Title: ACCOUNTING STANDARD-7
1ACCOUNTING STANDARD-7
CA. PANKAJ AGRWAL B.Com(Hons), LL.B., FCA
2OBJECTIVE SCOPE
- To prescribe the accounting treatment of revenue
and costs associated with construction contracts
because the date at which contract activity is
entered into and the activity gets completed fall
in different accounting periods. - Therefore, the primary issue is the allocation of
contract revenue and contract costs to the
accounting periods in which construction work is
performed.
3OBJECTIVE SCOPE
- This statement uses the recognition criteria
established in the Framework for the Preparation
and Presentation of Financial Statements to
determine when contract revenue and contract
costs should be recognised. - It applies to the accounting for construction
contracts.
4DEFINITIONS
- CONSTRUCTION CONTRACT
- is a contract specifically negotiated for the
- construction of an asset or combination of assets
- that are closely interrelated or interdependent
- in terms of their design, technology and function
or their ultimate purpose or use.
5DEFINITIONS
- Fixed Price Contract
- is a construction contract in which
- the contractor agrees to a
- fixed contract price or fixed rate per unit of
output, which - in some cases is subject to cost escalation.
6DEFINITIONS
- Cost plus Contract
- is a construction contract in which
- the contractor is reimbursed for allowable or
otherwise defined costs, - plus percentage of these costs or a fixed rate.
7Construction Contracts
- It includes contracts for rendering of services
which are directly related to the - Construction of the asset
- Destruction or restoration of assets
- Restoration of the environment following
demolition of assets.
8Combining and Segmenting
- If the contract covers number of assets,
construction of each asset be treated as a
separate construction contract when - Separate proposals have been made
- Each asset has been subject to separate
negotiation and the contractor and the customer
has been able to accept or reject that part of
the contract - The costs and revenues of each asset can be
identified
9Combining and Segmenting
- A group of contracts, whether with a single
customer or with several customers, should be
treated as a single construction contract when - The group of contracts is negotiated as a single
package - Contracts are closely interrelated that they are,
in effect, part of a single project with an
overall profit margin and - The contracts are performed concurrently or in a
continuous sequence.
10Contract Revenue
- It Comprises
- Initial amount agreed
- Variations in the contract work, claims and
incentive payments to the extent it is probable
that they will result in revenue and can be
measured.
11Contract Revenue
- A variation is an instruction by the customer for
a change in the scope of the work to be performed
under the contract. - A claim is an amount that the contractor seeks to
collect from the customer or another party as
reimbursement for costs not included in the
contract price. - Incentive payments are additional amounts payable
to the contractor, if specified performance
standards are met or exceeded.
12Contract Costs
- It comprises of
- Direct Costs
- Attributable Costs
- Specifically chargeable costs as per the terms of
the contract.
13Recognition of Revenue and Expenses
- To be recognised when the outcome can be
estimated reliably - Contract Revenue and Costs should be recognised
as revenue and expenses - by reference to the stage of completion of the
contract activity at the reporting date. - Expected Loss to be recognised immediately.
14Conditions for reliable estimate
- In case of Fixed Price Contracts
- Total revenue can be measured reliably
- Economic benefits will flow to the enterprise
- Contract costs to complete and the stage of
completion can be measured at the reporting date - Contract costs attributable to the contract can
be identified and measured
15Conditions for reliable estimate
- In case of Cost Plus Contracts
- Economic benefits will flow to the enterprise
- Contract costs attributable to the contract can
be identified and measured
16Stage of completion
- Proportion of costs to the estimated total cost
- Surveys of work performed
- Physical proportion of contract work
17Estimation of Outcome not possible
- Revenue to be recognised to the extent of costs
incurred of which recovery is probable. - Contract costs be recognised as an expense of the
period. - When the uncertainties that prevented the outcome
of the contract being estimated cease to exist,
revenue and costs be recognised.
18Expected Loss
- Expected Loss be recognised immediately when the
total costs are likely to exceed the total
revenue. - Loss is to be recognised
- even if no work has commenced on the project.
- Irrespective of the stage of completion
- Irrespective of the profits accruing on other
contracts.
19Disclosure
- Amount of Contract Revenue recognised
- Method used to determine the contract revenue
- Method used to determine the stage of completion
- For contracts in progress, it should also
disclose - Aggregate amount of costs incurred and recognised
profits
20Disclosure
- Amount of advances received
- Amount of retentions
- Gross amount due from and due to customers.
21ILLUSTRATION
Rs. In Lacs
22ILLUSTRATION
23ILLUSTRATION
24ILLUSTRATION
25ILLUSTRATION
26ILLUSTRATION - DISCLOSURE WORKING
27ILLUSTRATION - DISCLOSURE WORKING
28ILLUSTRATION Contd
Construction ContractsContract revenue
recognised as revenue for the year ended 31st
December XXX 1300 Aggregate amount of
Contract costsincurred and recognised profits
(less recognised losses) upto 31st December XXX
for all the contracts in progress 1435
29ILLUSTRATION Contd
The amount of customer advancesoutstanding for
contracts in progressas at 31st December
XXXX 125 Gross amount due from customers for
contract work presented as an asset 220 Gross
amount due to customers for contract work
presented as a liability (20)
30From Published Accounts
TRF LIMITED Profit on contract is recognised on
percentage completion method. The stage of
completion is determined as a proportion that
contract costs including the cost of WIP in
factory relating to contracts entered into on or
after 01.04.2003 to be in line with revised
Accounting Standard 7, (AS7) incurred for work
performed upto the reporting date bear to the
estimated total costs. Profit (contract revenue
less contract cost) is recognised only when stage
of completion is 40 or more when the outcome of
the contract can be estimated reliably. When it
is probable that the total cost will exceed the
total contract revenue the expected loss is
recognised immediately.
31From Published Accounts
Mukand Limited Accounting for Long Term
Engineering Contracts (a) Revenue for
engineering contract work executed (including
supplies services) is recognised on the basis
of percentage completion method and only after
the work has progressed to the extent of 10 in
each composite contract. Till such time, all the
costs are carried forward to the next accounting
year as Accumulated Contract Costs under
Inventories. Recognition of revenue is matched
with expenses incurred (on accrual basis) after
considering the contract value with associated
costs. Costs and Revenue are both recognised
upto 90 and debtors are reflected accordingly.
Balance is recognised only upon the
Preliminary/Final acceptance of job by the
client. Periodic advances received from customers
are not considered as income.
32From Published Accounts
Mukand Limited Accounting for Long Term
Engineering Contracts (b) Income which arises
out of invoicing of contract work and the
contract costs which are accounted on accrual
basis, are, both credited to income or charged to
revenue, as the case may be, only after at least
10 of the total estimated contract costs (i.e.
direct and indirect costs) are incurred (on
accrual basis). Till such time, all the costs
are carried forward to the next accounting year
as Accumulated Contract Costs under
Inventories and recognition of revenue is
correspondingly postponed. Direct costs include
all expenses specifically attributable to the
contract. Variation in estimates of contract
costs are updated each year by technical
certification.
33From Published Accounts
- Mukand Limited
- Accounting for Long Term Engineering Contracts
- Accumulated Contract Costs, after the stage
when they are not any further to be carried
forward in terms of (b) above, are charged to
revenue to the extent not specifically
attributable to the contract and balance is
transferred to Incomplete Contract Work under
Inventories. - Variations by way of escalation in price and
quantum of work is recognised as revenue in the
year in which claims are lodged as per the terms
of contract. Other claims are recognised as
revenue only upon final acceptance by customer. -
34From Published Accounts
Mukand Limited Accounting for Long Term
Engineering Contracts (e) All facilities in the
nature of assets created at the customers site
and which are to be abandoned at the end of the
contract, are, when under construction, carried
forward at Direct cost-to-date as Facilities at
Customers site Under construction. Upon
subsequent completion, they are carried forward
as Facilities at Customers site Completed
(both being grouped as Other Current Assets).
The completed facilities are written off in equal
annual installments over the period commencing
from the year of completion of the facility upto
the contracted year for completion of the
contract. Billable reimbursements against such
facilities, if separately identified in a
contract, are similarly credited in equal annual
installments against the write-off over the said
period.
35Issues
- Builder Vs Contractor
- Value of Turnover
-