Title: Lt Col Taylor Locker
1Department of DefenseRDResponsiveSpaceflight
(RRS)
VSS
VSE
Lt Col Taylor Locker Ch, Spaceflight Mission
Design DoD STP, Kirtland AFB, NM
Lt Col Kirk Sharp Senior Program Advisor DoD STP,
Kirtland AFB, NM
2Why Were We at SMC/TD?
- Propose a holistic concept for repeatable
launching of Space RDTE missions in 12-18
months, using mechanisms that are in place today - A solution other than give me money, people,
and a launch vehicle, and I can in X years . . . - Proposal solves the business (of spaceflight)
problem with standard customer - service provider
relationship - Proposal requires customer funding source only
- Accesses existing capacity across the ST
community - Need a champion to pursue this RRS strategy, or
redirection i.e. Gen Worden gave the challenge
3Bottom Line Up Front
- 1218 month ST spaceflight can be done today
with a team - Finding a solution has been hard, because no
single organization has all the RRS capability in
place right now - One could in future w new resources, IDIQ source
selections, etc - Thus, why not, an Alliance of Govt (all DoD or
para-DoD) Orgs/ Labs, each coming to the table,
to acquire any mission now? - STP has (at least the working level) coordinated
with AFRL, LANL, NRL, RDSMO, RSLP, SDL and
received a positive response (initial commitment)
to propose this RRS Alliance - Willingness to use their existing finance (FM)
and contracts (PK) mechanisms (e.g.,
funding/contract vehicles) to get work done today - Alliance requires a Board of Directors (Alliance
Principals), a Secretariat (e.g., STP), and a
reporting authority (e.g., SMC/TD) - Some SMC Flag Officer support for the proposed
Alliance
4Responsive Space (RS)Missions
Responsive Space
Question What is needed to reduce the cycle time
(currently gt48 mos) and have a repeatable 12-18
month cycle time for Space demonstrations?
5RD Responsive SpaceDiscovery Process
- Key ST Organizations
- Space ST Integrated Experiments (AFRL/VSE)
- Space Structures Controls ST (AFRL/VSS)
- Rocket Systems Launch Program (Det 12/RP)
- DoD Space Test Program (Det 12/ST)
- RD Space Missile Operations (Det 12/VO)
- Los Alamos National Laboratory (LANL/ISR)
- NRL Naval Center for Space Technology (NRL/NCST)
- USU Space Dynamics Lab (SDL)
- Activities
- Interviews
- Meetings with Key Organizations
- Workshop RRS Summit
- Data Collection
- Unique contribution
- Facilities
- Agreements
- Contracts
- Discussed w/ Likely S/C Build Contractors (e.g.,
RSDO) - Sought Aerospace Input
6Our Answer!
- Is Based On
- Expert opinion of some very experienced Space
RDTE (incl. ST) professionals (recog. best) - Experiences and review of unique technical
offerings from each key Space ST organization - Collaboration and cooperation of key
organizations to deliver a repeatable (vice one
off) process - If RRS problem is properly constrained (e.g., fit
Minotaur)
RD Responsive Space is not easy, and has never
been done on a repeatable basis!
Note Was in glory days of the late 60s by RRS
Alliance principal NCST and the glory days of SDI
by AFRL (MSTI)
7How We Attacked the Problem Discovery Tool
- RRS Scenarios
- Dedicated LV, Build S/C
- Dedicated LV, Bring S/C
- Piggyback on Host S/C
- Auxiliary kicked off LV
- (including Space Shuttle)
- ISS External Payload
- (Only ISS Power)
Applied to
8RRS Basic Concept
What we want to do..
Mission Level Activities
What one needs to have to allow it..
9RRS Doable Scenarios
- 1 Dedicated Launch Vehicle (Build S/C)
- 2 Dedicated Launch Vehicle (S/C Brought)
- 3 Piggyback on Host Spacecraft or LV
- 4 Auxiliary satellite deployed from launch
vehicle (includes shuttle deployables) - 5 ISS External Payload (Only ISS Power)
These scenarios helped identify needs, barriers,
dependencies, and get-aheads. They are a
starting point, not a destination.
10How We Attacked the Problem Discovery Tool
- RRS Scenarios
- Dedicated LV, Build S/C
- Dedicated LV, Bring S/C
- Piggyback on Host S/C
- Auxiliary kicked off LV
- (including Space Shuttle)
- ISS External Payload
- (Only ISS Power)
Applied to
We based solutions on what we know can be done
today, and on the team approach (for
repeatability depth)
11What Did We Learn- Results Of Discovery Process!
- Consensus A formal team, confederation of the
willing, Alliance, is necessary to carry out
repeatable RD Responsive Spaceflight credibly
NOW! - No one organization can muster critical mass to
accomplish the RRS goal repetitively TODAY! - A
single org (e.g., STP) could do it in the future
with the proper resource investment. - RD Responsive Space must be performed as a new
process leaves existing processes (e.g., SERB)
alone (non-responsive). - An Alliance collaboration offers a robust and
responsive foundation from which to build a
repeatable process synergy reduces schedule,
(esp. non recurring) cost, and cycle time - Organizational commitment to participate must be
followed by resource (manning funding)
commitment necessary to meet timeline for
responsive TBD in RRS Implementation - For each scenario there are barriers, needs,
dependencies, and schedule realities that must be
recognized and addressed
12Scenario 1 Dedicated LV, Build S/CExample
- Barriers
- Review Process increases time and dollars
- LV 18 Months unless pre-buy
- Personnel Availability
- Long lead time for S/C parts
- Frequency allocation process
- Technical Envelope
- Minotaur LV (Pre Buy)
- S/C Must Fit Minotaur
- Standard S/C Design
- Needs Dependencies
- Freeze Mission Requirements by PDR
- Concept design SRR in one month
- Train Ops on the ground with S/C when available
- Select LV by S/C SRR
- Need quick response to Govt Reviews
- Must have long lead items on-the-shelf
- Standard interfaces defined 30-60 days to PDR
- Schedule Realities
- If an existing standard bus is available 30-60
days to do PDR is doable - Technical complexity drives timeframe
- On-orbit time drives timeframe
- Use of approved COTS pre-positioning long
lead items essential - Each organizations integration approach drives
timeframe - Commissioning S/C will drive design timeframe
- LV Minotaur in 18 months doable without dollars
up front - Increased design margin improves speed of
reviews reduces risk
13RRS Alliance Member CapabilitiesCapabilities
Overlap Supports Rapid Availability Depth for
RRS Repeatability
One off, custom SV. In-house build with
contractor parts. Can meet 18 month schedule,
depending on sensor type. Some limited
capability. Shuttle Other
14The RRS Alliance Concept - How Would It Work?
RRS Alliance Board of Directors
RRS Customer
- RRS Alliance
- Secretariat
- Admin
- Cost Analysis
- Mission Support
15The RRS Alliance Concept - How Would It Work?
RRS Alliance Board of Directors
RRS Customer
RRS Alliance Capabilities (Brokered on a case by
case basis by BoD)
- Scenarios
- Dedicated LV, Build S/C
- Dedicated LV, Bring S/C
- Piggyback on Host S/C
- Auxiliary on LV
- (including Space Shuttle)
- ISS External Payload
- (Only ISS Power)
- RRS Alliance
- Secretariat
- Admin
- Cost Analysis
- Mission Support
16The RRS Alliance Concept - How Would It Work?
RRS Alliance Board of Directors
RRS Customer
RRS Alliance Capabilities (Brokered on a case by
case basis by BoD)
- Scenarios
- Dedicated LV, Build S/C
- Dedicated LV, Bring S/C
- Piggyback on Host S/C
- Auxiliary on LV
- (including Space Shuttle)
- ISS External Payload
- (Only ISS Power)
- RRS Alliance
- Secretariat
- Admin
- Cost Analysis
- Mission Support
RRS Mission
RRS Investment Vision
Technical Solution
- Future Needs
- Program
- Technology
- Processes
Management Approach
17Why An Alliance?Vice Single Organization
- The synergy of the sum of our best RD Space
professionals (team) is greater than any one org
(the parts) - Lowers cost, defines standards, utilizes existing
facilities, builds appropriate overlap for
greater repeatability, reduces cycle time - Increases technical envelope An increased
number of rapid response solutions to todays
need can be exercised - Shares investment in rapid response technologies
(e.g., TacSat series, /VSS GSFCs MR2) is
possible once a commitment from Alliance members
is formally established - A properly managed Alliance can keep shared
commitments visible and accountable, collaborate
vice compete - Broader experience with new tools (modeling
simulation) is enhanced with larger organization
participation (F1 model)
18Conclusion The Way Ahead
- RD Responsive Space Alliance Needs Sponsorship,
Resource Commitments to Develop Successful
Implementation Plan - Sponsor should appoint a Secretariat (e.g., STP)
to facilitate the Alliance BoD (Principals)
perform basic Alliance administration - Secretariat will need to codify commitments,
agreements, Implementation Plan, and execution
process - ASAP - Sponsor or Secretariat should be commissioned to
identify RD Responsive Space barriers and their
mitigation or work around - RRS Alliance Willing to Demonstrate Credibility
by Doing Real Pilot Mission of /TDs choice. We
now know it is Roadrunner! - Alliance will need continued SMC corporate
support of this strategy including help removing
red tape barriers
RD Responsive Space can be done TODAY!
19Roadrunner (TacSat-2) July 05? Spaceflight
(STP-RSLP)
Primary Experiments
- A panchromatic and three-color imaging system to
provide operational NIRS-5 data. (AFRL/VSE) - A 200W Hall thruster electric propulsion systems
the AFRL/PRS Micro-satellite Propulsion
Integration (MPI) experiment ranked 19 on the
03 DoD SERB list. - The software system to provide for autonomous and
rapid checkout of the satellites/payloads in
orbit. - In the current baseline data (imagery) would be
requested through the SIPRNET. These multiple
tasking requests would be tasked at the Virtual
Mission Operations Center (VMOC). - Target Indication Experiment (TIE). TIE is
ranked 15 on the 03 DoD SERB list. (NRL/NCST) - Miniaturized Vibration Isolation System (MVIS).
MVIS is ranked 6 on 03 DoD SERB list.
(AFRL/VSS) - AFRL/VSB Atmospheric Density System (ADS). ADS
is ranked 14 on the 03 DoD SERB list. - ShockRing is ranked 21 on the 03 DoD SERB list.
(AFRL/VSS)
Other Possible SERB Experiments
20We Give Free Estimates!(including other Govt
customers like JPL)
21Back Up Charts
22Other RRS Scenarios
- Technical Envelope, Schedule, Needs, Barriers
- Quad Charts
23Scenario 2 Dedicated LV, Bring S/C
- Technical Envelope
- Minotaur LV (Pre Buy)
- S/C Must Fit Minotaur
- Standard S/C Design
- Barriers
- S/C provider must recognize booster and OPS
Center Limitations - Frequency allocation process
- Needs Dependencies
- Nail down classification issues by end of mission
design (SCG if needed) - S/C structural model to do hard mount coupled
loads (takes 60-90 days) to start mission design - ICD Issues (to LV, to GSE) must be really fleshed
out up front - S/c frequencies, data rates, data stream must be
fully explained during mission design phase - FCC authorization must be obtained by S/C
- Lots of S/C technical data will be required by
Ops team - Mission assurance planning must be done up front
(roles and responsibilities laid out) - Operations characterization completed by PDR
- Ops handbook draft, support for
training/simulations - Need access to S/C technical team to support
operations development and on-orbit efforts - Full understanding of mission assurance
responsibilities - Need 6-9 months to prepare for operations if all
detail known
- Schedule Realities
- Need all S/C characterized by 2 months prior to
S/C thermal vacuum testing - If S/C bringer is also doing operations, only
need to provide launch - Need Mission Assessment at start (about 1
month) - Minimum ops development time 6-9 months (if same
as other types of s/c, if all data is available
24Scenario 3 Piggyback on Host S/C
- Technical Envelope
- Dependent upon S/C
- Barriers
- Current prime (sponsor) culture is against
doing piggybacks at all. Nothing but the
primary mission - Risk adverse primes (sponsors) (No new
technology, no additional things) - Frequency allocation process
- Needs Dependencies
- Detailed ICD for fitting on the Prime (by Prime
PDR, preconfigured interfaces) - Prime interfaces must be Nailed at start
- Must know before hand about capacity on primes
- Must have realistic costing for integration
- Schedule Realities
- Completely dependent on prime s/c schedule
- Preconfigured interfaces foster increased
potential to meet timeline
25Scenario 4 Auxiliary kicked off LV (incl.
Space Shuttle)
- Technical Envelope
- ESPA Class Spacecraft
- Standard S/C Design
- Barriers
- EELV not doing regular ESPA launches
- RD community ability to use every opportunity
(Lack of ) - For Shuttle, NASA Integration and Safety Process
- Frequency allocation process
- Needs Dependencies
- Details of unused capacity (by LV/mission)
- ICD for adapter (mechanical and electrical)
- Schedule driven by Prime payload
- EELV having contract mechanism to accept
secondaries (and trade space) - ISS core completed to free up Shuttle capacity
- Schedule Realities
- Very much like Option 1
- Schedule defined and controlled by Prime Payload
26Scenario 5 ISS External Payload (Only ISS
Power)
- Barriers
- NASA Integration Safety Process takes time
Money - NASA isnt a credible Partner because of past
history with DOD - NASA vs. DoD culture clash
- Frequency allocation process
- Technical Envelope
- Only taking ISS Power
- Limited crew involvement, low impact on ISS
- Safe without services
- Needs Dependencies
- ISS Constraints limit usability
- If you fit the ISS Paradigm then it is
responsive, capability is evolving
- Schedule Realities
- 24 months (can be accelerated)
27RRS Alliance Implementation
- Notional until Implementation Plan Is Fleshed Out
28RRS Alliance Implementation TBD Now That
Commissioned
Charter Provide an .. Structure Function of
the Board of Directors Requirements for Board
Membership Function of Secretariat
Commissioning Authority
29RRS Alliance Secretariat
Functional Position Full Time Equivalents Direct
or 1.0 Secretary 1.0 Mission
Designer 1.0 FM 0.2 PK 0.2 Secret
ariat Total 3.4
30Notional Project Flow
31Notional RRS Project Team
Functional Position Yr 1 Yr 2
Comments Mission Mgr 1.0 1.0 Team
Leads 1.0 1.0 Mission Design 1.0 0.0 S/C
Development 2.5 2.5 S/C contractor team LV
Integration 0.2 0.7 LV team, e.g.
RSLP Flight Planning 5.0 3.0 GS
Development 5.0 2.5 Flight Ops 1.0
5.0 FM 0.2 0.2 PK 1.0 0.5 "SPO"
Total 17.9 16.4
32RRS Alliance Capabilities
- Top Level Summary by Subject Area
33Alliance Support Infrastructure (e.g.,
Mechanisms, Contracts, etc)
- AFRL/VSE
- Aerospace Engineering (IT) Facility
- AFRL/VSS
- SBIRs w AeroAstro, SpaceDev, CSA, etc
- LANL/ISR
- Contract with SSTL (specifically for CFESat)
would new procurement for a 2nd satellite.
Various electrical, mechanical machining
vehicles, which can be used - NRL/NCST
- Contracts w Orbital, SpaceX, SpectrumAstro, etc
- RDSMO
- Contracts w Northrop-Grumman Lockheed-Martin,
Black (SCI, SAR/SAP) White (unclas) experiment
process capability. SCF with access to AFSCN - RSLP
- IDIQ w Orbital for Minotaurs, Peacekeepers
- STP
- No current RRS funding or contracting mechanisms
with exception of SMDC (initially would serve as
real estate broker for the Alliance when
commissioned) - SDL
- UARC funding mechanisms w NRL MDA, contracts
w SmallSats community
34Current Mission Planning Capabilities
- STP has performed extensive mission planning for
SERB experiments. STP receives specifications
for all payloads and then bundles them to
procure a new SV or finds individual piggyback
opportunities for each by matching requirements
of payload to established missions. STP has
mission planning processes in place in-house to
quickly and efficiently match payloads with
access to space. - NRL performs mission planning for their in-house
SV builds. - AFRL/VS performs mission planning for their
in-house SV builds. AFRL/VS Distributed
Architecture Simulation Lab (DASL) hosts
Satellite Tool Kit. Several multi-year contract
vehicles are available to perform mission mod and
sim (MRC, PSS, ICS, PRA, Dynacs, ASI), and they
have a lot of ceiling to MPIR money. Tasking
must be within scope of contract. Approx 30 days
to get them on-contract. - LANL has performed mission planning for our
in-house SV builds - SDL can provide up-front SV design. SDL services
can be accessed using the sole-source UARC
contract. (University Affiliated Research Center)
already in place. Any DoD organization can
funnel money through it as long as it has
something to do with space sensors, expect a
1-month turnaround. However, in an emergency we
can typically carry the program for a month or
two on internal funding. In those cases we have
started work on contracts within the same week.
35Current S/C Capabilities- Facilities
- AFRL/VS Aerospace Engineering Facility (AEF)
hosts environmental chambers, baking and curing
chambers, T-Vac chambers, EMI screen room, shaker
tables, clean rooms, solar simulation lamp, spin
table, and mass properties table. JT contract
handles most of the SV IT tasks. - SDL hosts Thermal Optical Research chamber, T-Vac
chambers, RF-shielded anechoic chamber, shaker
table, clean rooms, machine shop, and 5 SCIFS.
Scheduling is rarely a problem, and all could be
made available almost on-demand. - NRL hosts anechoic chambers, integration
facilities, clean rooms, T-Vac chambers,
vibration shakers, acoustic chamber, pyro shock
and static load test capabilities, ground-based
instrument calibration facilities, satellite
laser ranging facility, and an on-orbit
calibration facility. - LANL hosts clean rooms T-vac chambers screen
room various calibration facilities photon,
x-ray, neutron, and gamma-ray sources laser
linear accelerator classified and unclassified
computing facilities classified and unclassified
shock facilities RF and optics labs satellite
integration facility, and electron cyclotron
resonance ion beam facility. LANL also has 2
SCIFs for black projects.
36Current S/C Capabilities- Services
- AFRL/VS Distributed Architecture Simulation Lab
(DASL) has modeling and simulation capabilities
for SV subsystems, payload modeling,
hardware-in-the-loop evaluations, and development
of flight software. Several multi-year contract
vehicles are available to perform mod and sim
(MRC, PSS, ICS, PRA, Dynacs, ASI), and they have
a lot of ceiling to MPIR money. Tasking must be
within scope of contract. Approx 30 days to get
them on-contract. - SDL builds custom SVs, so does not have a
standard structure to offer, but can perform the
following Structure, electronics, and thermal
blanket design fabrication thermal reflectors
or paint application cable buildup sensor
re-design some sensor design build sensor and
spacecraft integration sensor testing
spacecraft testing (EMI/EMC, Thermal vac, shake
vibe) SV-LV integration assistance. SDL
services can be accessed using the sole-source
UARC contract. (University Affiliated Research
Center) already in place. Any DoD organization
can use it as long as it has something to do with
space sensors. Approx 30 days to get them
on-contract. - NRL builds custom SVs, so does not have a
standard structure to offer, but has task order
contracts with Orbital Sciences and Honeywell in
place for parts and services that can be used if
in scope. Can get them on-contract in a day, if
necessary.
37Current S/C Capabilities- S/C Builds
- AFRL/VSE has MightySat II.1 bus to offer. It has
flown. Long-lead items are in storage, and bus
can be available in less than 1 year. MightySat
specs 68.6cm x 88.9 cm x 88.9 cm, 125 Kg
(includes 37 kg payload), orbit avg. power
consumption 150 W (includes 60 W for payload). - SDL and NRL can build custom SVs in-house, and
provide them in under a year if the sensor is
simple. Schedule is highly dependent on sensor
selected.
38Future S/C Capabilitiesw Proper Resourcing
- AFRL/VSE working on a more capable (more payload
for the SV mass) model of MightySat called
MicroSat that is not yet available. - NRL/NCST is working with the Office of Force
Transformations Operationally Responsive Space
Experiment Initiative to provide a rapid,
tailored, and operationally relevant experimental
space capability to tactical forces. This
includes a standard micro-satellite bus,
interfaces, and a modular payload capability. - Within 2 months, SDL will be prepared to do a
full EMI/EMC test
39Current LV Capabilities
- RSLP is only provider in Alliance for launch
vehicles, launch analysis, integration
facilities. No current process for manifest of
secondaries exists. - Current OSP-2 contract with Orbital Sciences
provides Minotaur and Peacekeeper in negotiated
configuration only (task order contract).
Minotaur available 18 mos from money received to
launch
- OSP-2 Peacekeeper
- Capability 1030 Kg to 400nm, 99 inclination
- Approx payload envelope
- OSP Minotaur
- Capability 335 Kg to 400nm, 99 inclination
- Approx payload envelope
19
35
31
53
60
40
48
122
48
81
40Launch Vehicle Payload Volume Comparison
Minotaur
PK SLV
PK SLV (14.3 m3 507 ft3)
Minotaur (1.95 m3 69 ft3)
41Future LV Capabilities
- RSLP is only LV provider in Alliance
- RSLP is putting together own pitch for SMC chain
to offer quicker launches, if 4M is invested up
front. RSLP will take money and develop LV up to
certain point and freeze - could shorten launch
schedule to as short as 6-months. - Launch opportunities for secondaries
multi-payload adaptor and large payload fairing
for Minotaur are qualified and ready, but have
not flown (will fly in 05). 2 multi-payload
adaptors and a large payload fairing for
Peacekeeper in work. - Hope to have new Spaceports contract up in 2
years to provide access to VAFB, CCAS, WFF, and
Kodiak
42Current Operations Capabilities
- RDSMO has a ground system facility permitting
dynamic reconfiguration based on customer
requirements - In-house development or Customer delivered
equipment - Operations staff (cost shared with other programs
to the extent possible) - High and low level redundancy for aggregate
99.65 internal availability and 97 using the
AFSCN - NRL has a permanent control center (Blossom
Point) with mobile antennas and fixed antennas
inside and outside CONUS. - On-orbit payload data processing performed by
SAIC and MRC contractors for AFRL/VSE. - SDL has payload data reduction and analysis
capability. - LANL has two autonomous ground stations, LANL and
University of Alaska, Fairbanks for highly
inclined orbits. LANL also has the DPAC or the
highly sophisticated data processing center that
has been used by MTI that could be adapted.
43Miscellaneous RRS Notes
- Benefits of an Alliance vice Sole Source
- Increase sponsor commitment
- Enhance Personnel Retention and growth
- Influence RD Mission Design Requirements
- One-stop shop for RD Responsive Space
- Streamline Interfaces
- Identify Holes in our RD Responsive Space
Options - Alliance BOD must be a formal organization
authorized and validated - Requirement for Board Member
- Technically knowledgeable on their organizations
offering and able to get authority to commit - Able to make decisions about the acceptance of a
project to the RD Responsive Space - Must have TRUST
- Project/Program/Mission Manger
- Must be very experienced and able to handle
interfaces between organizations.