Title: PowerPoint-Prдsentation
1Status of FAIR J. Eschke, FAIR JCT
- Status FAIR technical preparations
- Status FAIR preparatory phase EU project
- Status negotiations / international contributions
- FAIR start scenario?
- FAIR launch event November 7-8, 2007
- Roadmap toward the FAIR GmbH
2Scientific / technical project preparations
-
- FAIR machine mini-TAC meetings
- Charge to the review groups CERN, April 21st,
- Review of Civil Engineering, May 14th
- RF review, May 15th, (Video-conference)
- Controls review, May 15-16th
- Proton Linac review, May 17th
- Review of Magnets and Cryogenics, May 24-25th
- Review of Lattices and beam dynamics, June 5th
- Review of Power Converters, June 5th
- FAIR machine TAC Meeting 11-13 June, 2007
- STI meeting 31 July 2007
- STI meeting 11 September 2007
-
3Listed experiment collaboration and related
meetings, since April 2007 CBM Workshop on
Silicon Detector Systems , April 18-20, 2007 at
GSI Workshop on Electromagnetic Probes of
Strongly Interacting Matter The Quest for
Medium Modifications of Hadrons June 18-22
2007, at ECT in Trento Workshop on Critical
Point and onset of Deconfinement, July 9-13,
2007 at GSI 10th CBM Collaboration Meeting
September 25 -28, 2007, in Dresden PANDA PANDA
Magnet Review at GSI 19. - 20. April
Collaboration Meeting at Dubna, July
2nd Collaboration Meeting at GSI, September
17-19th Collaboration Meeting in/at GSI December
10-14th SPARC Theory Group Meeting at GSI,
July, 17-18, 2007 NuSTAR NUSTAR Board of
Representatives Meeting, July 23, 2007
4Members of FAIR-TAC-2007
New chair of the Technical Advisory Committee
Thomas Taylor (CERN)
5Outcome 1
- TAC welcomes the creation of a FAIR Joint Core
Team and Technical Division and their visible
effect on project progress. - TAC is impressed by the remarkable achievements
obtained over the last 18 months. These
achievements demonstrate capability and give
confidence that success is within reach. - Considering that the project will effectively
begin one year later than assumed in the FBTR,
finds it unavoidable that the published schedule
is delayed by one year. - FAIR will be a state-of-the-art facility for
physics, the realization of which is a recognized
challenge.
6Since BaselineTechnical Report
- Machine lattices have been re-optimized and are
fixed now - HEBTs re-calculated
- simplifications by using nc rather than sc
magnets werever possible - Optics discussed and checked with external
experts (Hinterberger) - HESR further optimized (driven by FZ Jülich
TSL) - Recent discussion for nc lattice (field
tolerances) - Synchrotron SIS 100
- Performance limitations of NUCLOTRON magnets at
4 T/s - Synchrotron SIS 300
- Detailing of straight sections for transfer
SIS100 300 (injection) and extraction - Beam stability
- Non-linear studies on stability issues in
SI18/SI100/SIS300 - HEBT p-bar separator CR
minimize
losses due to chromatic aberrations - RESR focusing structure
- work on-going
- Stochastic Cooling
- Hardware procurement for test-stand under way
7Outcome 2
- The Committee is pleased that many of its
previous recommendations taken into account and
that significant progress has been made since its
last meeting. - the Committee advocates to focus efforts of
superconducting magnet development on the SIS300
and to seriously consider fall-back solutions
based on normal conducting magnets wherever
possible - for example in SIS100, HESR and beam
transfer lines. - The committee suggests to decouple the
installation of SIS-300 from that of SIS-100.
This would ease the commissioning of SIS-100 and
the scheduling of production and on-site
reception of the sc magnets of SIS-300.
8Progress in FAIR Hardware RD
MoU on prototype RD SIS300 bending
magnet Funding 3.7 M INFN, 1 M GSI
MoU on prototype RD SIS300 bending magnet IHEP
and GSI
Proton linac klystron ordered at Toshiba
low power CH-structure model tested
Start of procurement for test
stand Super-FRS quadrupole contract (Toshiba)
radiation resistant magnets
(BINP) Study on nc/sc magnets for NESR/RESR
(ELYTT)
Straight mark I full scale magnet under
fabrication at BNG / Würzburg Curved mark I full
scale magnet under fabrication at BINP /
Novosibirsk RD continued at JINP / Dubna
9Lab Directors meeting on accelerators in FAIR
- Preliminary Agenda October 1st and 2nd, 2007 at
GSI - October 1st, 2007
- 1400 Start of Meeting
- Presentation on the current status of the FAIR
project - Principles of FAIR In-Kind Contributions
- Work package structure
- Status of Specifications
- On-going RD projects for FAIR
- Expressions of interest for certain work
packages (presentations by lab directors or
their representatives) - October 2nd, 2007
- 900 Expressions of interest for certain work
packages contd ((presentations by lab
directors or their representatives) - 1400 Round table discussion
- 1600 Concluding session
- 1700 End of Meeting
10EU FP7 Preparatory Phase proposal for FAIR
- EU FP7 call for ESFRI roadmap projects
- - Scope support for preparatory phase of all
ESFRI roadmap projects - - Total budget of this EU call 130 M for 34
ESFRI project - - Up to 7 M EU support per project -- on average
4M - - Contract duration 1 4 years
- - Deadline for submission of proposals 2 May
2007 - Intention and ultimate goal of this EU call
- - "Implementation of project"
- - Main milestone signature of construction
agreement between partner countries - Main focus of proposal
- - Work on legal, organisational (project
management), governance, strategic and - financial issues (technical work only under
certain conditions) - - EU funding 100 (except for technical work)
- It is mandatory to include ministries and / or
funding agencies as participants in the proposal
11proposal over 7 M submitted on April 30, 2007
July 07 very good evaluation result
____________________________________
EC funding 4,9 M
official launch contract negotiations shall be
concluded fast
draft Annex-I has been submitted to EC
negotiation meeting on 14.9.2007
12FAIR EU FP7 "preparatory phase" project will be
funded by the European Commission
- The consortium of 27 participating institutions
(including 12 ministries or funding agencies) of
this EU project will receive 4,9M for the
personnel of the FAIR JCT and later of the FAIR
GmbH - Duration of the EU contract
- 36 months, start 1.8.2007
- The project covers seven work packages (WP),
which cover - all important coordination activities
mandatory for the "implementation" of FAIR! - - no technical Work packages
13Participation of Funding Agencies and Ministries
- Ministry of Science and Higher Education of
Poland - INFN Italy on behalf of the Ministry of Research
and University - Swedish Research Council
- Rosatom Russia
- BMBF Germany
- Ministry for Research France
- Ministry for Education Austria
- Helsinki Institute of Physics on behalf of the
Ministry of Education of Finland - Romanian National Authority for Scientific
Research on behalf of the Ministry of Research - Department of Science and Technology, India
14Nominated international members of FAIR Joint
Core Team
Link person country Z. Majka, Crakow,
Poland Link persons experiments PANDA G. Boca,
Pavia, Italy S. Tomassini,
Accelerator Division at LNF, Frascati,
Italy CBM R. Karabowicz, Crakow, Poland
D. Dutta, BARC, Mumbai and Anand Kumar Dubey,
VECC, India (1 FTE) D. Cozma and M.
Petris, NIPNE, Romania (1 FTE) S.
Belogurov, ITEP, Russia (?) NUSTAR Heikki
Penttilä, UNIVERSITY OF JYVÄSKYLÄ, Finland
W. Korten, CEA, Saclay, France
C. Mihai and T. Sava, NIPNE, Romania (1
FTE) C. Domingo, CSIC,
Spain APPA (SPARC, FLAIR,..) M Czarnota,
Institute of Physics, Kielce, Poland
Brian O'Rourke,
Belfast, UK
A. Hirtl, SMI, Vienna, Austria
Link persons accelerator HESR B. Gålnander,
TSL, Uppsala, Sweden HESR D. Prasuhn, COSY,
FZ-Jülich, Germany HESR A. Lehrach, COSY,
FZ-Jülich, Germany
15proposed distribution of EC funds for personnel
of FAIR JCT Application (7M) ?Contract
(4,9M) ? Reduction of EC funded person months
(in some cases not performed in order not to
endanger people coming to FAIR) Ministries /
Funding agencies do not receive EC funds
16FAIR Joint Core Team
22 FTE GSI, 2 FTE FZJ 15 FTE international JCT
members over 18 months
17Status of negotiations / international
contributions
- Germany will pay 75 of the construction cost of
1187M, if the - missing 25 (300M) are contributed by the
international partners. - At least 25 international contributions are
requirred. - If less than 25 international contributions are
confirmed - by October 17, 2007, a start scenario with a
smaller scope/costs - needs to be defined.
- Only the financed part of the FAIR project can be
launched - on November 7, 2007.
18Status of negotiations / international
contributions
India 3 (36M) confirmed by declaration Romania
1 (12M) confirmed by declaration Poland 2,5
(30M) confirmed by declaration Finland 5M plus
potential additional contribution in cooperation
with industry of Finland
announced United Kingdom 15M for NUSTAR and
PANDA plus potential
for 15M in addition (total 30M)
for the next 4 years possible?
decision end of 2007 Sweden 1 (12M) possible
?decision end of October Russia at least 5
(60M) announced by Kirienko (ROSATOM) ?
potential for significant bigger contribution
sign declaration at meeting Putin Merkel,
October 15 in Wiesbaden Italy 40M for SIS300
sc dipol magnets and 4M for PANDA magnet
announced Austria 0,5M per year
announced Spain negotiation on September 28 at
Madrid 2? China 1 ?, Greece ?, France no
shareholder ?
250 M until October 17, 2007 ?
19Project Staging
- Old idea Staging of the project
- ( three stages defined by optimizing start of
science) - New idea Staging ods the project
- ( two phases defined/matched with assured funding
level ) - Phase A start-version
- ( stage defined/matched with funding level by
October 2007) - Phase B all thats left out in Phase A
- (AB full project as defined in FAIR BTR -Annex
of Convention)
20Master Schedule - Civil Construction
STI Start scenario should contain all buildings
and facilities!
Start of Civil Construction is the critical
path! However, local authorities are prepared
for speeding up the process of construction
approval. Aim All permits available before end
of 2008 within legal procedures Focus ground
breaking in early 2009
21Start scenario
STI Do not exclude any science community from
FAIR Baseline Technical Report !
SIS 100/300
SIS 18
UNILAC
ISC Resolution The ISC asks the Joint Core Team
to work out scenarios for the start of FAIR
based on the announced international
contributions. The ISC expects the STI working
group to evaluate these start scenarios and to
report its conclusions at the next ISC meeting
(on October 17, 2007).
Radioactive Ion Production Target
Super FRS
HESR
Anti-Proton Production Target
Generation of RIBs - NUSTAR
CR
Generation of p-bar - PANDA
FLAIR
Generation HE HI - CBM
RESR
100 m
NESR
Applied- and atomic physics - APPA
22FAIR Kick-Off eventNovember 7-8, 2007 at GSI
- What's so important about that meeting?
- Up to now
- Only preparatory phase of FAIR
- RD
- Prototypes
- After Kick-Off
- Official start of construction
- Money starts to flow
- Organizational structures will evolve into FAIR
GmbH
23- Registration will open this week
- You will be informed
- FAIR Newsletter
- FAIR Newsletter Mailing List
- GSI Kurier Mail
- Web
24Agenda Kick-Off (I)
Wednesday 07.11.07 1100 Start of
registration 1430 1515 Coffee 1500 1545
Enter ESR (All seated by 1545) 1600
1710 Kick-Off Event Welcome H. Stöcker (5
Min) Welcome Addresses A. Schavan (BMBF) (10
Min) R. Koch (MinPres Hessen) (10 Min) 2 - 4
international speakers (total 20 Min) EU(?),
FAIR countries(?) Signature of Communiqué (10
Min) Action Element (Press Photos) 1710
1730 Press-Conference (Press and VIP) close to
ESR from 1800 Buffet with Music
25Agenda Kick-Off (II)
Thursday, 08.11.07 0900 1230 Scientific
Symposium 1230 1400 Lunch (Foyer) 1400
1700 Scientific Symposium Current wishlist of
speakers.... Wilczek, Schatz, Hayano, Henning and
more...
26FAIR Roadmap (I)
- Between 7.11., 'till end of the year 2007(not
necessarily prior to Nov. 7th, but desirable) - Nomination of Shareholders by all Contracting
Parties - Formation of Consortia, where applicable (e.g.
A, FIN) - Final Approval (slightly modified) of
Convention, Articles of Association and other
Annexes to Convention, Final Act (ISC, after
one more look by AFI) - Decision on language
- Further declarations / commitments
- Formation of Pre-Council by those who have made
Commitments / sent declarations.
27FAIR Roadmap (II)
- From November 'till January 2008
- Preparation of FAIR Company structure (Joint
Core Team ? Pre-Council) - Establishment of Search Committees for the
FAIR Managing Directors (ISC or Pre-Council) - Staffing of some required positions as soon as
possible for the Joint Core Team (JCT)
28FAIR Roadmap (II)
- April 2008
- Signature of Convention and Final Act by all
Contracting Parties - Signature of Articles of Association by the
Shareholders - Registration of the Company in the Trade
Register - May 2008
- Constitutive meeting of the Council
29Thank you for you attention!