Title: 2001 Winter Presentation
12001 Winter Presentation
2Site Location
3Site View
4Site History
1923
Boston Improved Sewage
1972
1968
5Site Constraints
- Peninsula, surrounded by water
- Area of in-filled land
- Winter snow
6Engineering Constraints
- Soil Properties
- Compactable Soil
- 4000 psf bearing capacity
- Capacity, silt/clay and sand mixture
- 20 water table
- Loading
- Live Load 50 psf
- Dead Load 70 psf
- Wind Load 35 psf
- Roof Load 28 psf
7Budget Information
8Architects Vision
air
With a clear understanding of the historical
influences of site, the land, the harbor, the
history of Boston
light
water
sewage
A Machine Of Flow
movement
9Architectural Design 1 (Redesign)
- Keep the integrity of the DOME
- Allow open center to remain
- Evaluate programmatic functionality
- Relocate sloped floor rooms to basement level for
ease of constructability of slabs
10Architectural Design 1 (Redesign)
11Engineering Design 1 Steel (Redesign)
- Composite steel design
- Regular column grid
- Easy installation
- Steel moment frame
Typical Beam W14X26 c1 Moment Frame W16X36
12Design 1 Steel Estimate (Redesign)
13Engineering Design 1 Precast (Redesign)
- 12 masonry wall
- 24 deep precast concrete girders
14Design 1 Precast Estimate (Redesign)
15Design 1 Schedules
- Finish Dates
- Steel - 09/28/16, Precast - 10/05/16
- Durations
- Steel 8 mo 4 wks, Precast 9 mo
Precast
Steel
16Architectural Design 2
- Concepts
- Flow like the waves of the bay
- Structure like the hull of a boat
- Gesture towards the historic influence of the
site - Open walls towards the oak trees
- Individuality between faculty and students
17Architectural Design 2
Auditorium Classrooms, seminar rooms,
labs Student offices Faculty offices, facilities,
administration
18Engineering Design 2 Steel
- Gravity System
- Composite steel design
- No truss for auditorium
Typical Beam W14X30 Typ Girder W24X55 Typ Col
W12X40 Auditorium beam w24X76
19Engineering Design 2 Steel
- Steel bracing
- Tube 3X3X1/4
- Foundation layout
- Strip spread footings
20Design 2 Steel Estimate
21Engineering Design 2 Precast
- Concrete gravity system
- Load bearing wall, 2-way slab
- 48 post-tensioned girders
22Engineering Design 2 Precast
- 12 masonry walls
- Load path
- Foundation layout
- 3 wide strip footing
23Design 2 Precast Estimate
24Design 2 Schedules
- Finish Dates
- Steel - 09/14/16, Precast - 09/21/16
- Duration
- Steel 8 mo 2 wks, Precast 8 mo 3 wks
Precast
Steel
25Architectural Design 3
- Concepts
- Box in a box
- Simple, double structure
- Advantageous use of sloped classroom and
auditorium floors
- Flow of light to below grade level
- Exterior wood structure to gesture towards trees
26Architectural Design 3
Auditorium Classrooms, seminar rooms,
labs Student offices Faculty offices, facilities,
administration
27Architectural Design 3
28Engineering Design 3 Steel
Inside Frame Plan
Gravity System
Steel Bracing Tube 3x3x1/4
29Engineering Design 3 Steel
Outside Frame Plan
Flat Roof
Steel Knee Brace Frame
30Design 3 Steel Estimate
31Engineering Design 3 Wood
Inside Frame Plan
Wood Wall Lateral System
Gravity System
32Engineering Design 3 Wood
Outside Frame Plan
Pre-fabricated wood truss with knee brace
Prefab wood truss 2"X6" Column 12"DIA Knee brace
2"X6" Joist 2"X4" Steel Brace 12"X2"
33Engineering Design 3 Wood
Outside Structure Load Path
Gravity Load
Lateral Load
34Engineering Typical Connection
Wood With Steel Plate Bolts
Steel Bracing
35Design 3 Wood Estimate
36Design 3 Schedules
- Finish Dates
- Steel - 08/24/16, Wood - 09/07/16
- Durations
- Steel 7 mo 3 wks, Wood 8 mo 1 wk
Wood
Steel
37Equipment Selection
Truck Crane
Mini Excavator
Skid Steer Loader
38Budget Comparison
39Design Evaluations
40Decision Matrix
Explanation of design rankings
1Best6Worst
Lowest point total wins
41Design Choice
- Design 3
- Best combination of strengths vs. weaknesses were
3W 3S from matrix - Wood/Steel Hybrid
- Combine the attractiveness/interest of 3W with
the cost and schedule benefits of 3S - Keep wood exterior structure of 3W, but
incorporate the steel interior structure of 3S
42Team Dynamics/Interaction
43Team Dynamics/Interaction
The most challenging and the most successful
part of this whole process is the perpetual
learning of our own and each others discipline
and how we must collaborate in order to succeed.
The structural system is not the only aspect of
the building. We need to think about the others'
intentions and constraints. Compromising between
different intentions is very important in
developing a successful project.
The greatest thing we will take away from this
class is learning how to successfully work in a
challenging situation with diverse people on a
project with little contact.
44Lessons Learned
- Cross-Discipline Knowledge
- Vocabulary
- Interests/Concerns
- Teamwork
- Tolerance
- Dependence/Collaboration
- Organization/Work Habits
- Technology
- New Applications
452001 Winter Presentation
Questions?