Real Options, Risk Governance, and Value-at-Risk (VAR)

About This Presentation
Title:

Real Options, Risk Governance, and Value-at-Risk (VAR)

Description:

Real Options, Risk Governance, and Value-at-Risk (VAR) * What is a real option? Real options exist when managers can influence the size and risk of a project s cash ... – PowerPoint PPT presentation

Number of Views:57
Avg rating:3.0/5.0

less

Transcript and Presenter's Notes

Title: Real Options, Risk Governance, and Value-at-Risk (VAR)


1
Real Options, Risk Governance, and Value-at-Risk
(VAR)
2
What is a real option?
  • Real options exist when managers can influence
    the size and risk of a projects cash flows by
    taking different actions during the projects
    life in response to changing market conditions.
  • Alert managers always look for real options in
    projects.
  • Smarter managers try to create real options.

3
Introduction to Real Options
  • Alternative, yet complementary, approach to
    DCF-based Capital Budgeting.
  • Many corporate investments (especially
    strategic ones) have embedded options.
  • Overlooking these options can lead to
  • under-valuing investment projects.
  • Using Real Options approach can improve project
    management as well as valuations.

4
Types of Real Options
  • Abandonment
  • Contraction
  • Temporary suspension
  • Permanent
  • Switch / Transition
  • Change Product Mix
  • Change Input Mix
  • Technical Obsolescence
  • Wait / Timing
  • Resolve Uncertainty
  • Identify Demand
  • Expansion
  • Existing Products
  • New Geographic Markets
  • Growth
  • New Products
  • RD

5
Four Procedures for Valuing Real Options
  • 1.DCF analysis of expected cash flows, ignoring
    the option.
  • 2.Qualitative assessment of the real options
    value.
  • 3.Decision tree analysis.
  • 4.Standard model for a corresponding financial
    option.

6
Analysis of a Real Option Example of a Basic
Project
  • Initial cost 70 million, Cost of Capital
    10, risk-free rate 6, cash flows occur for 3
    years.

7
Approach 1 DCF Analysis (ignoring option)
  • E(CF) .3(45).4(30).3(15)
  • 30.
  • PV of expected CFs (30/1.1) (30/1.12)
    (30/1/13)
  • 74.61 million.
  • Expected NPV 74.61 - 70
  • 4.61 million

8
Procedure 2 Qualitative Assessment
  • The value of any real option increases if
  • the underlying project is very risky
  • there is a long time before you must exercise the
    option
  • This project is risky and has one year before we
    must decide, so the option to wait is probably
    valuable.

9
Procedure 3 Decision Tree Analysis (Implement
only if demand is not low.)
10
Projects Expected NPV if Wait
  • E(NPV)
  • 0.3(35.70)0.4(1.79) 0.3 (0)
  • E(NPV) 11.42

11
Procedure 4 Use the existing model of a
financial option.
  • The option to wait resembles a financial call
    option-- we get to buy the project for 70
    million in one year if value of project in one
    year is greater than 70 million.
  • This is like a call option with a strike price of
    70 million and an expiration date of one year.

12
Inputs to Black-Scholes Model for Option to Wait
  • X strike price cost to implement project
    70 million.
  • rRF risk-free rate 6.
  • t time to maturity 1 year.
  • S (or P) current stock price 67.82 see
    following spreadsheet.
  • s2 variance of stock return 14.2 see
    following spreadsheet.

13
Discounted Cash Flow Valuation and Value-Based
Management
  • Link to Real Options Valuation Excel file
  • FM 12 Ch 13 Mini Case.xls (Brigham Ehrhardt
    file)

14
Relation between Financial Options Real Options
15
Calculating the NPV Quotient (NPVq)
  • _____ NPVq lt 1.0________NPVq gt 1.0_____
  • Negative NPV Positive NPV
  • Calls Out-of-Money Calls In-the-Money

16
Using Black-Scholes to Price a Real Option
  • Identify 5 key Inputs to B-S OPM
  • Initial Investment X 100
  • Current Assets Worth S 90
  • Assets Riskiness s 40
  • Deferral Time 3 years
  • Risk-free Rate 5
  • Note that current NPV -10 but NPVq 1.04
  • Using B-S OPM method, the Options worth
  • .284 90 25.56 !!
  • Above analysis shows that this might be a
    promising project in the future (the option to
    wait is valuable).

17
Tomato Gardens Real Options
18
Real Option Implementation Issues
  • Need to Simplify Complex Projects.
  • Difficulties in Estimating Volatility (use
    simulation, judgment, coefficient of variation)
  • Checking Model Validity (distributions, decision
    trees).
  • Interpreting Results
  • (sensitivity analysis is a must!)

19
Overview of Risk Governance Issues
  • Key Risk Management Responsibilities of Senior
    Managers / Board Members
  • Board / Senior Management must approve firms
    risk management policies and procedures.
  • Ensure that operating team has requisite
    technical skills to execute the firms policies
    and procedures.
  • Evaluate the performance of the risk management
    activity on a periodic basis.
  • Maintain oversight of the risk management
    activity (possibly with a board sub-committee).

20
Ways to Measure Manage Risk
  • Value-at-Risk (VAR) has become a popular summary
    measure of risk.
  • VAR is most useful when measuring market-based
    risks of financial companies (less meaningful for
    many non-financial companies).
  • Precursors to VAR (and still in use)
  • Maturity Gap
  • Duration and the Value of a 1 basis point change
  • Convexity plus Duration
  • Option-based Measures (delta, gamma, vega).

21
Why VAR has Become so Popular
  • VAR provides a succinct, dollar-based summary
    measure of risk which allows management to
    aggregate risks.
  • Also, traditional risk measures had several
    weaknesses
  • They could not be aggregated over different types
    of risk factors/securities.
  • They do not measure capital at risk.
  • They do not facilitate top-down control of risk
    exposures.
  • VAR is easy for senior management to interpret
    It measures the maximum dollar amount the firm
    can lose over a specified time horizon at a
    specified probability level (e.g., the 1-day VAR
    with 99 confidence is 5M)
  • (See Spreadsheet)

22
Calculating VAR (Three Methods)
  • Can calculate VAR via two types of simulation
    methods and one analytic method.
  • Historical Simulation
  • Identify Factors affecting market values of
    securities in the portfolio
  • Simulate future values of these Factors using
    Historical Data
  • Use the simulated Factor values to estimate the
    value of the portfolio several times (usually
    1,000 or more times)
  • Create a histogram of the portfolios expected
    change in value and identify the relevant
    probability level for the VAR calculation (e.g.,
    find the change in portfolio that occurs at the
    lowest 1 of the distribution).

23
Calculating VAR (cont.)
  • Monte Carlo Simulation
  • Follow the same steps as in the Historical
    Simulation method except you use Monte Carlo
    techniques to obtain the simulated Factor values
    (step 2 of the previous slide).
  • Analytic Variance-Covariance Method
  • Can be simpler to estimate since you dont need
    the entire distribution of Factor values (summary
    measures will suffice).
  • Specify Distributions and Payoff Profiles (e.g.,
    normal and linear).
  • Decompose Securities into Simpler
    Transactions/Buckets.
  • Estimate Variances/Covariances of Standard
    Transactions
  • Calculate VAR based on standard definition of
    variance.

24
Strengths / Weaknesses of the Three VAR Methods
  • Historical Simulation does not assume specific
    distributions for the securities and uses
    real-world data but it requires pricing models
    for all instruments and allows limited
    sensitivity analysis.
  • Monte Carlo Simulation makes it easier to do
    sensitivity analysis but requires the analyst to
    specify asset distributions as well as pricing
    models (also, one step removed from real-world
    prices).
  • Analytic Method is intuitively simpler and does
    not require any pricing models but it is not
    conducive to sensitivity analysis and cannot
    handle non-linear payoff profiles such as options.

25
Differences in VAR Estimates from the Three
Methods
  • Empirical Tests to date, tests of the three
    methods suggest that the approaches can yield
    similar results when
  • Portfolio payoffs are linear.
  • 95 confidence level is used.
  • There are not many large outliers in the
    historical data set.
  • Where Differences can Occur biggest differences
    can occur between the 2 simulation approaches and
    the analytic method when
  • Non-linear payoffs are a significant share of the
    portfolio and they do not cancel out (e.g., long
    a large number of put options).
  • Large number of outliers in the historical data
    set.
  • 99 or higher confidence level is used.

26
Choosing between the Methods
  • As in much of life, It Depends!
  • If the portfolio has linear (or weakly
    non-linear) payoffs, then the Analytic method
    might be best.
  • If the portfolio has strongly non-linear payoffs,
    then the two Simulation methods are better.
  • If stress-testing and sensitivity analysis are
    needed, then Monte Carlo Simulation is the
    preferred method (however, it can be very complex
    to remove all possible arbitrage opportunities
    from the simulation).

27
Who Should Use VAR?
  • Firms that have their values determined primarily
    by financial market risks should use VAR (e.g.,
    Investment banks, Brokers/Dealers, as well as
    CBs and Insurance Cos with active trading
    portfolios).
  • Firms that have their values determined by growth
    opportunities or growth options probably should
    not use VAR as their primary risk measure
  • (e.g., high tech or bio tech firms).
  • For firms with growth options, a VAR estimate is
    typically not relevant because the real value of
    these companies comes from non-traded assets
    where no-arbitrage arguments typically do not
    hold.

28
Implementing VAR
  • Parameter Selection
  • Time Horizon (e.g., 1-day or 10-day VAR)
  • Confidence Level (usually 95 or 99)
  • Variance-Covariance Data (unstable correlations
    vs. 1.0)
  • Other Important Issues
  • Sensitivity Analysis (how sensitive is the VAR
    estimate to the data set used in the analysis?)
  • Scenario Analysis (worst case vs. standard
    case)
  • Stress-testing (how does VAR change as the above
    parameters change?)
  • Back-testing (how good have past VAR estimates
    been in relation to actual portfolio changes?)
Write a Comment
User Comments (0)