Title: Aviation Outlook Pacific Island Airports
1Aviation OutlookPacific Island Airports
- Honolulu Airports District Office
2Aviation OutlookPacific Island Airports
- Airport Improvement Program Update
- AIP Grant Funds for the Pacific Island Airports
- AIP Priority Ranking System
- AIP Performance Criteria
- AIP Program Accomplishments
- ACIP Priorities Funding Strategy for FY-2008
3Aviation OutlookPacific Island Airports
- FAA Outreach and Training Activities
- Airports Program Training Workshops
- Airport Emergency Operations Training for
Micronesia Airports
4Airport Improvement Program Grant Funds for
Airports in the Pacific
FY-2002 76,358,196FY-2003
89,767,666FY-2004
102,796,375FY-2005
120,908,238FY-2006
70,693,036 FY-2007 136,154,847
5Airport Improvement Program Grant Funds for
Airports in the Pacific
- FY-2002
- Entitlements 52,014,044
- Discretionary 24,344,152
- FY-2003
- Entitlements 52,290,657
- Discretionary 37,477,009
- FY-2004
- Entitlements 48,791,062
- Discretionary 54,005,313
- FY-2005
- Entitlements 65,560,652
- Discretionary 55,347,586
- FY-2006
- Entitlements 38,419,109
- Discretionary 32,273,927
- FY-2007
- Entitlements 41,538,883
- Discretionary 94,415,964
6AIP Discretionary Funds
- Micronesia Airports are only eligible for AIP
driscretionary funds, not entitlement funds. - AIP discretionary funds are limited and are
distributed on a competitive basis based on the
AIP Priority Ranking System and Airport Sponsor
Performance.
7AIP Discretionary Funds AIP Priority Ranking
System
- Priorities
- Safety regulatory requirements
- Reconstruction infrastructure preservation
- Standards incorporate current FAA standards
- Capacity Enhancement increases capacity
8ACIP Funding Strategy
- Based on AIP Priority System
- ARFF Vehicles and Equipment
- Construct ARFF Buildings
- Pavement Rehabilitation including upgrades to
Airfield Electrical Systems Marking, Lighting and
Signage - Perimeter Security Fencing
- National Program Objectives
- RSA Improvements
- Class III Airport Compliance
9AIP Discretionary Funding Performance Criteria
- Construction projects funded with AIP
discretionary funds must have plans and
specifications completed and ready for bid
solicitation so that the AIP grant can be issued
based on construction bid prices.
10AIP Discretionary Funding Performance Criteria
- Projects funded with AIP discretionary funds must
be underway within six (6) months from the date
the AIP grant is signed.
11AIP Discretionary Funding Performance Criteria
- Projects funded with AIP discretionary funds must
be physically and financially completed within
four (4) years from the date of the AIP grant.
12AIP Discretionary Funding Performance Criteria
- In making AIP discretionary funding decisions,
the FAA is required to consider whether funding
has been provided for all other higher priority
projects.
13AIP Discretionary Funding Participation Rates
- For Pacific Island Airports
- Federal share 95 of eligible costs
- Sponsor share 5 of eligible costs
- Except Honolulu and Kahului Airports where the
participation rate is - Federal 75 / Sponsor 25
14AIP Program Accomplishments
- AIP Program Accomplishments
- ARFF Vehicle Acquisition
- Construct ARFF Buildings
- Pavement Rehabilitation including upgrades to
Electrical Systems, Airfield Marking, Lighting
and Signage - Perimeter Security Fencing / Roadway
151. ARFF Vehicle Equipment Acquisition
- We have funded new generation ARFF vehicle
acquisition throughout the Pacific Region
nearly 50 ARFF vehicle replacements are
identified. - We included RIV vehicles ARFF Auxillary
Equipment acquisition at airports where justified.
16(No Transcript)
17(No Transcript)
18(No Transcript)
19(No Transcript)
20(No Transcript)
212. ARFF Building Construction
- Palau
- Majuro
- Pohnpei
- Chuuk
- Yap
- Kosrae
- Fitiuta
- Ofu
- Kona
- Waimea-Kohala
- Hana
- Kalaupapa
- Molokai
- Lanai
- West Tinian
- Saipan
22Pago Pago International Airport
23Guam International Airport
24Saipan International Airport
25(No Transcript)
26(No Transcript)
27(No Transcript)
28(No Transcript)
293. Pavement Rehabilitation
- Saipan Runway
- Guam Runway Taxiway Extensions
- Pago Pago Runway (8/26)
- Palau Runway Terminal Apron(s)
- Majuro Runway Terminal Apron
- Pohnpei Runway Terminal Apron
- Kosrae Runway Terminal Apron
- Chuuk Runway Terminal Apron
- Yap Terminal Apron Runway
303. Pavement Rehabilitation
- Honolulu Taxiways
- Kahalui Runway (2/20) Access Road
- Lihue Taxiway C Apron
- Kona Taxiways Apron
- Hilo Taxiways Aprons
- Lanai General Aviation Apron
- Molokai Runway
- Dillingham Runway Taxiway
31Pago Pago International Airport
32Majuro International Airport
33Palau International Airport
34(No Transcript)
35(No Transcript)
36(No Transcript)
374. Perimeter Security Fencing
- Palau
- Majuro
- Pohnpei
- Chuuk
- Yap
- Kosrae
- Ofu
- Guam
- Rota
- Hilo
- Lihue
- Kalaupapa
38(No Transcript)
39Micronesia Airports ACIP Priorities for FY-2008
- Phased Projects under Construction
- Airport Master Plans System Plans
- Development of Maintenance Plans
- Development of ACMs
- Water Rescue Plans
- Wildlife Hazard Management Plans
- Conduct Obstruction Surveys
- Need for Capacity Enhancements
- Regional Airport System Needs
40Funding Strategy for FY-2008
- We plan to fund construction projects that have
construction bid prices to base the grant amount
on. - We need to have Planning consultant bids in by
April. - We need to have Construction bids in by May, no
later than June 1st. - NOTICE All FY-2008 AIP Grants must be accepted
by June 20th.
41Aviation OutlookPacific Island Airports
- FAA Outreach and Training Activities
- Airports Program Training Workshops
- Airport Emergency Operations Training for
Micronesia Airports - Table Top Exercises for Micronesia Airports
42Airports Program Workshops
- Workshops have been conducted
- Airport Compliance
- Airport Safety and Operations Specialists (ASOS)
- AIP Back-to-Basics (AIP-101)
- FAR Part 139 Airport Certification
- AIP Next Steps
- AIP Project Procedures
43Airports Program Workshops
- January 2007
- Conducted an AIP Program Guidance Certification
Workshop for the Micronesian airport
representatives. - Co-sponsored with and hosted by the Commonwealth
Ports Authority.
44(No Transcript)
45AIP Program Guidance Certification Workshop
- Workshop Agenda included
- AIP Program Guidance
- AIP Project Reports
- Airport Certification Guidance
- One-on-one ACIP Discussions
- Airport Project Tour
- Demonstration at Pacific Region ARFF Training
Center
46AIP Program Guidance Certification Workshop
- Challenges Ahead
- Manage your contracts
- Keep projects on schedule
- Need project bids early as possible
- Ensure best quality projects
- Ensure safety is maintained
- Make timely payments
- Prepare recordkeeping for audits
47(No Transcript)
48(No Transcript)
49(No Transcript)
50Airports Program Training Workshops
- January 2008
- We conducted an AIP Program Update
Certification Workshop for the Micronesian
airport representatives. - Co-sponsored with and hosted by the Republic of
Palau, and Palau International Airport.
51AIP Program Update Certification Workshop
52AIP Program Update Certification Workshop
- Workshop Agenda included
- AIP Program Guidance
- AIP Project Reports
- Airport Certification Guidance
- Best Practices / Lessons Learned
- One-on-one ACIP Discussions
- Airport Project Tour
- Airport Self-Inspection Training
53AIP Program Update Certification Workshop
- Challenges Ahead
- Procurement of Airport Maintenance Equipment
- Establish ARFF Vehicle Maintenance Practices
- Establish Airport Self-Inspection Programs
- Improve Wildlife Hazard Management Practices
54(No Transcript)
55(No Transcript)
56(No Transcript)
57(No Transcript)
58Airports Program Training Workshops
- August 2008
- We plan to conduct an Airport Sponsor Compliance
Refresher Workshop to cover airport sponsor
obligations and grant agreement assurances. - Co-sponsored with and hosted by the State of
Hawaii at Honolulu International Airport.
59(No Transcript)
60(No Transcript)
61Airport Emergency Operations Training
- Airport Emergency Planning
- Incident Command System
- Emergency Operations Center
- Table Top Exercises
- Airline Family Assistance Plan
- NTSB Role and Coordination
- Full-scale Disaster Exercise
- Formal Evaluation and Critique
62Airport Emergency Operations Training
- Planned Schedule for 2008
- Yap June 9 13, 2008
- Palau September 2008
63(No Transcript)
64(No Transcript)
65(No Transcript)
66(No Transcript)
67(No Transcript)
68(No Transcript)
69Airport Emergency Operations Training
- Table Top Exercises
- In January 2008, FAA sponsored an Emergency
Operations Tabletop Exercise on Chuuk. - Requested and supported by the Chuuk State
Governors Office.
70(No Transcript)
71(No Transcript)
72Airport Emergency Operations Training
- In conjunction with the 2008 PADW
- Emergency Crisis Management
- Emergency Operations Center Preparation
Management - Conducted by the Pacific Region ARFF Training
Center
73Aviation OutlookPacific Island Airports
- The Honolulu Airports District Office is
committed to providing quality workshops and
training to the Pacific Island airport sponsors
to provide guidance in administering the AIP
Program, and airport safety, certification and
compliance programs.
74Aviation OutlookPacific Island Airports
- The Honolulu Airports District Office is
committed to working with the Pacific Island
airport sponsors to develop the best strategy to
ensure maximum utilization of AIP funds for
airport infrastructure development to meet the
needs of the Pacific Island airports.
75One-on-One Sessions
- During this Workshop we are conducting One-on-One
Sessions with the Micronesian airport and
government officials to discuss their airport
development plans, priorities, project schedules,
funding timelines, and safety and security issues.
76One-on-One Sessions
- The One-on-One discussions will take place
immediately following each days presentations. - Monday Palau
- Tuesday F. S. M.
- Wednesday Marshall Islands
77One-on-One Sessions
- Invited to Join the One-on-One Sessions
- Airline Representatives - to discuss airport
safety concerns. - USDA Representatives to discuss wildlife hazard
concerns. - NWS FAA ATO to discuss SWARS integration into
ARFF buildings. - TSA Representatives to discuss airfield
security issues.
78Honolulu Airports District Office Contacts
- Ron Simpson, Manager HNL ADO (808)541-1232
Vacant, Cert. Inspector (808)541-1243
Gordon Wong, Project Manager (808)541-3565 Steve
Wong, Project Manager (808)541-1225 Carissa
Unpingco, Project Manager (808)541-1242 Donna
Ajifu, Program Analyst (808)541-1231 Cheryl
Tsutsuse, Admin. Officer (808)541-1232
79? ? ANY QUESTIONS ? ?
80ltSlide Titlegt
WHO IS THIS GUY?
81ltSlide Titlegt
82MAHALO NUI LOA