2001 Winter Presentation - PowerPoint PPT Presentation

1 / 45
About This Presentation
Title:

2001 Winter Presentation

Description:

2001 Winter Presentation Site Location Site View Engineering Constraints Soil Properties Compactable Soil 4000 psf bearing capacity Capacity, silt/clay and sand ... – PowerPoint PPT presentation

Number of Views:35
Avg rating:3.0/5.0
Slides: 46
Provided by: pblStanfo
Learn more at: http://pbl.stanford.edu
Category:

less

Transcript and Presenter's Notes

Title: 2001 Winter Presentation


1
2001 Winter Presentation
2
Site Location
3
Site View
4
Site History
1923
Boston Improved Sewage
1972
1968
5
Site Constraints
  • Peninsula, surrounded by water
  • Area of in-filled land
  • Winter snow

6
Engineering Constraints
  • Soil Properties
  • Compactable Soil
  • 4000 psf bearing capacity
  • Capacity, silt/clay and sand mixture
  • 20 water table
  • Loading
  • Live Load 50 psf
  • Dead Load 70 psf
  • Wind Load 35 psf
  • Roof Load 28 psf

7
Budget Information

8
Architects Vision
air
With a clear understanding of the historical
influences of site, the land, the harbor, the
history of Boston
light
water
sewage
A Machine Of Flow
movement
9
Architectural Design 1 (Redesign)
  • Keep the integrity of the DOME
  • Allow open center to remain
  • Evaluate programmatic functionality
  • Relocate sloped floor rooms to basement level for
    ease of constructability of slabs

10
Architectural Design 1 (Redesign)
11
Engineering Design 1 Steel (Redesign)
  • Composite steel design
  • Regular column grid
  • Easy installation
  • Steel moment frame

Typical Beam W14X26 c1 Moment Frame W16X36
12
Design 1 Steel Estimate (Redesign)
  • Total 3,145,000

13
Engineering Design 1 Precast (Redesign)
  • 12 masonry wall
  • 24 deep precast concrete girders

14
Design 1 Precast Estimate (Redesign)
  • Total 3,231,000

15
Design 1 Schedules
  • Finish Dates
  • Steel - 09/28/16, Precast - 10/05/16
  • Durations
  • Steel 8 mo 4 wks, Precast 9 mo

Precast
Steel
16
Architectural Design 2
  • Concepts
  • Flow like the waves of the bay
  • Structure like the hull of a boat
  • Gesture towards the historic influence of the
    site
  • Open walls towards the oak trees
  • Individuality between faculty and students

17
Architectural Design 2
Auditorium Classrooms, seminar rooms,
labs Student offices Faculty offices, facilities,
administration
18
Engineering Design 2 Steel
  • Gravity System
  • Composite steel design
  • No truss for auditorium

Typical Beam W14X30 Typ Girder W24X55 Typ Col
W12X40 Auditorium beam w24X76
19
Engineering Design 2 Steel
  • Steel bracing
  • Tube 3X3X1/4
  • Foundation layout
  • Strip spread footings

20
Design 2 Steel Estimate
  • Total 2,722,000

21
Engineering Design 2 Precast
  • Concrete gravity system
  • Load bearing wall, 2-way slab
  • 48 post-tensioned girders

22
Engineering Design 2 Precast
  • 12 masonry walls
  • Load path
  • Foundation layout
  • 3 wide strip footing

23
Design 2 Precast Estimate
  • Total 2,800,000

24
Design 2 Schedules
  • Finish Dates
  • Steel - 09/14/16, Precast - 09/21/16
  • Duration
  • Steel 8 mo 2 wks, Precast 8 mo 3 wks

Precast
Steel
25
Architectural Design 3
  • Concepts
  • Box in a box
  • Simple, double structure
  • Advantageous use of sloped classroom and
    auditorium floors
  • Flow of light to below grade level
  • Exterior wood structure to gesture towards trees

26
Architectural Design 3
Auditorium Classrooms, seminar rooms,
labs Student offices Faculty offices, facilities,
administration
27
Architectural Design 3
28
Engineering Design 3 Steel
Inside Frame Plan
Gravity System
Steel Bracing Tube 3x3x1/4
29
Engineering Design 3 Steel
Outside Frame Plan
Flat Roof
Steel Knee Brace Frame
30
Design 3 Steel Estimate
  • Total 3,083,000

31
Engineering Design 3 Wood
Inside Frame Plan
Wood Wall Lateral System
Gravity System
32
Engineering Design 3 Wood
Outside Frame Plan
Pre-fabricated wood truss with knee brace
Prefab wood truss 2"X6" Column 12"DIA Knee brace
2"X6" Joist 2"X4" Steel Brace 12"X2"
33
Engineering Design 3 Wood
Outside Structure Load Path
Gravity Load
Lateral Load
34
Engineering Typical Connection
Wood With Steel Plate Bolts
Steel Bracing
35
Design 3 Wood Estimate
  • Total 2,978,000

36
Design 3 Schedules
  • Finish Dates
  • Steel - 08/24/16, Wood - 09/07/16
  • Durations
  • Steel 7 mo 3 wks, Wood 8 mo 1 wk

Wood
Steel
37
Equipment Selection
Truck Crane
Mini Excavator
Skid Steer Loader
38
Budget Comparison
39
Design Evaluations
40
Decision Matrix
Explanation of design rankings
1Best6Worst
Lowest point total wins
41
Design Choice
  • Design 3
  • Best combination of strengths vs. weaknesses were
    3W 3S from matrix
  • Wood/Steel Hybrid
  • Combine the attractiveness/interest of 3W with
    the cost and schedule benefits of 3S
  • Keep wood exterior structure of 3W, but
    incorporate the steel interior structure of 3S

42
Team Dynamics/Interaction
43
Team Dynamics/Interaction
The most challenging and the most successful
part of this whole process is the perpetual
learning of our own and each others discipline
and how we must collaborate in order to succeed.
The structural system is not the only aspect of
the building. We need to think about the others'
intentions and constraints. Compromising between
different intentions is very important in
developing a successful project.
The greatest thing we will take away from this
class is learning how to successfully work in a
challenging situation with diverse people on a
project with little contact.
44
Lessons Learned
  • Cross-Discipline Knowledge
  • Vocabulary
  • Interests/Concerns
  • Teamwork
  • Tolerance
  • Dependence/Collaboration
  • Organization/Work Habits
  • Technology
  • New Applications

45
2001 Winter Presentation
Questions?
Write a Comment
User Comments (0)
About PowerShow.com