Transmission Access Challenges for Wind Generation - PowerPoint PPT Presentation

1 / 18
About This Presentation
Title:

Transmission Access Challenges for Wind Generation

Description:

Transmission Access Challenges for Wind Generation Developing solutions nationwide and in ERCOT Fundamental challenge in wind development is still resolving the ... – PowerPoint PPT presentation

Number of Views:36
Avg rating:3.0/5.0
Slides: 19
Provided by: attorneysL
Category:

less

Transcript and Presenter's Notes

Title: Transmission Access Challenges for Wind Generation


1
Transmission Access Challenges for Wind Generation
  • Developing solutions nationwide and in ERCOT

2
Fundamental challenge in wind development is
still resolving the chicken and egg problem.
  • renewable projects cannot secure contracts
    under RPS procurement procedures without knowing
    whether existing transmission will be able to
    accommodate them. At the same time, utilities
    are wary of investing in renewable transmission
    without assurances of cost recovery, which is
    premised on the renewable generation being
    built.1
  • 1 CEC 2005 Integrated Energy Policy Report at
    99 (November 2005).

3
In addition to the lack of adequate transmission
system development, specific transmission-related
challenges continue to inhibit development of
wind generation, e.g.
  • Lack of comprehensive regional transmission
    planning process and limited RTO/ISO authority
  • Imbalance charges in transmission tariffs
  • Obstacles in the interconnection process and
    interconnection queue delays
  • Transmission cost allocation and assignment
    methods
  • Calculation of the available transmission system
    capacity
  • Difficulties in the existing methods for
    evaluating requests for long-term firm
    point-to-point transmission service
  • Rate pancaking

4
The FERC, DOE, and Congress are taking steps to
respond to these impediments to the development
of wind generation
  • FERC Orders No. 661 and 661-A, Interconnection
    for Wind Energy
  • FERC Order 890, Open Access Transmission Tariff
    Reform
  • FERC CAISO Decision
  • FERC Docket No. RM07-19, Wholesale Competition in
    Regions with Organized Markets
  • DOE Designation of National Interest Electric
    Transmission Corridors
  • Senator Thune Amendment to Energy Bill
    designating Clean Energy Corridors
  • Senator Reid Clean Energy and Economic
    Development Act

5
FERC Orders No. 661 and 661-A, Interconnection
for Wind Energy
  • Standardizes interconnection agreements for wind
    generation above 20 MW
  • Requires transmission providers to append new
    provisions to the standard agreement for
    interconnecting large generating facilities,
    which are required under their open-access
    transmission tariffs, in order to address
    technical requirements and procedures for
    integrating large wind power facilities into
    their transmission systems
  • Requirements of wind generators
  • Wind generating facility must remain operational
    during voltage disturbances on the grid.
  • Large wind plants must, if needed, meet the same
    technical criteria for providing reactive power
    to the grid as required of conventional large
    generating facilities.
  • Provides for supervisory control and data
    acquisition (SCADA), if needed, to ensure
    appropriate real-time communications and data
    exchanges between the wind power producer and the
    grid operator.

6
FERC Order 890, Open Access Transmission Tariff
Reform Significant Reforms for Wind Generation
  • Greater consistency and transparency in the
    available transmission capacity (ATC) calculation
  • Provides for open, coordinated and transparent
    planning on a local and regional level
  • Reforms energy and generator imbalance penalties
  • Adopts a conditional firm component to
    long-term point-to-point service

7
FERC CAISO Decision Addresses chicken and egg
problem in California and provides a model for
other areas.
  • Approval of financing mechanism for the
    construction of transmission interconnection
    facilities to connect location-constrained
    resources to the CAISO grid.
  • Financing mechanism rolls in the cost of
    transmission facilities through transmission
    revenue requirement (TRR) of constructing
    transmission owner
  • Cost of the facility reflected in the CAISO
    transmission access charge (TAC), assessed on a
    gross load basis
  • Each connecting generator responsible for pro
    rata share of going forward costs of using the
    transmission line.
  • Once line is fully subscribed, all users of the
    grid pay the cost of the unsubscribed portion of
    the line through inclusion in the TAC.
  • Once facilities are constructed, generators of
    any fuel type eligible to interconnect and
    contract for unsubscribed capacity.

8
FERC Docket No. RM07-19, Wholesale Competition in
Regions with Organized Markets Docket to
determine how to improve competition in regions
with organized markets.
  • Regional markets can integrate more wind energy
    than small balkanized balancing areas, thus
    docket provides an opportunity to address
    critical wind issues interconnection queue
    logjams and insufficient RTO/ISO authority
  • Interconnection queue logjams are inhibiting
    development in MISO and CAISO. Queue management
    difficulties mean that deadlines are being missed
    and interconnection costs remain uncertain.
  • Given significant need for new transmission,
    RTOs/ISOs should have greater transmission
    planning authority and greater authority to order
    and approve construction.

9
DOE Designation of National Interest Electric
Transmission Corridors
  • Corridors designated in the Mid-Atlantic Area
    (OH, WV, PA, NY, MD, VA) and Southwest Area (CA,
    AZ).
  • Designations do not direct the construction of
    new facilities, but Energy Policy Act of 2005
    authorizes FERC to issue permits for new
    transmission facilities within National Corridor.
  • Senator Thune Amendment to Energy Bill
    designating Clean Energy Corridors
  • Would further amend the Energy Policy Act to
    provide for Clean Energy Corridors to be
    designated by the DOE specifies that FERC is to
    promulgate regulations for cost recovery of
    transmission providers that build and operate
    facilities authorized under the amendment.

10
Senator Reid Clean Energy and Economic
Development Act proposing National Renewable
Energy Zone designation
  • Based on Texas CREZ model
  • National Renewable Energy Zone designation
    provides for areas with significant renewable
    energy resources to be connected to transmission
    grid through transmission lines to be paid for by
    all utility consumers.

11
Transmission Access for Wind Generation in Texas
  • Implementation of Competitive Renewable Energy
    Zones
  • PUCT Interim Order Designated Competitive
    Renewable Energy Zones and Established Tiers of
    Transmission Transfer Capacity for ERCOT Study

12
Zones Approved by Commission
13
Tiers of transmission transfer capacity the PUCT
has asked ERCOT to review in Transmission
Optimization Study
14
Tiers of transmission transfer capacity as
proposed by ERCOT as of November, 2007
15
Preliminary transmission issues identified by
ERCOT in TOS
  • What is the definition of a CREZ transmission
    line?
  • Need to develop standardized terminology for
    direct interconnect, on-ramp, and other
    transmission interconnection terms
  • What is the definition of transfer capability
  • What is extent of ERCOT review of upgrades that
    are economic in reducing wind generation
    congestion?
  • Should there be a differentiation between
    upgrades for CREZ units vs. other economic
    upgrades?
  • What is potential impact of 765 kV and DC lines
    on system operation?
  • Need to develop standardized transmission line
    parameters and cost assumptions, which now vary
    by region.
  • Should transmission developed for lower MW
    scenarios be expandable?
  • Where should hubs/interconnection points be
    located within a CREZ?
  • Incorporate impact of Ancillary Services Study on
    TOS.

16
Public Utility Commission of Texas Docket No.
34560, Selection of Transmission Service
Providers Related to Competitive Renewable Energy
Zones
  • Proceeding in which the PUCT will determine how
    it will select TSPs to build new CREZ
  • related transmission infrastructure. Key issues
  • 1. Are there advantages to selecting transmission
    service providers on a competitive basis, in
    terms of cost or schedule, for the Competitive
    Renewable Energy Zone (CREZ) transmission
    projects? If there are risks associated with a
    competitive selection process, are the benefits
    sufficient that the Commission should implement
    such a process?
  • 2. Does the PUCT have the latitude to implement a
    competitive process for selecting transmission
    service providers outside of a contested case, in
    which service providers bid on identified cost
    factors (such as cost of capital), these factors
    are used to select a service provider, and a
    service providers bid on a cost factor is then
    incorporated into the rates for the transmission
    project?
  • 3. Does the PUCT have the latitude to adopt
    performance-based incentives (including CWIP in
    rates) and penalties for transmission service
    providers that are selected through a competitive
    process?
  • 4. How could performance-based rates be
    implemented for candidates that are not incumbent
    Transmission Service Providers with rate bases?
  • 5. What are the advantages and disadvantages of
    using the various components of the cost of
    capital as the chief criterion in the selection
    process?
  • 6. Are the business and operating risks of
    transmission-only companies different than those
    of transmission and distribution companies?

17
Public Utility Commission of Texas Docket No.
34577, Proceeding to Establish Policy Relating to
Excess Development in Competitive Renewable
Energy Zones.
  • Proceeding in which the PUCT will promulgate a
    rule to determine a
  • dispatch priority policy vis-à-vis first movers
    and latecomers to
  • prevent piling on problem. And, if transmission
    is not sufficiently
  • sized, rule may determine dispatch priority among
    first movers.
  • Key proposals
  • Nodal market will employ security constrained
    economic dispatch (SCED) to determine most
    efficient dispatch. No special dispatch
    mechanism.
  • Allocation of Congestion Revenue Rights
  • Adjusted Offer Curve
  • Day Ahead Operating Limit with Last In First Off

18
New challenge allocating resources among wind
developers
Write a Comment
User Comments (0)
About PowerShow.com