CPMC Cathedral Hill Hospital Project - PowerPoint PPT Presentation

1 / 41
About This Presentation
Title:

CPMC Cathedral Hill Hospital Project

Description:

CPMC Cathedral Hill Hospital Project Look ahead planning at design and preconstruction Lessons learned Baris Lostuvali Jessica Kelley – PowerPoint PPT presentation

Number of Views:62
Avg rating:3.0/5.0
Slides: 42
Provided by: p2slBerke
Category:

less

Transcript and Presenter's Notes

Title: CPMC Cathedral Hill Hospital Project


1
  • CPMC Cathedral Hill Hospital Project
  • Look ahead planning at design and preconstruction
  • Lessons learned

Baris Lostuvali Jessica
Kelley HerreroBoldt Southland
Industries CHH Structural Cluster
CHH MEP Cluster
2
  • Agenda
  • Project Background
  • Lean Design Principles
  • LPS process and look ahead planning
  • Future state
  • QA

3
CHH Project Background
4
CHH Project Background
5
CHH Project Background
  • Extension of urban core
  • Improved narrower profile
  • Appropriate to Van Ness Ave. character
  • Less off site sun view impacts
  • Massing sympathetic in height
  • and scale to the neighborhood
  • Improve downtown view

6
CHH Project Background
7
CHH Project Background
8
Lean Design Principles
  • Set Based Design
  • An iterative process of developing sets of
    solutions that satisfy cost, function and
    quality.
  • Sets of solutions are advanced until the last
    responsible moment
  • Sharing Incomplete Information Often
  • Willingness of team members to continuously share
    incomplete information.
  • Daily or at least weekly sharing of design and
    budget information.
  • Design and budget evolve simultaneously
  • Simultaneous design of Product and Process
  • Product and process design decisions are made
    simultaneously.
  • 3D Design / Modeling, and Digital Prototyping
  • Use digital prototyping to integrate design and
    cost characteristics.
  • Provide widespread access to the design model as
    it evolves.

9
Lean Design Principles
  • Detailed design by specialty contractors and
    vendors
  • Designers and engineers produce only those
    deliverables needed for permitting and needed by
    specialty contractors or other suppliers for
    detailing.
  • Multidisciplinary Design Teams - Designers,
    Facility Users, Constructors, Major specialty
    contractors and suppliers are contracted early
  • Value based proposal process.
  • Specialty Contractors and Suppliers work together
    early in the Design Phase to simultaneously
    develop the design and budget.
  • Multidisciplinary teams meet at least weekly.
  • Production Planning and Management
  • Production Planning and Management is applied
    during the Design phase using Constraints
    Analysis, and Weekly Work Plans.
  • Design and budget production is planned and
    managed to emulate a continuous flow process.
  • Project Based Production Management is formally
    applied using standard Lean Processes and
    Principles

10
Information flow - a typical design process
courtesy of
11
Information flow Typical tools
12
Information flow - Now we have the data Great !
courtesy of
13
Information flow - Goal
  • The right information
  • at the right place
  • at the right time

14
The Planning Scale
Project Level Activities
Phase Level Milestones
Phase Level Activities
Lookahead Tasks
Work Plan Tasks
Learning
15
Who is the Last Planner on CHH?
  • The Closest Management Person to the Actual Work
    Being Done within a Cluster Group
  • In Construction the Last Planner is Generally a
    Foreman
  • Last Planners will be Formally Designated and
    Coached

16
The Planning Leadership
Cluster Groups CG Leader
IPDT Production Planner
IDPT Master Scheduler
Project Level Activities
Phase Level Milestones
Phase Level Activities
Lookahead Tasks
Work Plan Tasks
Learning
17
Plan Development Detail
18
Master Schedule
19
Master Schedule Primavera P6
Master Schedule with Phases
20
Master Schedule
  • Primavera P6 central database.
  • Web access.
  • Milestones based on Senate Bill requirements,
    OSHPD, Owner business plan, and IPDTeam.

21
Alignment Meetings
22
Alignment Meeting
  • Focus on next near milestones to better define
    the deliverables within the phases.
  • For each milestone.
  • Identify the customer.
  • Brief on each milestone.
  • Clarify Conditions of Satisfaction.
  • Verify Responsibilities.
  • Not a discussion about sequence, or time, or
    dates.

23
Phase Scheduling
24
Phase Schedule Session
  • Perform a Reverse Phase Schedule (sequence using
    pull methods).
  • Build the schedule in terms of pre-requisite
    work, information, materials, tools, etc needed
    to complete the successor activity.
  • Identify specific Constraints (constraints log).
  • Use 8x5 cards while someone generating live in P6
    so that there is a distributable plan by the end
    of the session.
  • The Phase is the expanded detail within the
    Master Schedule

25
Look ahead Plan Weekly Work Plan
26
Lookahead Schedule View Primavera P6
6 Week Lookahead View
Master Schedule with Phases
27
Lookahead Schedule to Lookahead Plan
6 Week Lookahead View
View from Phase Schedule transfer to Plan
Lookahead Plan informs Phase Schedule
28
Six Week Lookahead View to Lookahead Plan
  • P6 to Excel.
  • Filter 6 Weeks from P6 Phase Schedule to be used
    in the Cluster Group facilitated Excel Lookahead
    Plan.
  • There is more detail on the Cluster Group
    WWPLookahead Plan than there will be in P6.
  • The Lookahead Plan is the internal workings of
    the Cluster Group.
  • Allows for the Cluster Groups to modify their
    plan freely without constantly changing or
    confusing the Phase Schedule.
  • Production Planner with Master Scheduler compare
    the information.
  • Color coding and Shared IDs are cues for updating
    the Phase Schedule.
  • The Lookahead does not have to be in Excel, it is
    an easy format that almost anyone can comprehend.

29
Weekly Work Plan Lookahead
EXAMPLE
30
Weekly Work Plan Lookahead
Metrics
Lookahead Plan
Weekly Work Plan
Constraints Prompt
Shared ID
Pull Lookahead onto WWP
31
Lookahead Planning Sessions
  • Start with a Six Week Lookahead View taken from
    the Phase Schedule.
  • Break week 1 and 2 of Phase Activities into Tasks
    that can essentially fit onto a Weekly Work
    Plan.
  • Review weeks 3, 4, and 5 to ensure that all
    constraints will be removed.
  • screen activities for constraints (materials,
    information, obstacles, permissions, anything
    hindering an activity from happening).
  • Achieve commitments to ensure the constraint
    removal.
  • The team only allows tasks to keep their
    scheduled dates if there is confidence that all
    constraints will be removed.
  • At this point planning is a regular non-formally
    scheduled meeting, it is part of everyday work.

32
Where are We? Constraint Log
33
Planning Cycles.
Monday
Tuesday
Wednesday
Thursday
Friday
Phase Schedule Informed from Cluster Group
Lookahead Plans
MEP
Equipment
Trade Coord
EIR
Core Group
Core Group
Exterior
Interior
Sustainability
Technology
Structural
6WLA View Distribute
Integrated Planning
IPDT LP Meeting
Master Schedule Informed from Phase Schedule
Continuous Update of Planning Wall
34
Metrics
  • Percent Planned Complete (PPC)
  • Tasks Anticipated (TA)
  • Tasks Made Ready (TMR)
  • Categories of Variance
  • Tasks Repeated
  • Root Cause Analysis (5 Whys)

35
IPDTeam Last Planner Meeting almost there
  • All are invited.
  • Brief Briefing on Phase Schedule.
  • Another forum to remove constraints.
  • 10 minutes each cluster group to report on
    current plan andmake requests, requires to be
    well prepared.
  • Not a working session (other than 5 Why).
  • Present root cause analysis (5 Whys) from
    Cluster Groups that can be learned from as an
    IPDT.
  • Focus on learning from plan failures.

36
Integrated Planning Meeting
  • Who attends?
  • Master Project Scheduler and Production Planner.
  • Cluster Group facilitators (representatives from
    both design and construction).
  • Discuss and update the Phase Schedule as it
    relates to current areas of focus and concern.
  • Forum to release constraints.
  • A live P6 working session.

37
Where are We?
  • Learning about how to take the detailed planning
    of the cluster groups to inform the master and
    phase schedule while recognizing the iterative
    ever changing nature of design.
  • Not plan people to death.
  • This is our future state and in the future it
    will look nothing like this.

38
Where are We? Identify the key interdependencies
between clusters
39
Where are We? First Run Study
40
Future state
  • Traditionally, the design phases of projects
    suffer from
  • Temporary organizations / departmental silos
  • poor understanding of complexity
  • inevitable iteration rework
  • unforeseen changes
  • inappropriate project management methodologies
    tools
  • What is working now
  • The right information at the right place at the
    right time
  • Better foresight thru LPS and look ahead planning
  • Highlight the interfaces between disciplines
  • Co-location is effective and powerful
  • Integrating the design development processes of
    all participants
  • What we are focusing on for future improvement
  • Identifying process knots and options for
    unraveling them
  • Continuing to utilize appropriate management
    methodologies tools
  • Using tracking metrics more to adjust current
    planning

41
THANK YOU !
What are your takeaways?
What questions have been provoked?
Baris Lostuvali Jessica
Kelley HerreroBoldt Southland Industries
Write a Comment
User Comments (0)
About PowerShow.com