Port of San Francisco Capital Cost Scenarios

Description:

Pier 35 $67,992,459. Major substructure and superstructure repairs within five years ... One berth at east face. Pier 30-32 - Option 2 $327,087,347 ... – PowerPoint PPT presentation

Number of Views:37
Avg rating:3.0/5.0
Slides: 7
Provided by: bobga4
Category:

less

Transcript and Presenter's Notes

Title: Port of San Francisco Capital Cost Scenarios


1
Port of San FranciscoCapital Cost Scenarios
  • A Presentation and Discussion
  • June 20, 2007

2
Capital Cost Scenarios
  • Pier 35 67,992,459
  • Major substructure and superstructure repairs
    within five years
  • Seismic upgrade may be triggered
  • No changes to the shed
  • No extension for longer vessels
  • Pier 27 - Option 2 52,488,293
  • Renovate shed without structural changes
  • No seismic upgrade
  • Pier 27 - Option 3 77,000,000
  • Pier extension for second berth
  • Additional terminal space for second berth

3
Capital Cost Scenarios
  • Pier 30-32 - Option 1 235,614,614
  • Substructure rehab and seismic upgrade
  • Extend northeast corner
  • One berth at east face
  • Pier 30-32 - Option 2 327,087,347
  • Add additional pier extension for second berth

4
Potential Joint Use Scenarios
  • Trade shows
  • Solid demand
  • Scheduling conflicts
  • Special events
  • Demand needs further study
  • Unique space should stimulate demand

5
Potential Revenue Sources
  • Passenger charges 800,000 annually
  • (200,000 passengers _at_ 4)
  • Joint use revenues 500,000 annually
  • (Special event net revenue)
  • Annual tax revenues 897,000
  • (From BAE report)
  • Total annual project revenues 2,197,000
  • Capitalized value 25,900,000

6
Gap Analysis