Title: Renewable Energy Regulations: Issues and India’s Reponse
1Renewable Energy RegulationsIssues and Indias
Reponse
Rajkiran V Bilolikar
2Agenda
- Renewable Energy Scenario
- Policy Base for RE promotion
- RE regulations support
- RE regulations Issues
- Pricing Options
3Technical Potential of Renewable Energy
- Technical Potential of Renewable Energy in MW
4Technical Potential of Renewable Energy
- Indias installed capacity of Renewable power in
MW (31.03.2008)
5Technical Potential of Renewable Energy
- State wise Gross Potential and Installed Capacity
in MW - WIND
6Technical Potential of Renewable Energy
- Biomass Power Generation Potential and Installed
Capacity
7Technical Potential of Renewable Energy
- State wise Gross Potential and Installed Capacity
in MW - Biomass
8Technical Potential of Renewable Energy
- State wise Gross Potential and Installed Capacity
in MW Small Hydro (2007
9Technical Potential of Renewable Energy
- Solar Based installations in India March 31,
2008
10Technical Potential of Renewable Energy
- India Receives Solar Energy - 5000 trillion
kWh/year equivalents - (Total Energy Consumption in FY 2010-11 projected
as 848 billion kWh by CEA)
11Renewable Energy Programme - India
- India Started its renewable energy programme in
1981 - Establishment of Commission for
Additional Sources of Energy - Converted the same into Ministry of Non
conventional sources of Energy resources in 1992 - In year 2006, it was renamed Ministry of New
and Renewable energy (MNRE)
12Policy Base for RE Promotion
- Electricity Act 2003
- Section 86(1) of EA 2003 mandates SERC to
- Promote Co-generation from Renewable Sources of
energy by providing suitable measures for
connectivity to Grid and sale of electricity to
any person, and also specify, for purchase of
electricity from such sources, a percentage of
total consumption of electricity in the area of
distribution licensee - National Tariff Policy
- Para 6.4 of the Tariff Policy stipulates
- Pursuant to provisions of 86(1) (e) of EA 2003,
Appropriate Commission shall fix minimum
percentage for purchase of power from RE sources
in the region and its impact on retail tariffs
13Policy Base for RE Promotion
- National Rural Electrification Policies (NREP)
2006 - Include provision of access to electricity to all
households by 2009 - Quality and reliable power supply at reasonable
rates - For villages/habitations where grid connectivity
is not feasible of cost effective, off-grid
solutions based on stand alone renewable systems
may be taken up - Supports to achieve target of 10 renewable
energy through RPO (Renewable Purchase
Obligation)
14Integrated Energy Policy 2006
- Power regulators must seek alternative incentive
structures that encourage utilities to integrate
wind, Small Hydro, cogeneration into their
systems - Power regulators should mandate feed-in-laws for
renewable energy where appropriate, as provided
under the electricity Act - Generation based incentives for MW scale grid
connected solar PV and thermal power plants - An additional tariff for new wind power plants
which donot claim accelerated depreciation benefit
15Renewable Energy regulations support
- Renewable Energy Purchase Obligations
- Feed in Tariffs
- Fiscal Incentives such as accelerated
depreciation and tax holiday - Generation Based Incentive
16Policy Framework for Promotion of Renewable Energy
- Feed-in Tariff Policy
- It is a generic description of a policy that pays
a price, a tariff for the electricity generated
by RE that is fed into or sold to the grid - Transparent, comprehensible, equitable
17Policy Framework for Promotion of Renewable Energy
18Policy Framework for Promotion of Renewable Energy
- Renewable Portfolio Standard
- The EA 2003 has outlined several enabling
provisions to accelerate the development of RE
based generation - (Section 3) National Electricity Policy and Plan
for development of power system based on optimal
utilization of resources including renewable
sources of energy. - (Section 61(h)) Tariff Regulations by Regulatory
Commission to be guided by promotion of
generation of electricity from renewable energy
sources in their area of jurisdiction. - (Section 86(1)(e)) Regulatory Commission to
Specify Purchase Obligation from renewable energy
sources. - (Section 66) Appropriate Commission shall
endeavor to promote the development of market
(including trading) in power in such a manner as
may be specified and shall be guided by National
Electricity Policy in Section 3
19RPOs targets in few states
20Key Features of existing RPOs
- Specify of RE every utility need to purchase
- Single target for overall renewable energy
purchase, - Usually close to existing purchase levels,
- In some cases Y-o-Y targets,
- Technology specific targets in some States
- Period is up to five years,
- Applicable to OA/Captive in only three States,
- Purchase of RE from outside the State is not
permitted, - Silent on mode of procurement, competitive or
cost based - Weak on enforcement methodology
21Policy Framework for Promotion of Renewable Energy
- Foreign Investment Policy
- Proposal for up to 100 percent foreign equity
participation in a joint venture qualify for
automatic approval - Foreign investment Promotion Board (FIPB)
- Encourages for BOO basis
- There is no prior approval of the Government is
required to set up industrial undertaking with
FDI by NRIs - RBI permitted Indian Companies to accept
investment under the automatic route without
obtaining prior approval from RBI to set RE based
projects
22Policy Framework for Promotion of Renewable Energy
- Foreign Investment Implementation Authority
(FIIA) - Under the Ministry of Commerce and Industry
- Would provide one stop after care service to FIs
by helping them to expedite approvals and
clearances and to sort out operational problems - Act as single point interface between the
investors and Govt agencies
23Policy Framework for Promotion of Renewable Energy
- Industrial Policy
- MNRE is promoting medium, small, mini, micro
enterprises for manufacturing and servicing of
various types of RE systems and devices - For setting up of an RE industry, industrial
clearances as well as no clearance from CEA for
power generation up to Rs. 1000 million - RE power generation projects five year tax
holiday - RE Equipment manufacturing soft loans are
available through IREDA - Private sector companies can set up enterprises
to operate as licensee or generating companies - Customs duty concession is available for RE
spares and equipment
24Policy Framework for Promotion of Renewable Energy
- Joint Ventures Policy
- Its a financial as well as technical
collaboration and they are used by FIs - Usually JVs are in the form of takeovers or
strategic alliances - Policies for small scale industries
- Does not exceed Rs. 10 million
- Not permitted more than 24 equity in its paid up
capital from any industrial undertaking, foreign
/ domestic - National Small Industries Corporation (NSIC)
provides assistance
25Policy Framework for Promotion of Renewable Energy
- Incentives for investing in RETs
- Fiscal incentives
- Direct taxes 100 depreciation in the first
year of installation - Exemption / reduction in excise duty
- Exemption from central sales tax and customs duty
concessions on import of material, components etc - Income Tax
- Sec 32 accelerated 80 depreciation on
specified RE based devices - Section 115 J Exemption from MAT to industrial
undertakings on profits derived from the business
of generation and distribution of electricity - 100 deduction in respect of profit and gains
from business of collecting and processing
biodegradable wastes
26RE Regulatory Issues - RPOs
- What is the basis for determination of these
percentages and should the RPO include both the
minimum and maximum percentage? - Whether DISCOMs should be free to procure RE
power from other DISCOMs in case of
non-availability of RE sources within their own
distribution area to meet the target? - Whether the RPO percentage shall be applicable
for all distribution companies operating in a
state or should separate percentages be fixed for
different DISCOMs? - Further should the DISCOMs be free to purchase RE
power from outside the state and if so how?
27RE Regulatory Issues Tariff/ Pricing
- Is it more appropriate to set tariffs for RE
based power based on cost-plus principles or
linked to the cost of generation of the marginal
plants? - Is there a tariff setting mechanism by which
environmental benefits of RE sources can be
quantified? In cost plus regime can incentives
be introduced by the regulator and be built in
tariff structure of such sources? - What would be appropriate cost sharing mechanism
if tariffs which are set using the cost-plus
principles exceed the average cost of generation
from RE sources?
28RE Regulatory Issues Grid Connectivity
- Who should bear the cost of grid extensions up to
the nearest receiving sub-station? - Should there be a sharing of cost by the
developer? - What should be the approach for deciding the
technical parameters of interconnection?
29Alternative Approaches for Tariff Determination
- Cost Based Approach
- The cost based approach relies on the requisite
station wise information and is adjusted by
performance standards by regulators where the
rate of return on capital investments is
regulated and a cap is imposed on clear profit - Marginal cost / Avoided cost based approach
- The marginal cost or the avoided cost based
approach considers the unit cost of energy
displaced at the margin by the energy generated
at the margin by the renewable energy based power
plant
30Pricing options for non-firm power
- Short run marginal costing/Avoided cost
- UI Mechanism formulated under ABT
- Capacity charge
- Energy charge
- UI charge
- RECs
31Need for inter-state sales
- Renewable sources are not spread evenly across
country - Many states with no or little RE are not able to
promote RE - States with good RE have exhausted their capacity
- Currently, no mechanism for purchase of RE across
the State boundary - It may not be possible to carry out inter-State
sales using CERC OA Regulations for following
reasons - Most RE generators are difficult to schedule
- Transaction would be expensive due to low
capacity factors of RE - RE generators are not connected to STU but to
Discoms - Intra-state balancing systems have not yet
stabilized - Therefore, a mechanism which will enable
inter-state sale and purchase of renewable energy
is required.
32NAPCC Specific Provisions related to RE
- At National level for FY 2010, target for RE
Purchase may be set at 5 of total grid purchase,
to be increased by 1 each year for 10 years. - SERCs may set higher target than this minimum at
any point in time. - Central State Govts may set up a verification
mechanism to ensure that renewable power is
actually procured. - Appropriate authorities may issue certificates
that procure renewable power in excess of the
national standard. Such certificates may be
tradable, to enable utilities falling short to
meet their RPS. - Penalties as may be allowed under EA 2003 may be
levied, if utilities are still falling short in
RPS.
33Concept of Renewable Energy Certificate
34Model Guidelines / Procedure for Accreditation
35Procedure for Registration
36Procedure for Issuance
37Procedure for Redemption
38Renewable Energy Certificates General Features
- STEP 1 The applicant shall apply for
Accreditation on the Web Based Application and
shall also submit the same information in
physical form with the State Agency. - The application for accreditation shall contain
- (i) owners details,
- (ii) operator details
- (in case the owner and operator are different
legal entities), - (iii) Generating Station details
- In case, the Applicant has multiple RE generation
projects then, separate Applications will have to
be submitted by the Applicant for each RE
generation project. Accreditation of each RE
generation project shall be carried out
separately. - The Application made for accreditation of RE
generation project shall be accompanied by a
non-refundable processing fee and accreditation
charges (one time and annual, if any) as
determined by the Appropriate State Electricity
Regulatory Commission from time to time.
39Renewable Energy Certificates General Features
- STEP 2 The State Agency shall assign a unique
acknowledgement number to the Applicant for each
application for accreditation of its RE
generation project, for any future
correspondence. - STEP 3After receipt of application in physical
form for accreditation, the State Agency shall
conduct a preliminary scrutiny to ensure
Application Form is complete in all respect along
with necessary documents and applicable
processing fees and accreditation charges. The
State Agency shall undertake preliminary scrutiny
of the Application within 5 working days from
date of receipt of such Application.
40Renewable Energy Certificates General Features
- STEP 2 The State Agency shall assign a unique
acknowledgement number to the Applicant for each
application for accreditation of its RE
generation project, for any future
correspondence. - STEP 3After receipt of application in physical
form for accreditation, the State Agency shall
conduct a preliminary scrutiny to ensure
Application Form is complete in all respect along
with necessary documents and applicable
processing fees and accreditation charges. The
State Agency shall undertake preliminary scrutiny
of the Application within 5 working days from
date of receipt of such Application. - STEP 4 After conducting the preliminary
scrutiny, the State Agency shall intimate in
writing to the Applicant for submission of any
further information, if necessary, to further
consider the application for accreditation or
reject application. The reasons for rejecting the
application for accreditation shall be recorded
and intimated to Applicant in writing within 2
working days from date of receipt of the
completed application by State Agency.
41Renewable Energy Certificates General Features
- STEP 5While considering any application for
accreditation of RE generation project, the State
Agency shall verify and ascertain availability of
following information - Undertaking of 'Availability of Land' in
possession for setting up generating station - Power Evacuation Arrangement permission letter
from the host State Transmission Utility or the
concerned Distribution Licensee, as the case may
be - Confirmation of Metering Arrangement and Metering
Location - Date of Commissioning of RE project for existing
eligible RE Project or Proposed Date of
Commissioning for new RE for accreditation - Undertaking regarding Off-take/Power Purchase
Agreement - Proposed Model and Make for critical equipment
(say, WTG, STG, PV Module) for the RE Project.
Confirmation of compliance of critical equipment
with relevant applicable IEC or CEA Standards - Undertaking for compliance with the usage of
fossil fuel criteria as specified by MNRE - Details of application processing
fees/accreditation charges
42Renewable Energy Certificates General Features
- STEP 6 The State Agency,
- after duly inspecting/verifying conditions
elaborated in Step 5, shall grant 'Certificate
for Accreditation' to the concerned Applicant for
the proposed RE Generation project - assign a specific project code number to that
effect which shall be used by the such Applicant
(Eligible Entities) for all future correspondence
with the State Agency. The process of
accreditation shall normally be completed within
30 days from date of receipt of complete
information by State Agency. In case
accreditation is not granted at this stage, the
reasons for rejecting the application for
accreditation shall be recorded and intimated to
Applicant in writing. - STEP 7 If accreditation is granted, the State
Agency shall also intimate accreditation of
particular RE generation project to the following
entities, - The Central Agency, as defined under Clause 2(1)
(b) - The host State Load Despatch Center
- The distribution company in whose area the
proposed RE generation project would be located.
43Renewable Energy Certificates General Features
- 1 certificate ? 1 MWhe of renewable energy
generated -
- Mechanism is used in many countries, RPS (US
Japan), ROCs (UK), RECs (Australia). - Certificates are traded to meet the mandatory
targets for RE purchases by utilities/DISCOMs - Targets establish demand
- Market for RECs sets price
- At times regulators fixes the ceiling price in
form of penalty to bring in certainty - Purchase of REC would be deemed as purchase of
renewable energy. - Entity under S 86(1)(e) obligation can purchase
RECs to satisfy its obligation.
44REC Mechanism for implementation in India
- Renewable Energy Certificate (REC) shall be proof
that certain environmental attributed have been
produced by way of generation of renewable energy - RE generators will be selling two products
- Electricity generated by RE source
- Environmental attributes in the form of REC
- Electricity will be procured by the licensee to
whose network RE generator is connected - Purchase would be at the prices determined by the
SERC which may be average power purchase price
for that utility - It will reduce the burden on the local
distribution licensee - RECs could be procured by all entities subjected
to RPS. - For serving RPS, purchase of RECs should serve
the purpose
45Thank YouRajkiran V. Bilolikar,Assistant
Professor, Energy Area,Administrative Staff
College of India, Bella Vista, Raj Bhavan Road,
Hyderabad - 500082 T 91 40 6653 4390F 91
40 6653 4356M 91 9704087888rajkiran_at_asci.org.
in