Collaboratory for Research on Global Projects - PowerPoint PPT Presentation

1 / 39
About This Presentation
Title:

Collaboratory for Research on Global Projects

Description:

'Avoiding and Settling Disputes on International Construction Projects' ... Caroni River, Venezuela SE of Caracas. Completed 1985. Cost US$ 4-5 Billion ... – PowerPoint PPT presentation

Number of Views:71
Avg rating:3.0/5.0
Slides: 40
Provided by: crgpSt
Category:

less

Transcript and Presenter's Notes

Title: Collaboratory for Research on Global Projects


1
Collaboratory for Research on Global Projects
  • Global Projects Seminar Series
  • Avoiding and Settling Disputes on International
    Construction Projects
  • Professors Ron Shumway Nick Sorensen

2
Prof. Ron Shumway
  • JD, Duke University Law School BA, BYU
  • Director KPMG Managing Director FTI Consulting
  • Bechtel Principal Counsel for Contracts
    Disputes
  • Eurotunnel Claims Management Committee
  • General Counsel, Atkinson Construction Company

Atkinson
3
Prof. Nick Sorensen
  • Juris Doctor, University of Chicago Law School
    BA, Brigham Young University
  • Bechtel Claims Manager
  • BART Extension to SFO, Special Counsel
  • General Counsel, Ball, Ball Brosamer and The
    Scott Companies
  • Associate General Counsel, Dillingham
    Construction

dillingham
4
Global Projects Seminar Series
  • A Tale of Three Projects
  • Positive and Negative Examples
  • for
  • International Project Development

5
Global Projects Seminar Series
  • Lo Que Mal Abarca, Mal Termina
  • Spanish Proverb

6
Project 1 - Guri Dam
  • Caroni River, Venezuela SE of Caracas
  • Completed 1985
  • Cost US 4-5 Billion
  • Provides 70 of Venezuelas electricity
  • Finished without a claim or dispute everyone
    happy
  • But it wasnt always that way . . .

7

8

9

10

11
Why Guri (finally) worked well
  • Cost reimbursable contract
  • Incentives
  • Target Fee
  • Milestone Bonuses
  • Good contract administration
  • But more importantly . . .
  • Owner did their homework up front more on that
    later

12
Project 2 - Eurotunnel
  • Strange solicitation for proposals with schemes
    for fixed link
  • Governments of UK and France selected winner, but
    did not invest (privately financed by 220 banks)
  • Offers of helium balloons, Euro-Bridge (cars),
    Euro-Route (trains cars), Eurotunnel (trains)
  • Bid at US7 Bn finished at US13 Bn
  • Technological triumph financial disaster

13
(No Transcript)
14
(No Transcript)
15
(No Transcript)
16
(No Transcript)
17
(No Transcript)
18
Why Eurotunnel went wrong
  • Winner of proposal stage composed entirely of
    contractors
  • First negotiated construction contract with self
    while Eurotunnel (owner) was captive of
    contractors
  • Eurotunnel later spun off and sold stock to
    (mostly French) widows orphans
  • During negotiations, banks were the only
    counterweight
  • Result was good for contractors, less so for
    owner
  • Project met projections for traffic sales but
    not payback of loans widows orphans lose

19
How to get it Right
  • Details after Professor Sorensen
  • dissects Dabhol / Enron

20
  • The Dabhol Power Project

21
India and the State of Maharashtra
22
The Major Players
23
Initial Plan The Gas Pipeline from the Caucasus
24
Under Construction
25
Stopped

26
(No Transcript)
27
(No Transcript)
28
Restartedthe Dabhol Power Plant LNG Terminal
29
Getting it right up front
  • Will my investment be protected by local laws,
    authorities and institutions?
  • Will governmental bodies and financial
    institutions honor their agreements with me?
  • If theres a dispute, will it be in a forum
    thats timely and fair to me?

30
Getting it right up front
  • Realistically an Owner must prioritize, and has
    limited control over cost, schedule and quality
  • First Priority 60
  • Second Priority 30
  • Third Priority 10

31
Example
  • Owner says
  • Gotta keep the cost down cost comes first!
  • Generally means fixed price and competitive bids
  • Which generally means design-bid-build
  • Takes longer
  • Quality suffers

32
If the Owner wants...
Cheapest, but takes longest. "Quality" is
inversely proportional to completeness, accuracy,
etc. of design. Cheap design poor quality
disputes.
33
If the Owner wants...
Can jigger all these with incentives bonuses
34
  • Can you make the Contractor financially
    responsible?
  • Lets look

35
  • Top Ten Contractors
  • 1985 - 2005
  • From Engineering News-Record

36
Top U.S. Contractors1985 - 2005
1985
2005
37
Remember . . .
  • Over the long haul, all contractors are headed
    the same place
  • Make sure your career doesnt head the same way
  • Sign up for CE 290 L, Law for Engineers
    Spring Semester 2007

38
(No Transcript)
39
CE 290 L Law for Engineers
Write a Comment
User Comments (0)
About PowerShow.com