Title: Monthly Status Report Template V0.2
1SMS-TO3 January 30, 2004 Project Review
Presented to NDOT Safety Engineering by IMGS Dav
id Doerter Friday, February 6, 2004
SMS Monthly Status Report Version 0.5 January 30,
2004
2Revisions
3Contents
- Project Overview
- Status Overview
- Current Stage
- Project Indicators
- Critical Issues
- Cost Status
- Technical and Schedule Status
- Issues and Concerns
- Risks
- Document List
- Summary and Discussion
4Project Overview
5Project Overview
6Project Overview Description
- Project Description
- SMS is a multi-phased project to develop a
Statewide Roadway Safety Management System to
compile and analyze statewide crash data,
inventory high crash locations, analyze crash
causation, model solutions, evaluate, and program
overall roadway safety at NDOT. - Business Problem Solved
- Plan, design, construct, and implement a computer
system to replace outdated existing legacy
system.
7Project Overview -Organization
8Status Overview
9Status Overview
1
2
NA
10Status OverviewInc. Oversight Task
- Tasks 4 LRS Migration, 5 Event Migration, 8
Maintenance Report, 11 HAL Prototype - Task Description
- Issue Tasks are behind schedule and will run
past the contract end date of January 31, 2004. - Impact
- Recommended Action Continue work until
complete. - New Direction None. Estimate that project is
within weeks of completion.
11Status OverviewCritical Task
- Tasks All tasks except Kick-off, JumpStart
Support, and CrossRoads Coordination. - Task Description
- Issue Costs for tasks exceed budgeted estimates
due to unanticipated difficulty with data
migration effort and underestimation of effort to
perform tasks. - Impact IMGS project financial difficulty.
Underestimation of effort also negatively impacts
schedule. No cost impact to NDOT. - Recommended Action Continue to perform work
necessary for a successful project. - New Direction None. Estimate that project is
within weeks of completion.
12Cost Status
13Cost Status Overview
- SMS Task Order 3 (5) - (awarded 01/01/03, PoP
thru 10/31/03, extended to 1/31/04) - Total Funding Available 305,050
- Less Expended (as of 10/31/03) 299,616
- Funding Remaining 5,434
-
- Monthly Burn Rate Estimated at 23.5K (Travel
Estimate Labor Estimate) - Remaining Funding Estimate (through 1/31/04)
- 0.23 months of funding remain to cover 0
remaining project months (Funding Remaining /
Burn Rate) - Travel Estimate - 5,399
- Labor Estimate - 35
14Invoice Status
- Invoice Status
- Total Invoiced thru 11/28/03 244,688.75
- Invoice MPJ0003445 (pd.) 15,852.70
- Invoice MPJ0003587 (pd.) 18,515.00
- Invoice MPJ0003877 (pd.) 18,697.50
- Invoice MPJ0003994 (pd.) 16,692.50
- Invoice MPJ0004164 (pd.) 13,446.56
- Invoice MPJ0004438 (pd.) 76,702.50
- Invoice MPJ0004738 84,781.99
- Total Paid 159,906.76
- Net Outstanding 84,781.99
15Budget / ActualComparison by TASK
Note Travel and expenses are not current and
will be updated after IMGS updates invoicing.
Believe travel is actually 100 used..
16Cost Status Summary
(Cumulative)
17Technical and Schedule Status
18Schedule Status By Task
1Q03
4Q03
1Q04
2Q04
3Q03
2Q03
TASK
Kick-off
1/03
3/03
Req Update
2/04
ATP
12/03
LRS Data
2/04
Event Data
2/04
Training
8/03
Support
4/04
Maint Req
2/04
Coordinate
11/03
Project Mgt
2/04
HAL P-Type
2/04
Baseline Original Plan LRE Latest Revised
Estimate
19Schedule Status - Deliverables
20Schedule Status Deliverables (cont.)
21Issues and Concerns
22Issues and Concerns
- Concern See critical tasks.
- Cause
- Impact
- Corrective Action / Recommendation
- Get Well Date
23Risks
24Risks
25Risks