to
seismic activity - highly variable hardness strength
- moderately to highly weathered
- Relatively strong and incompressible
- excellent foundation support
19Geology and Seismicity
- Regional Geology
- Seismicity Faulting
- distance to faults
- Geologic Hazards
- ground shaking
- liquefaction
- lateral spreading
- landsliding
- tsunami
20Discussion, Conclusions Recommendations
- Discussion Conclusions
- discuss issues, alternatives, implications
- conclude foundations type and settlement,
shoring, soil improvement - Recommendations
- provide recommendations regarding the
geotechnical aspects of the project
21Settlement
- Consolidation
- A slow process of squeezing water out in soft
clay, resulting in denser packing of soil
particles, when overlain by new fill - Liquefaction
- Temporary loss of shear strength in loose sand
due to a rise in excess pore water pressure
generated by strong seismic shaking - Seismic Densification
- Densification of loose sand above the water table
due to ground shaking - Foundation Settlement
22Groundwater
- Depth groundwater encountered
- Likely fluctuations
- Design
23Ground Improvement
- Stone columns
- Compaction grouting
- Chemical grouting
- Jet grouting
- Dynamic compaction
24Foundations
- The most appropriate foundation type depends on
- Subsurface conditions
- Building type and size
- loading conditions
- basement levels
- Site constraints
- noise
- vibrations
- proximity to existing improvements
- proximity to bay, channel
- Economics
25Shallow Foundations
- Footings
- isolated
- continuous
- grid (waffle)
- Mat
26Shallow Foundations
- suitable where competent material is encountered
at subgrade elevation - can be used in fill where it is improved and
building is small and light - mat can be used to span localized areas of
non-support - mat can be used on softer soil in excavation
where weight of structure is equal to or less
than weight of soil removed
27Deep Foundations
28Piers
- Efficient can use one large diameter pier in
lieu of several piles - Lengths can be adjusted in the field reduce
waste - Derive capacity mainly from friction
- Use casing and/or drilling fluid if groundwater
and/or loose soil is present
29Driven Pile
- Concrete piles are economical in Bay Area
- Use where soft soil or un-documented fill is
present - Can be used at sites with high groundwater table
or thick Bay Mud - Fabricated at yard (concrete) good quality
control - Moderately high capacity
30Retaining Walls
- Restrained vs. Unrestrained Walls
- Design wall pressure is higher for restrained
walls - Drained vs. Undrained Walls
- undrained walls are designed to resist
hydrostatic pressure - Drainage
- drainage panels
- gravel drain
- weep holes/pipes
- Waterproofing
- where moisture transmission is unacceptable
31Floor Slabs
- Slab-on-grade
- supported on ground
- less expensive
- will lose support and settle/crack if settlement
occurs beneath slab - Structural slab
- supported on foundations
- more expensive
- can span areas of non-support due to liquefaction
and/or settlement
32Floor Slabs
- Vapor Barrier
- typically included beneath floor slabs above the
water table - consists of
- 4 crushed rock
- 10 mil visqueen
- 2 sand
- alternatives include Griffolyn T65-G
- easier to install
- takes less space
- more expensive
- perform moisture emission testing prior to
placement of floor covering
33Seismic Design
- Provide site class (A through F)
- Provide spectral acceleration values for Maximum
Considered Earthquake (MCE) and Design Earthquake
(DE)
34Seismic Design
- Site Class
- A hard rock
- B rock
- C very dense soil and soft rock
- D stiff soil profile
- E soft soil profile
- F
- liquefiable
- more than 10 feet of peat
- more than 25 feet of very high plasticity clays
(PIgt75) - more than 120 feet of soft/medium stiff clay (Bay
Mud)
35Excavation
- Allowable slopes
- Shoring
- Dewatering
36Site Preparation Earthwork
- Site preparation
- remove pavements, organics
- abandon utilities
- abandon/remove old foundations
- overexcavation
- Earthwork
- compaction requirements
- acceptable fill materials
37Utilities
- Settlement
- hangers
- flexible connections
- sleeved connections
38Pavements
- Flexible
- Rigid
- Pavers
- pedestrian
- vehicular
39Site Drainage
- Keep water away from building
- Collect all downspouts and surface water
- All water should be directed to storm drain
40Additional Geotechnical Services
- Review geotechnical aspects of plans and
specifications - Observation geotechnical aspects of construction
- confirm subsurface conditions are as expected
- contractor performs work in accordance with plans
and specifications
41Limitations
- Conclusions and recommendations are based on
limited subsurface exploration - We should provide observation services to check
work is completed per plans, specs, and our
recommendations