Title: Transmission Access Challenges for Wind Generation
1Transmission Access Challenges for Wind Generation
- Developing solutions nationwide and in ERCOT
2Fundamental challenge in wind development is
still resolving the chicken and egg problem.
- renewable projects cannot secure contracts
under RPS procurement procedures without knowing
whether existing transmission will be able to
accommodate them. At the same time, utilities
are wary of investing in renewable transmission
without assurances of cost recovery, which is
premised on the renewable generation being
built.1 - 1 CEC 2005 Integrated Energy Policy Report at
99 (November 2005).
3In addition to the lack of adequate transmission
system development, specific transmission-related
challenges continue to inhibit development of
wind generation, e.g.
- Lack of comprehensive regional transmission
planning process and limited RTO/ISO authority - Imbalance charges in transmission tariffs
- Obstacles in the interconnection process and
interconnection queue delays - Transmission cost allocation and assignment
methods - Calculation of the available transmission system
capacity - Difficulties in the existing methods for
evaluating requests for long-term firm
point-to-point transmission service - Rate pancaking
4The FERC, DOE, and Congress are taking steps to
respond to these impediments to the development
of wind generation
- FERC Orders No. 661 and 661-A, Interconnection
for Wind Energy - FERC Order 890, Open Access Transmission Tariff
Reform - FERC CAISO Decision
- FERC Docket No. RM07-19, Wholesale Competition in
Regions with Organized Markets - DOE Designation of National Interest Electric
Transmission Corridors - Senator Thune Amendment to Energy Bill
designating Clean Energy Corridors - Senator Reid Clean Energy and Economic
Development Act
5FERC Orders No. 661 and 661-A, Interconnection
for Wind Energy
- Standardizes interconnection agreements for wind
generation above 20 MW - Requires transmission providers to append new
provisions to the standard agreement for
interconnecting large generating facilities,
which are required under their open-access
transmission tariffs, in order to address
technical requirements and procedures for
integrating large wind power facilities into
their transmission systems - Requirements of wind generators
- Wind generating facility must remain operational
during voltage disturbances on the grid. - Large wind plants must, if needed, meet the same
technical criteria for providing reactive power
to the grid as required of conventional large
generating facilities. - Provides for supervisory control and data
acquisition (SCADA), if needed, to ensure
appropriate real-time communications and data
exchanges between the wind power producer and the
grid operator.
6FERC Order 890, Open Access Transmission Tariff
Reform Significant Reforms for Wind Generation
- Greater consistency and transparency in the
available transmission capacity (ATC) calculation - Provides for open, coordinated and transparent
planning on a local and regional level - Reforms energy and generator imbalance penalties
- Adopts a conditional firm component to
long-term point-to-point service
7FERC CAISO Decision Addresses chicken and egg
problem in California and provides a model for
other areas.
- Approval of financing mechanism for the
construction of transmission interconnection
facilities to connect location-constrained
resources to the CAISO grid. - Financing mechanism rolls in the cost of
transmission facilities through transmission
revenue requirement (TRR) of constructing
transmission owner - Cost of the facility reflected in the CAISO
transmission access charge (TAC), assessed on a
gross load basis - Each connecting generator responsible for pro
rata share of going forward costs of using the
transmission line. - Once line is fully subscribed, all users of the
grid pay the cost of the unsubscribed portion of
the line through inclusion in the TAC. - Once facilities are constructed, generators of
any fuel type eligible to interconnect and
contract for unsubscribed capacity.
8FERC Docket No. RM07-19, Wholesale Competition in
Regions with Organized Markets Docket to
determine how to improve competition in regions
with organized markets.
- Regional markets can integrate more wind energy
than small balkanized balancing areas, thus
docket provides an opportunity to address
critical wind issues interconnection queue
logjams and insufficient RTO/ISO authority - Interconnection queue logjams are inhibiting
development in MISO and CAISO. Queue management
difficulties mean that deadlines are being missed
and interconnection costs remain uncertain. - Given significant need for new transmission,
RTOs/ISOs should have greater transmission
planning authority and greater authority to order
and approve construction.
9DOE Designation of National Interest Electric
Transmission Corridors
- Corridors designated in the Mid-Atlantic Area
(OH, WV, PA, NY, MD, VA) and Southwest Area (CA,
AZ). - Designations do not direct the construction of
new facilities, but Energy Policy Act of 2005
authorizes FERC to issue permits for new
transmission facilities within National Corridor. - Senator Thune Amendment to Energy Bill
designating Clean Energy Corridors - Would further amend the Energy Policy Act to
provide for Clean Energy Corridors to be
designated by the DOE specifies that FERC is to
promulgate regulations for cost recovery of
transmission providers that build and operate
facilities authorized under the amendment.
10Senator Reid Clean Energy and Economic
Development Act proposing National Renewable
Energy Zone designation
- Based on Texas CREZ model
- National Renewable Energy Zone designation
provides for areas with significant renewable
energy resources to be connected to transmission
grid through transmission lines to be paid for by
all utility consumers.
11Transmission Access for Wind Generation in Texas
- Implementation of Competitive Renewable Energy
Zones - PUCT Interim Order Designated Competitive
Renewable Energy Zones and Established Tiers of
Transmission Transfer Capacity for ERCOT Study
12Zones Approved by Commission
13Tiers of transmission transfer capacity the PUCT
has asked ERCOT to review in Transmission
Optimization Study
14Tiers of transmission transfer capacity as
proposed by ERCOT as of November, 2007
15Preliminary transmission issues identified by
ERCOT in TOS
- What is the definition of a CREZ transmission
line? - Need to develop standardized terminology for
direct interconnect, on-ramp, and other
transmission interconnection terms - What is the definition of transfer capability
- What is extent of ERCOT review of upgrades that
are economic in reducing wind generation
congestion? - Should there be a differentiation between
upgrades for CREZ units vs. other economic
upgrades? - What is potential impact of 765 kV and DC lines
on system operation? - Need to develop standardized transmission line
parameters and cost assumptions, which now vary
by region. - Should transmission developed for lower MW
scenarios be expandable? - Where should hubs/interconnection points be
located within a CREZ? - Incorporate impact of Ancillary Services Study on
TOS.
16Public Utility Commission of Texas Docket No.
34560, Selection of Transmission Service
Providers Related to Competitive Renewable Energy
Zones
- Proceeding in which the PUCT will determine how
it will select TSPs to build new CREZ - related transmission infrastructure. Key issues
- 1. Are there advantages to selecting transmission
service providers on a competitive basis, in
terms of cost or schedule, for the Competitive
Renewable Energy Zone (CREZ) transmission
projects? If there are risks associated with a
competitive selection process, are the benefits
sufficient that the Commission should implement
such a process? - 2. Does the PUCT have the latitude to implement a
competitive process for selecting transmission
service providers outside of a contested case, in
which service providers bid on identified cost
factors (such as cost of capital), these factors
are used to select a service provider, and a
service providers bid on a cost factor is then
incorporated into the rates for the transmission
project? - 3. Does the PUCT have the latitude to adopt
performance-based incentives (including CWIP in
rates) and penalties for transmission service
providers that are selected through a competitive
process? - 4. How could performance-based rates be
implemented for candidates that are not incumbent
Transmission Service Providers with rate bases? - 5. What are the advantages and disadvantages of
using the various components of the cost of
capital as the chief criterion in the selection
process? - 6. Are the business and operating risks of
transmission-only companies different than those
of transmission and distribution companies?
17Public Utility Commission of Texas Docket No.
34577, Proceeding to Establish Policy Relating to
Excess Development in Competitive Renewable
Energy Zones.
- Proceeding in which the PUCT will promulgate a
rule to determine a - dispatch priority policy vis-à-vis first movers
and latecomers to - prevent piling on problem. And, if transmission
is not sufficiently - sized, rule may determine dispatch priority among
first movers. - Key proposals
- Nodal market will employ security constrained
economic dispatch (SCED) to determine most
efficient dispatch. No special dispatch
mechanism. - Allocation of Congestion Revenue Rights
- Adjusted Offer Curve
- Day Ahead Operating Limit with Last In First Off
18New challenge allocating resources among wind
developers