Title: Building a Web-Based Reporting System: Lessons Learned
1Building a Web-Based Reporting System Lessons
Learned
2Presenters
- Jacque Frost
- Chris Maxwell
3Presentation Overview
- Project plan and required resources
- Tool demonstration
- Project timeline
- Issued faced and lessons learned
- Working with Information Technology
- Working with the data owners
- Data issues
- Policy/Security issues
- Summery
4Why a Web-Based Reporting System
- Meet increasing unit level data requests
- Provide data to non-experts
- Decrease OIR ad-hoc reporting volume
- Provide data standardization
- Provide roll-up to official totals
- Consistency in unit Strategic Plans
5Planned Project Scope
- Web tools
- 100 thin-client
- Intuitive in use, zero training
- Reporting focus
- Most requested type of information
- Start with drilling into the Data Digest totals
- Will not be comprehensive or a full BI solution
6Planned Resources Required
- Institutional Research (OIR)
- Will be responsible for application development
- About 0.4FTE for up to a year to establish a
series of web tools - Information Technology (IT)
- Purchase, install, configure software
- Set up and maintain server
- Troubleshoot as needed
7A Typical Tool
- Student Enrollment Tool Restricted Access
8Project Timeline
- November 2002 Development begins
- February 2003 First application published
- August 2003 First production tool published
- October 2003 First three Data Digest tools
published
9Project Timeline (cont.)
- February 2004 Salary tools and portal published
under direction of provost - July 2004 Sponsored Program Services (SPS) tools
published - November 2003 - Present More Data Digest and
other tools are published, tool edits continue.
Service also used for data collection and surveys
10Issues Faced and Lessons learned
11Working with Information Technology (IT) Issues
Faced
- Initial Resistance
- Did not see need for pre-BI solution
- Did not want to support non-IT chosen technology
- Not in line with ITs OnePurdue vision
- Agreement to OIR plan for project
- Additional support IDN datamart project
- If you cant beat them, join them!
12Working with IT Lessons Learned
- Do not give up or give in on key issues
- If necessary, use the leverage of the OIR office
- Always look forward
- Concentrate on successes
- Leave conflicts behind
13Working with the Data Owners Issues Faced
- Publishing web tools can make OIR look like the
data owner - OIR does not own the data - yet is providing it
at any imaginable level of breakdown, at any time
with the click of a mouse - Encountered initial data owner resistance/concerns
- Data security/policy issues
- Loss of control over the information
14Working with the Data Owners Lessons Learned
- Involve them very early in the process - show
them the earliest drafts of the web tool - Communicate continually
- Quickly address concerns and suggestions
- Use a sign off policy on tool release
15Working with the Data Issues Faced
- Web tools are very demanding of the data
- Great data for campus reporting can look much
worse on drill downs - Data availability was a critical limiting factor
in this project - Time needed to build a typical new tool days
- Time needed to get signed off data months
16Working with the Data Lessons Learned
- Do not wait until the data are perfect
- Release tools with notes and caveats
- In general, do not fix the data with application
programming - The web tool needs to agree with SQL database
queries that use the same criteria - Allow the web tool to expose some deficiencies,
it can spur data owners and IT to make fixes
17Security and Policy issues
- FERPA
- Drill downs can easily expose unit1 records
- Internal Purdue policies
- Might not be well documented in one case we
received a waiver - Goal is to provide access to anyone with a
business need for the information - No real sensitive information available with
tools
18Summary
19Overall Results
- Project was a success!
- Proceeded on schedule with anticipated resources
- ITs IDN datamart project was a plus
- Tool use
- 3,000 primary queries by about 300 users in our
first full year (Oct 03 Sep 04) - Increasing traffic now averaging about 18
primary queries per business day
20Overall Results (cont.)
- Still the source for Purdue data over the web
- ITs BI tool still not in production
- Standardization of reported data a big plus
21Overall Lessons Learned
- IT support role / OIR application developer role
worked very well - Used strengths of each area
- OIR control of tools enabled very fast turn
around times for any needed edits / enhancements - Data Digest totals validated the tools
- In retrospect, could have more aggressively
marketed the project
22Overall Lessons Learned (cont.)
- Tool logging is invaluable
- Technical issues were not the most challenging
aspects of this project - Data, people, and politics
- Accept politics as an integral part of the project
23- This is exactly what I need. Now I can sleep
peacefully over the weekend!
24QUESTIONS/COMMENTS