Title: Fundamentals of Project Management
1Fundamentals of Project Management
- Dr. George F. Jergeas
- Project Management Specialization
- University of Calgary
2Schedule
- Day 1
- Game
- Introduction
- PMI stuff
- Step 1 - Define phase
- Step 2 - Plan phase
- Sequence activities
- Time estimate
- Day 2
- Cost estimate
- Step 3 - Organize phase
- Select team and PM
- Step 4 - Control phase
- Step 5 - Close out phase
35 Step Project Management PLANNING
IMPLEMENTATION
CONTROL
ORGANIZE
DEFINE
PLAN
CLOSE
Identify project activities
Determine Personnel Needs
Define Management Style
Obtain Client Acceptance Install
Deliverables Document the Project Issue Final
Report Conduct Post- Implementation Audit
State the Problem
Identify Project Goals
Estimate time and cost
Recruit Project Manger
Establish Control Tools
Recruit Project Team
Prepare Status Reports Review
Project Schedule Issue Change Orders
Sequence Project Activities
List the Objectives
Determine Preliminary Resources
Identify Critical Activities
Organize Project Team
Write Project Proposal
Identify Assumptions and Risks
Assign Work Packages
Project overview WBS
Recruit Criteria Variance
Reports Final Report
Project network
Define Work packages Status Reports
Audit Reports
Critical Path Assign Work
Packages Staff Allocation Reports
4Step 2 Plan the project Basics of Cost
Estimating
5Agenda
- Introduction
- What is an estimate
- Estimating process
- What constitutes a good estimate
- Basic types of cost estimates
- Order of Magnitudes
- Definitive Estimates
6Introduction
- Cost estimates
- Key to successfully conceived, managed and
completed projects - Not limited to construction
- An approximation procedure
- Mistakes can be very costly!
7What is a Cost Estimate?
- AACE Definition
- A compilation of all the costs of the elements
of a project or effort included within an agreed
upon scope - To the contractor
- To forecast cost required to complete a project
in accordance with the contract, plans and
specifications - To the owner cost includes
- Administering the contract
- Contractor's charges, consultants and suppliers
fees - Price of land, financing and operating costs
8What Constitutes a Good Estimate?
- A clear, sound basis
- An agreed upon realistic execution plan
- A sound plan for estimating development
- Good estimating methods and data base
- Well documented basis of estimate
- Good experienced estimator
9Order - of - Magnitude Estimates
- A quick method of determining an approximate
probable cost of a project due to the following
specific situations - Time constraints
- High cost of a detailed estimate
10Order - of - Magnitude Estimates
- Prepared without detailed engineering data
- Square feet of floor area
- Cubic feet of volume
- Plant capacity for input and output
- Km of road surface type
- Use In feasibility studies of a project and
screening several types of alternatives or
proposals - Accuracy /- 30
11Definitive Estimates
- Prepared from very defined engineering data
- Requires as a minimum
- Plans and elevations
- Piping and instrument diagrams
- Single line electrical diagrams
- Equipment data sheets and quotations
- Architectural and structural details
- Soil data and sketches of major foundations
- A complete set of specifications
- Accuracy /- 5
12Components of a Cost Estimate
- Direct Cost
- Labor actual amount paid to field personnel
- Materials essential to constructing and
operating a facility including equipment
installed permanently - Equipment used to perform a contract
- Subcontracts
13Components of a Cost Estimate
- Indirect Costs
- Overhead
- Home office overhead
- Job site overhead (general conditions)
- Taxes
- Risks
- Contingency
- Profit
- Escalation
14Site Overhead (General Conditions)
- Cost of items that cannot be charged to a
specific element of work - Supervision
- Temporary facilities
- Office trailers
- Toilets
- Utilities
- Permits
- Photographs
- Clean-up
15Profit
- Is the amount of money included by the contractor
in its price as compensation for risk, effort and
endeavor in undertaking a project. - It is the money left after a contractor has met
all costs (both indirect and direct). - Profit amount included is very subjective and
depends on - Size of project
- Extent of risk involved
- Need for work
- Extent of competition
16Contingency
- An amount added to cover any additional costs
that may occur during construction. - To determine the amount of contingencies
desirable, an estimator should rely on - Personal judgment, or
- Through statistical analysis of past project costs
17Estimated Conference Planning Budget
CONFERENCE PLANNING 243,325
Site 170,425
Program 41,100
Marketing 31,800
Theme 600
Materials 13,300
Speakers 27,200
Date 1,000
Location 169,425
Lists 2,000
Brochure 29,800
Registration
3 conf calls with pgm comm
Travel/expenses for 16 speakers _at_ 500 per speaker
3 site visits _at_ 800/visit food _at_50 per
person/day for 3 days for 1100 meeting rooms _at_
225/day/room for 3 days for 3 rooms
Deposit
25,000 labels _at_ 80/1000
Obtain Speaker Materials 800
Prepare Conference Notebook 12,500
Design Brochure 12,800
Mail Brochure 17,000
Layout 16 pages _at_ 50/page Printing 30,000
copies _at_ 0.40/copy
25,000 pieces _at_ 0.68/piece
1100 binders _at_ 5/binder photocopy materials
350,000 pages _at_ 0.02/page
Edit/format _at_ 50/speaker
18PM ANNUAL CONFERENCE REVENUE EXPENSE BUDGET
- Revenues
- Registrations - 1100 _at_ 335
..368,500 - Expenses
- Salary
- Graphic artist
...800 - Total Salary..
800 - Non-Salary
- Travel...2
1,600 - Printing.1
9,000 - Postage...1
7,000 - Mailing Lists
.2,000 - Telephone.
600 - Supplies.6
,300 - Speaker Honoraria
.8,000 - Site Deposit
..1,000 - Food165,0
00 - Meeting Room Rental
..2,025 - Total Non-Salary..2
42,525 - Total Expenses24
3,325
19Estimating Issues
- Underestimating
- Dont be overly optimistic about time and costs
- Cause problems in the long run and produce
unsatisfactory product - Overestimating
- Danger that project will not get approval
- Over compensating for unexpected delays/problems
20Estimating Issues
- Use your WBS Define the lowest level of
activities to estimate the time and dollars
required - Check activities costs on previous projects
- Take into account circumstances during
implementation, weather, transportation costs,
availability of materials and labour etc.
21Summary
- There are different types of estimates
- Each type used for specific purpose but no
substitute of definitive estimates - An estimate information data base is essential
- Good estimates come from looking at the details
22Important Points
- Order-of magnitude estimating important to owner
- Owner examines the estimate before continuing
with further development of project. - Liability issue based on the information
contained in your estimate, major decisions are
often made by the owner - This places a responsibility and liability on you
as an estimator
23Important Points
- Acquaint yourself with terminology, elements of
cost which include labor, equipment and material
costs - Develop habits of thoroughly reviewing contract
documents - Remember to document and maintain the data base
24Step 2 - Plan the Project Writing a Project
Proposal
25Agenda
- Writing a proposal
- The purpose
- Format
- Executive summary
- Background
- Project manager
- Activity
- Schedule
- Budget/project cost
265 Phase Project Management PLANNING
IMPLEMENTATION
CONTROL
DEFINE
ORGANIZE
PLAN
CLOSE
Identify project activities
Determine Personnel Needs
Obtain Client Acceptance Install
Deliverables Document the Project Issue
Final Report Conduct Post- Implementation Audit
Define Management Style
State the Problem
Identify Project Goals
Estimate time and cost
Recruit Project Manger
Establish Control Tools
Recruit Project Team
Prepare Status Reports Review
Project Schedule Issue Change Orders
Sequence Project Activities
List the Objectives
Identify Critical activities
Determine Preliminary Resources
Organise Project Team
Write Project Proposal
Identify Assumptions and Risks
Assign Work Packages
27Writing a Project Proposal
- Represents the transition from the planning
(define, plan) to implementation (organising,
control, close) - Used as an information source to decide whether
the project should proceed to the implementation
phase - Different terminology used
- DBM, Brief, Scope Definition Statement
28Purpose
- The project proposal provides
- A statement of the need, the approach being taken
and the expected benefits - Description of project activities, timelines and
resources required - Documentation for project control
- Briefing document for new team members and others
in the organisation
29Purpose
- Tool for decision making, managing, controlling,
training and reporting - Written for
- Senior management
- Project team
- Other managers who are indirectly involved
- Consultants
30- The remainder of this section should be reviewed
by attendees. - Please go to slide 43
31Format
- Executive summary
- States the fundamental nature of proposal and
benefits that are expected - Should deal with
- Nature and approach to technical problem
- Plan for implementation of project if approved
- Plan for logistic support and administration
- Description of team that will complete the work
and their experiences on other projects
32Technical Approach
- General description of the problem to be
undertaken - Organisational approach
- Provides sufficient detail for the reader to
understand what is intended - Method for resolving critical problems outlined
33Technical Approach
- Proposal to meet clients requirements identified
- Procedures for testing and inspections to assure
performance, quality, reliability and compliance
34Implementation Plan
- Contains estimate of time, cost and materials to
be used - Lists sub-systems of project in cost estimate
- Estimates of personnel, equipment and resources
are provided by period - Major milestones are indicated
35Logistics Plan
- Description of how skills, facilities, equipment
will be supplied - Administration strategy
- Nature and timing of reports
- budget, progress, evaluations and audits
- Handling and costing of change orders
36Past Experiences
- How the proposed team has performed?
- Who the key personnel are and their
qualifications? - Keep in mind - the purpose of the proposal is to
convince the funder that the project should be
supported
37Format Example
- Proposal components
- Project name
- Project manager responsible
- Activities
- Schedule
- Budget
38Format
- Project Name
- Label to identify the project
- Should reflect uniqueness of the project
- Project Manager
- Person responsible for project
- Must be able to manage budgets, schedules, team
and meet specifications
39Format
- Activity
- Identified by number, description and name
- Method for team to refer to an activity
- Should be short, but reflect task to be
undertaken - Description states in precise terms the work to
be done
40Format
- Schedule
- Based on the analysis of the network
- Provides anticipated start and finish dates.
- Dates may change
41Format
- Budget
- Information provided at an aggregated level
- Details attached if requested by senior
management - Includes
- Labour cost estimates
- Financing costs
- Materials and equipment costs (See Figures )
42Project Definition Report
43Any Questions?
44Step 3 Organize the ProjectImplement the
Project and Organize the Team
45Agenda
- Organize the team
- Determine the personnel requirement and skills
- Select the Project Manager
- Select the Project Team
- Characteristics of PM and team
- What makes teams work
465 Step Project ManagementPLANNING
IMPLEMENTATION
Obtain Client Acceptance Install
Deliverables Document the Project Issue
Final Report Conduct Post- Implementation Audit
CONTROL
CLOSE
DEFINE
ORGANIZE
PLAN
CLOSE
Identify project activities
Determine Personnel Needs
Define Management Style
Obtain Client Acceptance Install
Deliverables Document the Project Issue
Final Report Conduct Post- Implementation Audit
State the Problem
Identify Project Goals
Estimate time and cost
Recruit Project Manger
Establish Control Tools
Recruit Project Team
Prepare Status Reports Review
Project Schedule Issue Change Orders
Sequence Project Activities
List the Objectives
Identify Critical activities
Determine Preliminary Resources
Organise Project Team
Write Project Proposal
Identify Assumptions and Risks
Assign Work Packages
47Implementation Phase
- Start once the project has been approved
- Project team for the implementation is
formed/procured - In-house and external
- Procurement procedures
- Work package assignments can commence
- Deliverables are agreed upon and clearly
understood - Control systems are established
- Time, Quality, Cost, Safety .
48Organising the Project Team
- Projects are only as successful as the project
manager and team who implements them - Building an effective team takes a lot of work
- Must consider more than just a persons technical
skills
49Organising the Project Team
- The selection of team members is based on skills,
availability and personality - There needs to be a commitment and chemistry
among the team members - Team building is not a perfect art, there is
always the risk of conflict
50Organising the Project Team
- Organized and located to facilitates open
continuous communication - This does not mean they have to be physically
located together - Team members may be reallocated for the duration
of the project or remain in their function areas
51Organising the Project Team
- Large projects
- Dedicated core team
- Structured
- More defined roles
- Need for open and continuous communication lines
- Self contained
52Organising the Project Team
- Small projects
- Part-time commitment from team members
- Team members remain in their functional units
- Conflicting priorities/demands exist
- Conflicts may arise from having more than one
boss or more than one team involvement
53Organising the Project Team
- Be sure all parties understand the need to
- Build the team,
- What the priorities are within in the
organisation and - Their assistance is appreciated
- Project manager to ensure that the cross
functional relationships are maintained and
supported
54Characteristics of an Effective Project Manager
- Understands purpose of the project
- Has the necessary background and experience
- Effective leader with proven managerial ability
55Characteristics of an Effective Project Manager
- Has credibility with team and client
- Sensitive to project and corporate politics
- Excellent communication skills
- Consistent behaviour
- Facilitator rather than a dictator
56Selection of Project Manager
- Key position on the project
- Selection of appropriate individual is essential
to success of the project - Selection criteria should be established based on
the skills required to carry out project
57Project Manager Selection Criteria
- 1. Background and Experience
- Should be consistent with the nature and needs of
the project - Education should be compatible with nature and
expectations of the project - Look for a individual with a mix of conceptual,
analytical, operational and practical experience
58Project Manager Selection Criteria
- 2. Leadership
- Ability to design, co-ordinate, control and
implement project plan - Stay the course until completion
- Ability to see the big picture and understand the
details
59Project Manager Selection Criteria
- 3. Technical expertise
- Ability to direct, evaluate, and make decisions
on technical alternatives - Does not and cant be an expert in all areas of
the project - Should have expertise in project management, team
management and training
60Project Manager Selection Criteria
- 4. Interpersonal skills
- Should be able to
- Motivate, inspire, and coach
- Actively listen, give and receive feedback
- Empathise, relate feelings, needs and concerns in
a positive manner - Prevent and resolve conflicts, negotiate
- Keep team, senior management and stakeholders
informed through effective communication channels
61Project Manager Selection Criteria
- 5. Proven Managerial Ability
- Good track record, excellent indicator of the
future - Knowledge of the organisation and its operation
- Ability to effectively interface with all levels
of the organisation - Ability to link project goals to corporate
mission and goals
62Selecting the Team
- Selection of team members depends on a number of
factors - Nature of the technical work to be done
- Level and type of expertise required at each
phase of the project - Availability of staff in the organisation and
reporting relationships
63Team Selection Criteria
- Similar to those of the project manager
- More emphasis on the technical skills
- Interpersonal skills essential
- Ability to function as a team member with shared
goals and objectives (us instead of me)
64Effective Team Characteristics
- Commitment to the project goals and completion
- Ability to communicate, share responsibility and
power - Flexible willing to change or try some new
methods - Technically competent
- Willing to
- Admit mistakes
- Admit not have all the answers
- Accept feedback
65Effective Team Characteristics
- Politically astute
- Team players
- Creative and open to suggestions
- High self esteem, can do attitude
- Willing to work for more than one boss, across
formal structure and authority system - Results oriented
66What Makes Teams Work
- Successful Projects
- The team has fun
- Have the support of senior management
- Everyone understands the reason for the project
- Conflicts are addressed and dealt with
- The entire organisation is committed
67What Makes Teams Work
- Successful projects
- Team understands the organisations mission and
how the project fits within that mission - Team understands what is to be achieved and when
it is achieved - Trust and communication
68Step 4 - Control the Project
695 Step Project ManagementPLANNING
IMPLEMENTATION
Obtain Client Acceptance Install
Deliverables Document the Project Issue
Final Report Conduct Post- Implementation Audit
CONTROL
CLOSE
DEFINE
ORGANIZE
PLAN
CLOSE
Identify project activities
Determine Personnel Needs
Define Management Style
Obtain Client Acceptance Install
Deliverables Document the Project Issue
Final Report Conduct Post- Implementation Audit
State the Problem
Identify Project Goals
Estimate time and cost
Recruit Project Manger
Establish Control Tools
Recruit Project Team
Prepare Status Reports Review
Project Schedule Issue Change Orders
Sequence Project Activities
List the Objectives
Identify Critical activities
Determine Preliminary Resources
Organise Project Team
Write Project Proposal
Identify Assumptions and Risks
Assign Work Packages
70Project Control
- Schedule control
- Cost control
- Team performance evaluation
- Change control
71Schedule Control
72Incorporating Project Changes into the Schedule
- When a change is requested or needed, you should
- Estimate the impact on the schedule by
incorporating any additional tasks and revised
duration estimates - Add activities that were overlooked when the
original plan was developed - Add new activities due to unanticipated events
- Obtain client approval before proceeding
- A new baseline plan is established and used as
the benchmark for comparison
73Approaches to Schedule Control
- Schedule control involves four steps
- Analyse the schedule to determine which areas may
need corrective action - Decide what specific corrective actions should be
taken - Revisit the plan to incorporate the chosen
corrective actions - Recalculate the schedule to evaluate the effects
of the planned corrective actions
74Approaches to Schedule Control
- If the planned corrective actions do not result
in an acceptable schedule, repeat the previous
steps
75Approaches to Schedule Control
- Each time a schedule is recalculated
- Identify the critical path
- Identify any activities that have a negative
slack - Compare paths where slippage have occurred (Slack
got worse) with the previously calculated
schedule - Apply acceleration to the paths with negative
slack - The most negative slack should be given top
priority - Focus on activities that are in progress or to be
started in the immediate future - Focus on activities that have long duration
estimates
76Acceleration
- To reduce schedule
- Apply more resources to speed up an activity
- Add more people
- Increase hours per day or increase days per week
- Assign person(s) with greater expertise or more
experience - Reduce the scope or eliminate the activity if
possible - Increase productivity through improved methods or
technology
77Acceleration
- Trade-off in the form of an increase in costs or
a reduction in scope - This could jeopardise elements of the overall
project objective scope, budget, schedule,
and/or quality - There may be a dispute over who should absorb any
increased cost to accelerate - Bonus provision if project is completed early
- Liquidated damages
- Project meetings are a good forum for addressing
schedule control issues
78Evaluation of Delays in the Work
- Questions to determine that a delay in the work
is compensable - Was the cause of the delay beyond the
contractors control? - Did the contractor fail to take normal
precautions? - Was the contractor ready and able to work?
79Evaluation of Delays in the Work
- Did the contractor submit a detailed schedule
projecting project completion within the allotted
time? Was the schedule updated regularly? Did
the updated schedule justify time extension? - Did this schedule contain a critical path
analysis or equivalent? - Has the contractor maintained sufficient forces
in those operations along the critical path where
needed to meet target dates?
80Evaluation of Delays in the Work
- How have causes, other than normal weather,
beyond the control and without the fault or
negligence of the contractor affected target
dates along the critical path? - Has the contractor proven unusually severe
weather with such information as climatological
data, return probability of severe storms, or
flood depth data?
81Evaluation of Delays in the Work
- Did the weather phenomenon actually delay
operations along the critical path or in
secondary operations? - Was the contractor shut down for other reasons?
82Cost Control
83Cost Control System
- Any cost control system should enable a project
manager to observe current perfomance
(productivity) levels, compare them with budget
levels and institute corrective actions to keep
productivity, and ultimately costs, within
acceptable range
84Elements of Effective Cost Control System
- Observation
- Comparison of observation with budget
- Corrective action to take if necessary
- Can also serve as
- A basis for a productivity improvement program
- A measure of productivity loss caused by adverse
factors and changed conditions such as winter
work, acceleration, design changes, etc.
85Cost Control System
- Compares actual man-hours expended to earned
hours - Actual work hours come from contractors daily
time sheets - Earned hours are calculated by multiplying the
completed quantities during a period by estimated
man-hours per unit quantity - See figure following as an example
86Labour Productivity Report
87Budget
Money
Time Now
Actual Expenditure
Cost overrun
Earned Value
Time
Delay
88Money
Budget
Ahead of schedule
Earned Value
Making Money
Actual
Time
89Example Activity Variance Report
Fundamentals of Project Management
Tool Kit
90Conclusion
- You can draw immediate attention to significant
deviations from what was planned - Indicate what corrective action is necessary and
by whom -
- Dependent on accurate reporting and correct
allocation of hours expended
91Performance Evaluation
92Joint Evaluation
- Progress meeting
- Forum for identifying a problem
- Specific criteria to evaluate effectiveness
- Teamwork
- Timely problem resolution
- Periodic survey
- Comparisons of survey responses identify areas of
improvement and potential problems
93Measuring Success
- Met target price, quality and schedule
- Goals achieved
- Benchmarking
- Positive client feedback
- Great safety record
- Disputes resolved effectively
94Joint Evaluation
1. Communications between the owner/contractor
personnel are 2. Top management support of
partnering process is 3. Problems,
issues or concerns are 4. Cooperation between
owner and contractor personnel is 5.
Responses to problems, issues, or concerns
frequently become
Difficult, guarded
Easy, open, up front
1 2 3 4 5
Not evident Inconsistent
Obvious, consistent
1 2 3 4 5
Attacked promptly
1 2 3 4 5
Ignored
Cool, removed, detached,
Genuine, unreserved, complete
1 2 3 4 5
Personal issues
Treated as project problems
1 2 3 4 5
95Change ControlChanges and Extra Work
96This Session
- Definition
- Impact costs
- Basic principles in handling change orders
- Types of changes
- Elements of a change order
- Recommendations for good practice
97Change Order
- Is a written agreement to modify, add to, or
otherwise alter the work from that set forth in
the contract documents at the time of opening
bids, provided that such alteration can be
considered to be within the scope of the original
project otherwise, a contract modification may
be required - It is the only legal means available to change
the contract provisions after the award of
contract
98Change Order
- Could be addition to or deletion from the work
- Changes in the method of execution or manner of
work performance - Change in owner-furnished materials or facilities
- Change in the contract time or order of the work
- Correct errors in the plans or specifications
- Direct results of contractor suggestions that are
approved by the owner and its agents
99Change Order
- Changes may involve
- A price change in the contractors favor
- Cash credit to the owner
- No price change at all
- Make sure payment covers
- Impact costs Loss of productivity
- Time extensions
100Basic Principles in Handling Change Orders
- No work should be included beyond the scope of
the base contract - The identity of the individuals authorized to
request and approve change orders should be
established early - During the start up meeting the change order
handling procedures must be established/discussed
101Basic Principles in Handling Change Orders
- All changes in the work must be authorized in
writing prior to the execution - The scope of a change order must be clear
- A request for a change proposal should contain
enough information to enable the contractor to
make a realistic estimate
102Basic Principles in Handling Change Orders
- The contractor should submit its proposal to
execute a change order as soon as possible after
receiving the request - The owners approval or rejection should follow
as soon as possible - The Change Order should be fair. It should
recognize the contractors right to include - Overhead and profit percentages
- Compensation for legitimate time-delay claims
- Compensation for legitimate impact costs if any
103Types of Changes
- Directed changes
- Owner directs the contractor to perform work that
differs from that specified in the contract - Easy to identify and mutually recognized
- Disagreements tend to center on questions of
financial compensation and the effect of change
on the schedule
104Types of Changes
- Constructive Changes
- Is an informal act authorizing or directing a
modification to the contract caused by an act or
failure to act - Defective plans and specifications
- Engineers interpretation
- Higher standard of performance than specified
- Improper inspection and rejection
- Change in method of performance
- Owner nondisclosure
- Impossibility/impracticability of performance
105Types of Changes
- Constructive Changes
- Must be claimed in writing within time specified
in the contract - Major source of disputes
106Change Order Form
- Description of change
- Reason for change
- Change in contract price
- Change to contract time
- Statement that secondary impacts are included
- Approvals by owners and contractors
representatives
107Sample of a Change Order
- PROJECT TITLE
- PROJECT NO. CONTRACT NO. CONTRACT DATE
- CONTRACTOR
- The following changes are hereby made to the
Contract Documents - Construction of access bridge abutment No. 1
drainage system and - Reset two penstock bearing plates. All in
accordance with revised DWG S-17209 - Revision 4, dated August 29, 2000
- JUSTIFICATION
- Unforeseen soil conditions
- CHANGE TO CONTRACT PRICE
- Original Contract Price
- Current contract price, as adjusted by previous
change orders - The Contract Price due to this Change Order will
be (increased) (decreased) by - The new Contract Price due to this Change Order
will be - CHANGE TO CONTRACT TIME
- The Contract Time will be (increased)
(decreased)by calendar days - The date for completion of all work under the
contract will be - Requested by dated
- Recommended by dated
108Recommendation for Good Practice
- Percentages for overhead and profit to be applied
- Determination of the individual representative of
the owner who is authorized to approve change
orders - Procedures to be followed in the submittal of
change order proposals - Change order forms to be used
109Recommendation for Good Practice
- Time extensions required, if any
- The detail required of contractors when
submitting change order proposals - - Will a complete breakdown of all costs be
required? - Brief description - Descriptive drawings
- Overtime necessary due to change orders -
consideration of decreased productivity - Responsibility for record drawings brought about
due to the change orders
110Dealing with Disputes Keys to Project Control
111Agenda
- Causes
- Obstacles to resolution
- Successful settlement
112Causes of Disputes
- Design changes, errors/omissions and extras
- Late owner-supplied equipment
- Lack of co-ordination
- Changed soil/site conditions
- Access to site
113Causes of Disputes
- Delays and acceleration
- Insufficient bid preparation time
- Inadequate bid information
- Underestimation by contractors
- Inadequate management
114Resolving Disputes
- Face to face by parties themselves
- By appointing a mutually acceptable third party
-
- By accepting the jurisdiction of the courts
115Obstacle to Resolution
- Owners bias
- Contractors bias
- Total cost claims
116Successful Settlement
- Get the facts
- Keep good records
- Know your contract
- Preserve your rights
- Show Cause-Effect-Entitlement-Quantification
117Settlement of Disputes
- The following options are available
- Negotiation
- Mediation
- Dispute Resolution Board
- Mini-trial
- Arbitration
- Litigation
118Mediation
- Voluntary
- Non-binding
- Economical
- Assist negotiation
119Arbitration
- Binding
- 1 or 3 arbitrators
- Selection of arbitrators
- Each party selects one arbitrator
- Both select a chairperson
- Could be expensive
120Dispute Resolution Board
- DRB consists of three members and is established
at the beginning of project - Non-binding
121Mini-trial
- Presentation of both sides arguments before an
advisory panel and executives of both sides. May
include a judge -
- Predict the likely outcome and the strength and
weakness of the case - Voluntary and non-binding
122Litigation
- Adversarial
- Costly
- Voltaire I have only been ruined twice in my
life. The first time was when I lost a lawsuit
the second, when I won one!
123Problem Resolution
- Lowest level with time limit
- Escalated to the next level of management
- No action is not an option
124Problem Resolution
125Problem Resolution
- Systematic approach
- Seek solutions
- Increased and higher quality discussion
- Win-win solutions
- Equality of rights among parties
- Agree on no adversarial relations
126Problem Resolution Negotiation
- Separate the people from the problem
- Focus on interests, not positions
- Invent options for mutual gain
- When possible, use objective criteria
127Step 5 Close the Project
128Agenda
- Purpose
- Prerequisite activities
- Project termination process
- Final project report
- Rewarding successes and learning from failures
1295 Phase Project Management PLANNING
IMPLEMENTATION
CONTROL
DEFINE
ORGANIZE
PLAN
CLOSE
Identify project activities
Determine Personnel Needs
Define Management Style
Obtain Client Acceptance Install
Deliverables Document the Project Issue
Final Report Conduct Post- Implementation Audit
State the Problem
Identify Project Goals
Estimate time and cost
Recruit Project Manger
Establish Control Tools
Recruit Project Team
Prepare Status Reports Review
Project Schedule Issue Change Orders
Sequence Project Activities
List the Objectives
Identify Critical activities
Determine Preliminary Resources
Organise Project Team
Write Project Proposal
Identify Assumptions and Risks
Assign Work Packages
Project overview WEBS
Recruit Criteria Variance
Reports Final Report
Project network
Define Work packages Status Reports
Audit Reports
Critical Path Assign Work
Packages Staff Allocation Reports
130Purpose
- To ensure all deliverables are installed or
implemented according to time, budget and
specification
131Purpose
- To ensure that the works have been completed as
specified, and that all facilities work properly - To provide a record of the actual execution,
together with operating instructions - To train staff in the use of the works
132Purpose
- To formally close out contractual relationships
- Obtain sign off on final report to show
contracted deliverables have been successfully
implemented - To formally terminate project team assignments
- To ensure adequate project documentation and
baseline information for changes that may need to
occur in the future - To obtain clients acceptance of project work and
deliverables
133Activities
- Test the engineering performance
- Search for non-operational defects, e. g. those
that affect only the appearance - Inspect the facilities thoroughly and have
defects remedied - Prepare as-built drawings and record
- Start up, test and adjust all services
- Prepare operational instructions and maintenance
manuals - Train staff
- Monitor performance of work against original
requirements
134Deficiency Lists
- These are lists of required repairs or completion
of deficient/incomplete items. - Schedule for completion of deficiencies.
- Need a sign-off procedure.
- Need a handover process to turn project over to
Owner in organized way.
135Records
- During implementation, difficulties may arise
which result in changes to the original design.
Records of these changes will be kept during
implementation, mainly for financial reasons.
These must be brought together to make a complete
record of the actual execution.
136As-built Drawings
- Mandatory on some projects.
- Should be provided on all projects.
- Reflect what was actually built.
- Contract documents must set a date for completion
of as-built drawings. - Make sure they are worked on as the project is
built . . . do not wait for the end of the job.
137Warranties, Spare Parts and Manuals
- Watch for differing warranty starts and
durations. - Recommended parts list.
- Operations and Maintenance Manuals.
- Service and warranty contacts and service
agreements/expectations.
138Termination Process
- Project termination can be complicated
- A systematic approach is required to successfully
cover all bases in terminating contracts and
relationships. - Stay in close contact with the client and
administration to ensure close down meets with
the clients satisfaction.
139Termination Process
- Generally the termination phases include
- 1. Prepare termination logistics
- 2. Document project
- 3. Conduct post implementation audit and
prepare and submit final report - 4. Obtain client approval
- 5. Close operation
140Prepare Termination Logistics
PROJECT TERMINATION PHASES
Close Operation
Document The Project
Project Termination Phases
Obtain Client Approval
Conduct Post- Implementation Audit Prepare and
Submit Final Report
1411. Prepare termination logistics
- Establish project termination design
- Assign a termination manager
- Assign a termination team to assist manager
- Conduct a termination meeting to review process
- Assign close-out tasks
1422. Document the Project
- Prepare personnel termination reports
- Close down project office and reporting system
- Terminate all financial documents
- Complete all payments and expenses
- Collect all debts prepare the financial project
close out report
1432. Document the Project
- Terminate all work orders, contracts, assignments
and outstanding supplier and customer
obligations. - Document completion and compliance with all
vendors and contractors. - Close all project sites and return all project
equipment.
1443. Conduct Post -Implementation Audit
- Complete Final Report
- Submit report to client
- Evaluation of projects goals and activity
achievement. - Measured against the project plan, budget, time
deadlines, quality of deliverables,
specifications and client satisfaction.
145Final Report
- Should answers the following questions
- Was the project goal achieved?
- Was the project work done on time?
- Was it done within budget?
- Was it done by specifications?
- Was the client satisfied with the project
results? - Memory or history of the project.
- File others can refer to, study progress and
impediments of the project. - Can follow many formats.
146Final Report
- Usually includes the following elements
- Overall success and performance of the project
- Organisation and administration of the project
- Techniques used to accomplish project results
- Assessment of project strengths and weaknesses
- Recommendation of project manager and team for
continuation or extinction of project
1474. Client Approval
- Obtain Client approval.
- 5. Close Operation
- Close all physical sites and terminate remaining
project staff.
148Rewarding Successes and Learning From Failures
- Closing a project is a celebration of effort.
- Brings resolution to the process.
- Project manager should bring the team together to
review their journey. - Way of closing formal and informal relationships.
- Way to re-enforce learning that occurred.
- Final get together brings project full circle.
149Summary
- All projects must be closed off.
- Project should meet with client acceptance.
- Provide installed deliverables.
- Document the process and achievements.
- Provide closure for the team and client.
150Critical Factors in Successful Project
Implementation
- Mission
- Senior Management
- Schedule
- Client Consultation
- Personnel
- Pinto, J. K. and D. P. Slevin (1987). IEEE
Transactions on Engineering Management EM34(1)
22-28.
- Technical Tasks
- Client Acceptance
- Monitoring Feedback
- Communication
- Troubleshooting
151Project Management Education / Training
- Online resources (websites and list servers)
- Each other (sharing knowledge and experiences)
- Balance experience with education
- Project Management Institute PMBOK Guide,
http//www.pmi.org
152Additional Online Resources in Project Management
- http//www.gantthead.com
- http//www.allpm.com
- http//www.4pm.com
- http//www.ipma.ch
- http//appl.nasa.gov/pmdp/handbook/guide.htm
- http//www.pmforum.org
- http//www.projectconnections.com
- http//www.tenstep.com
- http//listserv.uts.edu.au/mailman/listinfo/pmnet
- http//www.spottydog.u-net.com/
153Concluding Remarks
- Projects - an increasingly important way of
working - Project management is challenging, rewarding
- Keep it simple, use aspects of project management
that make sense - Dont be an Accidental Project Manager
- Its OK to make mistakeslearn from them to
improve project management practices
154Thats all and thank you
- Good luck in managing your projects
155Sample Templates and Forms
1565-Step Project Management PLANNING
IMPLEMENTATION
CONTROL
DEFINE
ORGANIZE
PLAN
CLOSE
Identify project activities
Determine Personnel Needs
Define Management Style
Obtain Client Acceptance Install
Deliverables Document the Project Issue
Final Report Conduct Post- Implementation Audit
State the Problem
Identify Project Goals
Estimate time and cost
Recruit Project Manger
Establish Control Tools
Recruit Project Team
Prepare Status Reports Review
Project Schedule Issue Change Orders
Sequence Project Activities
List the Objectives
Identify Critical activities
Determine Preliminary Resources
Organize Project Team
Identify Assumptions and Risks
Write Project Proposal
Assign Work Packages
Project overview WBS
Recruit Criteria Variance
Reports Final Report
Project network Define
Work packages Status Reports
Audit Reports
Critical Path Assign Work
Packages Staff Allocation Reports
157Project Overview - Sample
Sample
158Project Overview
Project Name Project Manager
Problem/Opportunity
Goal
Objectives
Success Criteria
Stakeholders
Risks and Assumptions
Prepared by Date Approved
by Date
Fundamentals of Project Management
Tool Kit
159Stakeholder and External Issues Analysis
STAKEHOLDER and External Issues
Their Objective/Purpose
Their Strategy
Their Potential Impact on the project
How They Operate
Where they gain Support
How to Manage them and your plan for mitigation
Fundamentals of Project Management
Tool Kit
160Risk Management Template
161WBS - Sample
CONFERENCE PLANNING
SITE
MARKETING
PROGRAM
DATE
PLACE
THEME
MATERIALS
SPEAKERS
LISTS
BROCHURE
REGISTER
OBTAIN MATERIALS
PREPARE KITS
DESIGN BROCHURE
MAIL BROCHURE
Sample
162 Estimated Project Planning Budget
Cost __________
Description __________
Cost __________
Description __________
Cost __________
Description __________
Cost __________
Description __________
Cost __________
Description __________
Fundamentals of Project Management
Tool Kit
163Estimated Conference Planning Budget
CONFERENCE PLANNING 243,325
Site 170,425
Program 41,100
Marketing 31,800
Theme 600
Materials 13,300
Speakers 27,200
Date 1,000
Location 169,425
Lists 2,000
Brochure 29,800
Registration
3 conf calls with pgm comm
Travel/expenses for 16 speakers _at_ 500 per speaker
3 site visits _at_ 800/visit food _at_50 per
person/day for 3 days for 1100 meeting rooms _at_
225/day/room for 3 days for 3 rooms
Deposit
25,000 labels _at_ 80/1000
Obtain Speaker Materials 800
Prepare Conference Notebook 125,500
Design Brochure 12,800
Mail Brochure 17,000
Layout 16 pages _at_ 50/page Printing 30,000
copies _at_ 0.40/copy
25,000 pieces _at_ 0.68/piece
1100 binders _at_ 5/binder photocopy materials
350,000 pages _at_ 0.02/page
Edit/format _at_ 50/speaker
164Project Schedule - Sample
Project ____________________
Project Manager ____________________
Date _____________
Sample
165Project Schedule
Project ____________________
Project Manager ____________________
Date _____________
Fundamentals of Project Management
Tool Kit
166RACI Charts (F.T Hartman)
2.4.5 Major Element Amelia
Drover Fred 2-5
Deliverable_____________________
Manager___________________ Project_________
DATES
A C G C F M J W B D M H F W L
S W E
Budget Actual Budget Actual W/Hrs.
W/Hrs. Cost Cost
ACTION
Activity Another activity Build something
R A A C I I - I C 120
400 - R C I A A I
A - 50
50 R - A C I I - C -
345 1,500 - R C I A
A I A - 127
- R A A C I I - I C
90 9,000 R - A C I
I - C - 55
1,700
Another Item Yet another Design a bit
Design more Sneeze Gesundheit
- A R I C C A I I 455
875 R C A A I C I
- - 200
7,785 - R I I C - - - -
65 -
Another thing Wait for item More stuff Finish
A C R - C I C - - 20
100,000 - I C A A R
I A I 655
- R A - I C I A A A 80
- A I C I I A A
A R 12 100
167RACI Charts
168RACI Chart
169PM ANNUAL CONFERENCE REVENUE EXPENSE BUDGET
- Revenues
- Registrations - 1100 _at_ 335
..368,500 - Expenses
- Salary
- Graphic artist
...800 - Total Salary..
800 - Non-Salary
- Travel...2
1,600 - Printing.1
9,000 - Postage...1
7,000 - Mailing Lists
.2,000 - Telephone.
600 - Supplies.6
,300 - Speaker Honoraria
.8,000 - Site Deposit
..1,000 - Food165,0
00 - Meeting Room Rental
..2,025 - Total Non-Salary..2
42,525 - Total Expenses24
3,325
170Project Definition Report
171Sample of a Change Order
- PROJECT TITLE
- PROJECT NO. CONTRACT NO. CONTRACT DATE
- CONTRACTOR
- The following changes are hereby made to the
Contract Documents - Construction of access bridge abutment No. 1
drainage system and - Reset two penstock bearing plates. All in
accordance with revised DWG S-17209 - Revision 4, dated