Title: Recovery and Purification of HFC by Distillation
1Recovery and Purification of HFC by Distillation
- Ramin Afrasiabi
- Tony Calabria
- John OBrien
- Chemical Engineering 160
- November 28th, 2000
BIG-D Chemicals
2Motive for Project
- Chlorine atoms from CFCs induce the decomposition
of ozone (O3) in the stratosphere. - Replacement of the ozone-destroying CFCs
refrigerants with the environmentally-friendly
HFC-125 refrigerant.
3Project Background
Design Project Focus
HCl
Reactor Effluent, Feed to Distillation Train
Series of Distillation Columns
Feed to Upstream Reactor
Reactor
HFC-125
CFC-115
4Project Goals
- Design Conventional and Extractive Distillation
Processes to Recover HFC-125, CFC-115, and HCl. - Compare Economics of Two Competing Processes
- Recommend Cost-Efficient Scheme Based on Economic
Results
BIG-D Chemicals
5Project Timeline
-Preliminary Database Creation
08/00
-Determined Mass and Energy Balance Requirements
using Aspen Tech Simulator
09/00
-Equipment Sizing
10/00
-Calculated Fixed and Variable Costs
11/00
-Profitability Analysis
11/00
-Commence Plant Construction
01/01
-Project Completion/Commissioning
12/02
-Salvage Plant
12/15
6 Conventional Distillation for HFC Recovery
HCl Product
Raw Feed
HFC Product
BIG-D Chemicals
Feed to T-202
CFC Product
7Extractive Distillation For HFC Recovery
HFC Product
HCl Product
Extractant Feed
Raw Feed
CFC Product
Extractant Recycle
BIG-D Chemicals
8Equipment Sizing
- Unit Operations
- Distillation Towers
- Compressors
- Pumps
- Condensers
- Reboilers
- Pressure Vessels
- Sized Using Aspen Simulation Results
9Sizing Heat Exchangers
- Modeled using LMTD
- Input (from Aspen)
- Heat Duty
- Hot, Cold Temperatures
- Appropriate Materials
- Output
- Overall HTC (U)
- tubes / pass
- HT Areas
- Dimensions
10Equipment Cost Analysis
CBM f (equipment size, operating pressure,
material of construction)
Extractive
Conventional
- CBM includes
- Equipment Purchase Cost
- Materials
- Labor
11Variable Cost Analysis (Scheme I)
12Profitability Analysis
- Purpose To Determine
- Extractive Conventional
- Fixed Cost Variable Cost lt
Fixed Cost Variable Cost - Calculated
- - Earnings (S COS D taxes)
- - Annual Cash Flow
- - Net Present Value _at_ 15
- Cash Flow Discounted To Present Worth
- Sum of Discounted Cash Flows NPV
13Bottom Line
- NPV Calculated
- Over 15 Years
2015 NPV for Scheme II is 2.5 MM greater than
Scheme I
14Recommendation / Future Plans
- Scheme II Promises Greatest Economic Potential
- Submit Plant Design for Contractor Bid (Dec.
2000) - Commence Plant Construction (Jan. 2001)
- Commission Plant Addition (Dec. 2002)
15Acknowledgments
- Professor Wallman
- Professor Lynn
BIG-D CHEMICALS