Title: INVESTMENT OPPORTUNITIES IN THE NIGERIAN POWER SECTOR REFORM
1INVESTMENT OPPORTUNITIES IN THE NIGERIAN POWER
SECTOR REFORM
- Ms. Bolanle Onagoruwa,
- Director General
- Bureau of Public Enterprise
Investment Forum, Corporate Council on
Africa 10th March 2011
2Outline
- Introduction
- Objectives of reform in the Sector
- Reform process
- Reform Institutions and Roles
- Role of Private Sector
- Strategy for Increasing Private Sector
Participation - Update on the Privatisation Program
- Challenges
3Introduction
- Estimated 100 million Nigerians are without
access to electricity. - Remainder receive low or irregular supply
- Total installed capacity is about 8,663 MW
(excluding about 4,775 MW under construction. - Available capacity about is about 4842 MW
- 0ver 35 billion dollars of investments required
in the next 5 years - Average energy delivered per employee (GWh/staff)
of 0.66 - 30 percent of electricity billed not collected
4Introduction
- Current Average power generation is 3,200MW
5Objectives of reform
- Increase electrification
- Ensure cost reflective tariffs
- Attract private sector investments into sector
- Create competitive electricity market
- Increase electrification
- Investments in new power generation facilities
- Rehabilitate existing power generation facilities
6Objectives of reform
- Attract private sector investments into sector
- Privatization of state-owned interest in electric
power utilities - Attract Independent Power producers and Oil
companies into power generation. - Ensure cost reflective and competitive tariffs
- Through Multi Year Tariff Order
- Create competitive electricity market
- Entry point competition for new generation
ensures affordable prices for consumers - Transparent regulatory framework and clear market
rules
7Reform Process
- The Electric Power Reform started in 2000 with
the inauguration of Electric power Implementation
Committee.(EPIC) - The National Electric Power Policy document was
approved by the Federal Government in 2001 - NEPA was vertically unbundled into generation,
transmission and distribution in 2004 - The Electric Power Sector Reform Act became law
on 11th March 2005 - NEPA was transformed into PHCN Plc as a holding
company for the assets, liabilities, employees,
rights and obligations of NEPA. The process of
incorporation of PHCN was concluded on 5th May
2005 - NCP by an Order published in a Federal Gazette
gave 1st July 2005 as the initial transfer date
of assets, liabilities and staff of NEPA to PHCN
8Reform Process
- NERC was inaugurated in October 2005 as the
sector regulator - In November 2005, eighteen 18 New successor
Companies comprising of 6 generation
companies, 1 transmission company and 11
distribution were incorporated - The Market Rules to guide the operations in the
electricity industry was approved in 2008. - Relevant market codes (Grid, Distribution,
Performance, Metering etc) have been issued - Companies to carrying on the role of bulk trading
in transition and liability management have been
incorporated as Nigerian Electricity Liability
Management Company (NELMCO) and Bulk.
9Reform Institutions and Roles
- Market operations
- - To oversee the market and commercial
arrangements - System operations
- - Overseeing dispatch and grid control
- Nigeria Electricity Liability Management Company
- - To manage legacy liabilities and stranded
assets - Nigeria Electricity Bulk Trading Co Ltd
- - Created as a Special Trader with bulk purchase
and resale licence - - Manage existing PPAs and new procurement of
power in the transition
10Reform Institutions and Roles
- Electricity Management Services Ltd
- - Carry out consulting services and provide
shared services, such as logistics and meter
testing. - National Power Training Institute of Nigeria
- - Provide world class training to support the
utilities manpower. - Overall broad policy formulation resides with the
Federal Ministry of Power - NERC carries out regulation and market
surveillance - NCP/BPE drives the reform and liberalization of
the power sector.
11Role of Private Sector
- The Power Policy 2001 and Electric Power Sector
Reform Act 2005 identified the Private sector as
the key driver for the future of NESI - The government is to primarily provide, policy
and independent regulation. - The private sector is expected to provide
- Investments
- Managerial capacity
- Technology and
- Competition
12Role Cont.
- To achieve government objectives, the private
- sector is expected to
- Acquire interest or take over existing assets in
in the sector. - Develop green field projects
13Strategy for Private Participation
- Full implementation cost recover structures
through MYTO - Credit enhancement schemes such as
- Industry securitization arrangements
- Partial risk guarantees
- Regulatory certainty( through the reconstitution
of NERC). - Creation of an electricity market and
implementation of market rules. - Massive government investment to strengthen the
grid, including gas infrastructure.
14Strategy
- Nigeria Bulk ElectricIty Trading Company Limited
(NBETCO) is set up to manage orderly procurement
of IPPs in the transition. - Gas Supply and Transportation agreements being
signed under a sector template developed by Gas
Aggregation Company of Nigeria. - Performance improvement benchmarked against the
MYTO assumptions. - Successor companies to operate commercially to
improve sector sustainability.
15Private Participation
- Private participation in the sector may be either
in green-field or brown filed projects. - The privatization program will proceed along
government approved timelines and policies. - Private participation in existing assets will be
through, asset sale, core investor sale,
management contract and long leases (concession).
16Privatisation Strategy
Privatisation Strategies
17Objectives of Privatisation
- Principal objectives of Disco Privatisation
include - Improving efficiency by increasing collections,
reducing technical and non-technical losses and
reducing costs - Increasing access to electricity
- Improving infrastructure through private sector
investment - Ensuring fair tariffs to all end-users
- Increasing commercial viability of the power
sector - Improving customer service
18Companies to be Privatised
- PHCN Successor Generation Companies
- 4 Thermal Generation Plants
- 3 Hydro Plants (2 Hydro Power Companies)
- PHCN Successor Distribution Companies
- 11 Distribution Zones covered by 11 Distribution
Companies
19Companies to be Privatised
Thermal Power Generation Companies Ugheli Power
Plc
20Companies to be Privatised
Thermal Power Generation Companies Geregu Power
Plc
21Companies to be Privatised
Thermal Power Generation Companies Afam Power Plc
22Companies to be Privatised
Thermal Power Generation Companies Sapele Power
Plc
23Companies to be Privatised
Hydro Power Generation Companies Kainji / Jebba
Power Plc
24Companies to be Privatised
Hydro Power Generation Companies Shiroro Power
Plc
25Disco Privatisation Process
- Structure of Disco Privatisation
- Disco Investor / Operator selection will evolve
through 3 key stages - Expressions of Interest
- Technical and Commercial Bids
- Two Step Bid Evaluation
- Technical
- Commercial
26Disco Privatisation Process
- Expression of Interest (EOI) Disco Schedule
- EOI submission closed March 4, 2011
- EOI evaluation has commenced.
- Pre-qualified bidders will be required to sign a
confidentiality agreement and to pay a 20,000
fee for each disco of interest. - List of pre-qualified bidders will be made
available. - Interested investors will be encouraged to join
prequalified firms either financial investors or
technical partners
27Disco Privatisation Process
- Request for Proposal Stage Key Requirements
- Pre-qualified bidders will receive an Info
Memorandum and Request for Proposal - Bidders will be given access to physical and
e-data room. - Bidders will be able to carry out physical due
diligence - Bidders will be issued with draft copies of the
Multi-Year Tariff Order (MYTO) - Bidders are encouraged to submit comments on MYTO
- Bidder comments on MYTO will be subject of
conference to be organized by sector regulator
(NERC)
28Disco Privatisation Process
- Request for Proposal Stage Requirements
- Bidders will be required to submit a proposal
showing their ATCC loss reduction programme for
the first 5 years - The ATCC loss reduction proposal will be based
on the final MYTO issued by NERC - The efficiency levels assumed by NERC in MYTO
will be the minimum bench mark - The value to be placed on each distribution
company will be determined in line with the MYTO
issued by NERC - Bidders will know in advance how much they are
expected to pay for acquiring 51 equity of each
company - Bidders will also be required to submit a
security deposit
29Update on the Privatisation
- Transaction Advisers appointed
- Advert for Expression of Interest in 11
distribution companies on the 13th of December
2010. - Road show organized in Lagos, Dubai, London, New
York and Johannesburg - Submission will close on the 4th of March 2011
- DISCO privatisation will focus on reduction of
ATC losses - Engagement of management contractor for TCN is
currently on. - Sale of non-operational assets in Ijora, Calabar
and Oji still in progress
30Concluding Remarks
- The reform for of the power sector presents
enormous investment opportunities. - Nigeria has put in place investment friendly
initiatives including - Foreigners can own 100 of investment
- Guarantee against expropriation of investments
- Repatriation of profits guaranteed by law
- Generous tax incentives
- One of the highest ROI in the world
31Concluding Remarks
- Huge local market (population of 150million)
- Access to the West African sub-regional market
- Cheap but skilled labour
- Nigeria has embarked on extensive sectoral
reforms and institution of legal/regulatory
conducive to PSP for both existing facilities and
for new investments
32For further details.Electric Power Sector
DepartmentBureau of Public Enterprises234