1Procedures for Aerodrome Certification in
PakistanModule - 8
AERODROME CERTIFICATION COURSE
2Procedures for Aerodrome Certification
- Objectives
- Identify and discuss Steps of Aerodrome
- certification Process.
- Review the preparation requirements associated
with inspections. - Discuss phases of on site inspection and post
inspection activities.
3Procedures for Aerodrome Certification
AERODROME CERTIFICATION
Directorate of Air Navigation and Aerodrome
Regulations
4Procedures for Aerodrome Certification
- Aerodrome Certification Procedures should
- comply with the legislation
- identify the controlling regulations/
requirements - be exercised by officials/Inspectorate Staff of
DAAR, CAA Pakistan - use common formats and
- cover all the tasks associated with certification.
5Procedures for Aerodrome Certification
- Tool to be used by DAAR
- Aerodrome Certification Procedures Manual
- Aerodrome Inspector Handbook
6Aerodrome Certification Procedures Manual
- Aerodrome Certification Procedures Manual should
content procedures for - Assessment of application for aerodrome
certificate - Grant and Issue of aerodrome certificate
- Granting exemptions
- Renewal of aerodrome certificate
- Amendment of aerodrome certificate
- Surrender of aerodrome certificate
- Suspension and cancellation of aerodrome
certificate - Amendment of aerodrome manual.
7Aerodrome Certificate Procedures Manual
- Aerodrome Certification Procedures Manual should
content forms for - Application for Issue/Renewal of Aerodrome
Certificate
8Aerodrome Certification Procedures Manual
- Aerodrome Certification Procedures Manual should
content sample of Aerodrome Certificates and
sample letters for - Grant of an Aerodrome Certificate
- Refusal to Grant an Aerodrome Certificate
- Granting Exemptions
- Cancellation by Surrender an Aerodrome
Certificate - Amendment of an Aerodrome Certificate
- Non-consent to Amend an Aerodrome Certificate
- Warning Notification
- Suspension of an Aerodrome Certificate
- Cancellation of an Aerodrome Certificate
9Aerodrome Certification Procedures Manual
- Aerodrome Certification Procedures Manual should
content following checklists - Aerodrome Certificate Issue Checklist
- Aerodrome Certificate Surrender Checklist
- Aerodrome Certificate Amendment Checklist
- Aerodrome Certificate Suspension or Cancellation
Checklist - Aerodrome Manual Amendment Checklist
10Aerodrome Certification Procedures
- Step 1 - Assessing a formal application
- Designated officials of DAAR, CAA Pakistan needs
to be satisfied before a Certification process
can be proceed for the issue of Certificate - an application made in the prescribed form and
duly filled up D2.2 of ANO-001-DRAS-1.0 - an Aerodrome Manual including establishment of an
effective Safety Management System is provided
D2.11, D4, D5 D7 of ANO-001-DRAS-1.0
11Aerodrome Certification Procedures
- Step 1 - Assessing a formal application (contd.)
- submitted a compliance checklist in respect of
the requirements contained in CAR issued on the
subject of Aerodrome Design and Operations and - fee is remitted by crossed Demand Draft drawn in
favour of Pay Accounts Office, CAA Pakistan.
12Aerodrome Certification Procedures
- The minimum period required for processing the
application is about one month from the date of
receipt of application along with properly
formulated aerodrome manual to allow for detailed
consideration and inspection of the aerodrome
before the issue of a Certificate Section 2.5.1
of ACCP.
13Aerodrome Certification Procedures
- Step 2 Assessment of the Aerodrome Manual and
associated documents for acceptance/approval by
DAAR, CAA Pakistan in accordance with the
National Framework - does it comply with regulations/ requirements
(completeness) ? - does the management system indicate proper
operation and maintenance will occur? - review and identify any gray areas and return to
the applicant as needed to clarify those areas. - Refer to ACP Pakistan
14Aerodrome Certification Procedures
- Step 3 Initial Inspection of the Aerodrome
Facilities, Services and Equipment D8 of
ANO-001-DRAS-1.0. - To be conducted before granting an aerodrome
Certificate. - Purpose
- To ensure that the aerodrome is adequately
staffed with competent and trained personnel - To ensure that aerodrome facilities, services and
equipment meet national and international
standards - To ensure that aerodrome manual is sufficient
- To ensure that a Safety Management System is in
place and functioning.
15Step 3 Initial Inspection of the Aerodrome
Facilities, Services and Equipment
- Inspection Phases
- Inspection Preparation
- Entry Meeting and Inspection In Briefing
- Administrative Inspection
- Field Inspection (day and night inspection)
- De-briefing on Inspection (Exit Meeting)
-
- Post Inspection Activities
- Inspection Report
- Follow-Up Activities
- Closing Inspection Findings
16Inspection Phases
- Phase 1 Inspection Preparation
- Plan and coordinate with aerodrome operator for
the inspection of the aerodrome (on site visit) - Determine the make-up and size of the DAAR
inspection team needed (is more than 1 inspector
required, what other skill areas will be
needed.) - Prepare an inspection programme/schedule and
provide to the aerodrome operator - Ensure that the aerodrome operator has conducted
necessary coordination with other agencies
working at the aerodrome ATS providers, Airport
Security force and others as necessary.
17Coordination With ATS Providers
18Inspection Phases
- Phase 1 Inspection Preparation (contd.)
- Review the following documents
- Aerodrome manual
- Any approved exemptions
- Previous inspection records
- Instrument approach charts
- Obstruction charts
- Accident and incident history
- Pending construction plans and documents.
19Inspection Phases
- Phase 1 Inspection Preparation (contd.)
- Equipment to take
- Camera
- Handheld GPS
- Handheld compass
- Inclinometer
- Distance measuring wheel
- 50 100 m measuring tape
- Calculator
- Radio for ATC Communications
- Appropriate clothing
- Necessary forms and records.
20Inspection Phases
- Phase 2 Entry Meeting and Inspection In Briefing
- Conduct entry meeting with the Airport Manager
(senior aerodrome management) - Inspection in briefing with key aerodrome staff
- Review inspection schedule
- Current airport status
- Recent new developments
- Coordinate ARFF response test
- Coordinate inspection of the movement area
- Coordinate night inspection
- Include comments and/or concerns of aerodrome
operators.
21Inspection Phases
- Phase 3 Administrative Inspection
- Review aerodrome manual and SMS
- Review NOTAM records
- Review RFF training records
- Review aerodrome operators self inspection
records - Review fuel safety inspection records
- Review aerodrome emergency plan (including
full-scale exercises conducted) - Review disabled aircraft removal plan
- Consider conducting a survey of aerodrome
personnel or having selected staff complete a
questionnaire.
22Inspection Phases
- Phase 4 - Conduct the site visit for verification
of all areas in the aerodrome manual - verify all the aerodrome data on-site
- check and test physical characteristics,
facilities and equipment - dimensions and surface condition of movement
areas and associated strips, shoulders and safety
areas - obstacles at and in the vicinity of the
aerodrome - aeronautical ground lights (approach and runway
lights) - lights that could produce glare
23Taxiway Centreline lights
24Inspection Phases
- Phase 4 - Conduct the site visit (contd.)
- standby power systems
- wind direction indicators (illuminated)
- markings, signs and markers
- Obstruction markings and lights
- ground earthing points
- aerodrome perimeter wall and fencing
- RFFS equipment (meets category?)
- fuelling facilities
- construction areas
25Illuminated Windsock
26Taxiway Edge Markings and Lights
27Inspection Phases
- Phase 4 - Conduct the site visit (contd.)
- competence and training of aerodrome operators
staff - aerodrome maintenance equipment
- runway sweeping equipment
- disabled aircraft removal equipment
- wildlife management equipment
- radio transceivers in vehicles and hand held
- Coordinate and conduct any flight-checks
required.
28Inspection Phases
- Phase 4 - Conduct the site visit (contd.)
- While inspecting Fire Fighting Services
Example - Inspect RFF personnel training records
- Randomly check the knowledge of fire-fighters
- Conduct a timed-response drill
- Check the alarm system
- Check the personal protective equipment
- Check the fire-fighting and rescue equipment
- Check supplies and stores of agent.
29Rescue and Fire Fighting Services
30RFF Equipment
31Condition of Alarm System
32Inspection Phases
- Phase 4 - Conduct the site visit (contd.)
- Fuel Safety Example
- Observe if the aerodrome operators conducts
adequate fuel safety oversight - Ensure that fire safety is incorporated into
local RFF standards - Ensure aerodrome is complying with local fire
safety regulations fire code.
33Inspection Phases
- Phase 4 - Conduct the site visit (contd.)
- Night Inspection
- Check visibility of pavement markings
- Insure that runway and taxiway lights are correct
and clearly visible - Obstruction and construction areas are clearly
visible - Check for night time wildlife activity.
34Obstruction markings and lights
Marking and lighting of glide path antenna
and hut.
35Inspection Phases
- Phase 5 De-briefing on Inspection (Exit
Meeting) - Consolidate all notes/comments developed during
the inspection - Review the results of the inspection with the
operator (major findings) - Determine/establish correction dates for
discrepancies (minor discrepancies) - Require immediate corrective action for unsafe
conditions
36Installation of DVOR/DMEThe Crane Boom
Penetrating Approach Surface
Immediate Corrective Action for Unsafe Conditions
37Post Inspection Phases
- Phase 1 Inspection Report
- Contents
- Formal Inspection Report
- Inspection Findings
- Conclusion and Recommendations
- Attachments
- Formal Report to Aerodrome Operator of
Discrepancies - Inspection Checklists
- Inspection Finding Forms
- Recommended Supplemental Paper work, such as
- RFF timed response drill
- AEP review etc.
38Post Inspection Phases
- Phase 2 Follow Up Activities
- Inspection reports should be filed to allow for
periodic follow-up on existing discrepancies. - Corrective action plan established with agreed
correctives dates. - Monitoring the implementation of corrective
action plan. - Reminder letters.
- Move to enforcement action if operator fails to
comply with corrective action plan.
39Post Inspection Phases
- Phase 3 Closing Inspection Findings
- Corrective action plan is closed when all
discrepancies are corrected or are transferred to
another form of action (i.e. transferred to a
long term corrective action plan). - Final close-out letter is sent to aerodrome
operator officially closing out the inspection. - All documents are filed appropriately.
40Aerodrome Certification Procedures
- Step 4 Grant or Refusal of Aerodrome
Certificate - If the assessment was unsuccessful DAAR should
formally notify the applicant, stating reasons
why the aerodrome Certificate has not been
granted - major findings were observed which affect on
safety of aircraft operations - aerodrome operator need to submit the corrective
action plan on those findings and rectify
accordingly. - After submission by the aerodrome operator an
action taken report to DAAR, the follow up
inspection may be planned.
41Aerodrome Certification Procedures
- Step 4 Grant or Refusal of Aerodrome
Certificate - If the assessment was successful, DAAR will
- formally notify the applicant, and
- provide an aerodrome Certificate with validity of
three years period subject to certain conditions,
if deemed necessary. - Exemptions to non-compliances with certain
Regulations/ Requirements would be granted if the
aerodrome operator had applied for with full
justification and submission of report on safety
assessment carried out.
42Aerodrome Certificate Public Use Category
43Aerodrome Certificate Public Use Category
44Aerodrome Certificate Public Use Category
45Aerodrome Certification Procedures
- Step 5 Administration of aerodrome Certificate
and on-going safety assurance - Procedure should account for
- administrative tasks
- initiating surveillance programs.
- Step 6 CAA Pakistan internal notification and
advising AIS and Industry of a newly Certificated
Aerodrome - Procedure for notification of a newly
Certificated aerodrome - within CAA Pakistan
- to Aerodrome Operators and aviation industries
- publication in CAA Pakistanwebsite in the list of
Certificated aerodromes.
46Administration tasks associated with the issue of
Aerodrome Certificate
47Thank you End of Module 8 Procedures for
Aerodrome Certification in Pakistan
48Procedures for Aerodrome Certification in Pakistan