Title: 1 of 25
1Kansas City District
- FORT RILEY
- MILITARY PROGRAM HIGHLIGHTS
- OCTOBER 10 2007
2(No Transcript)
3Master Plan
4-1 BCT Permanent 193M / FY 12-13 Brigade,
battalion COFs 11 barracks
Div Hq/Sust Bde 178M / FY 06-07 Div
Headquarters Barracks Bde and Bn area
2/1 BCT Permanent 69M / FY09
1/1 BCT Permanent 30M / FY10
CAB Phase 1, 152M / FY 07 Phase 2, 109M / FY
08 Phase 3, 46M / FY 11 Barracks Airfield
facilities
Echelon Above Bde 10th ASOS 12M / FY 08 MP Bn
31M / FY 09 Engr Bn 37M / FY 12
Runway Repairs 17M / FY 07
ORTC PH II 27.5M / FY 11
Waste Water Plant 16.5M / FY 09
Hospital Addn/Renov 28M / FY 09
4Brigade Footprints (General Locations)
3BCT (2/1 BCT)
4
4BCT
NON-DIV UNITS
1BCT
5BLDG 8300 MIL POL
Brigade Footprints
BLDG 7630 CAB HQ
BLDG 7803 DISCOM
BLDG 7620 CAB HQ
BLDG 7622 DISCOM
BLDG 7788 (2 COF) CAB
BLDG 7808 DISCOM
BLDG 7608 (3 COF) CAB
BLDG 7450 DISCOM
BLDG 7432 (3 COF) CAB
BLDG 7740 DIV/DISCOM
BLDG 7780 CAB
3BCT
4
BLDG 7434 CDC ADMIN
4BCT
BLDG 7520 CAB
NON-DIV UNITS
BLDG 7410 DOC
BLDG 7350 CAB
BLDG 7270 BAND
1BCT
BARRACKS 7647/49
BLDG 7220 EOD
7610
BLDG 7173 EOD
7224/27
DBL COF EOD
7818
6MARSHALL ARMY AIRFIELD
- DOL Trlrs
- DOL CONTRACTORS
BLDG 710 FUEL TRKS LCT
LCT/AVCATT PADS BLDG
BN HQ, 2 DBL COF, BSB COF GSAB
BLDG 720 POL PLTS
Warehouse KSARNG
BLDG 722 2-1 GSAB
2 SPRUNG Shelters GSAB
BLDG 727 2-1 GSAB
BLDG 808 3-1 AVN
BLDG 725 2-1 GSAB
BLDG 723 2-1 GSAB
FUEL STORAGE
BLDG 804 601 ASB BN
BLDG 835 AVN UNIT OPS
BLDG 802 1-1 ATK
BLDG 853 3-1 AVN
BLDG 833 601st ASB
2 Tension Shelters ASB
BLDG 817 1-1 ATK
BLDG 810 4 COF
BLDG 820 601st ASB SSA
BLDG 840 ASB
BLDG 812 5 COF
3 DBL COF, SHOWER
BLDG 814 TMC
7On Going Projected Construction
Custer Hill Div HQs Air Support Opns Sqdn
Facility Bde and Bn HQs Company Ops
Facilities Maintenance Facilities Barracks Unmanne
d Aerial System Facility Health Dental
Clinic Child Development Center Access Control
Building Retail Fuel Point
Camp Funston Deployment Support Facility Site
Prep ORTC Enlisted Barracks Railhead
Facilities Military Working Dog Facility
Whitside Barracks Child Development
Center Hospital Addition / Alteration Physical
Fitness Facility Warrior Transition Unit
Marshall Army Airfield Bde and Bn HQs Company
Operations Facilities Maintenance Hangars Runway
Improvements DOC Admin / TSB / LSB
Facilities Dining Facility
Camp Forsyth Fire Station AFH Chapel CDC x
2 PX Commissary Addition
Family Housing Areas AFH Custer Hill Camp
Forsyth RCI
Historic Main Post Bldg Renovation ACP
Improvements
8MASTER PLAN MISSION FACILITIES
FY06 Div Hq/Sust Bde Ph1
FY07 Div Hq/Sust Bde Ph 2 CAB Ph 1 Runway
Repairs Barracks Complex w/COF Unit Ops
Facilities
FY08 CAB Ph 2 Unit Ops
Facilities Barracks 10th ASOS Ops Facilities
FY09 Unit Ops Facilities Battalion
Complex Bde Complex 2/1 BCT
FY10 Bde Complex 1/1 BCT
FY11 CAB Bn Complex
FY12 BCT Complex 4-1 BCT Ph
1 Vehicle Maintenance Shops Engineer Combat Bn
FY13 Bde HQs Bldg Ph 2 4-1 BCT
9MASTER PLAN -- COMMUNITY AND HOUSING FACILITIES
FY 07 Health Clinic Child Dev Ctr Child Dev
Ctr Shopping Ctr
FY 08 Child Dev Ctr Health and Dental
Clinic Commissary Addn
RCI Construction
FY09 Hospital Addn/Renov
FY10 Waste Water Plant
FY 11 Access Control Building Chapel w/Rel
Ed Community Activity Center Fire Station
FY 12 Fitness Ctr Addn
10MASTER PLAN - RANGE AND TRAINING LANDS
FY 06 Digital MPTR
FY 07 Battle Command Training Ctr
Tank, Bradley Gunnery Range Aerial
Multi-Purpose Ranges
FY 08 Digital MPRC
FY 10 Shoot House Training Support Center Igloo
Storage Infantry Platoon Battle Course Fire and
Movement Range Infantry Squad Battle Course
Small Arms Ranges
Manhattan
Impact Area
Manhattan Airport
FY 11 Enlisted Barracks, Transient Training
Ogden
FY 12 Mil Working Dog
Cantonment Area / Airfield / Close In Training
FY 13 Known Dist Range Qualification Training
Range
Junction City
11MASTER PLAN - STRATEGIC MOBILITY
Manhattan Airport 2 miles
FY 06 Ramp - Manhattan Airport Alert Holding
Facility Deployment Spt Facility
FY08 Fuel Facilities
FY09 Fuel Facilities Rail Siding
Improvements
UPRR
FY 10 Pallet Processing Facility Airfield Control
Group Ops Forbes Field
Forbes Field, Topeka 65 miles
12Division / Sustainment Bde HQs
Project 63983 APPN BCA5 CWE 178,000 FY
06 91,000 (1st Phase Div HQs Bde HQs) FY
07 87,000 (2nd Phase Band Facility 4 Co COF
2 Co COF Div Tac Equip Fac Bde Trps Bn TEM
Facility Div STB BTB TEM) Description
51.5M -- 135K SF 3 Story Command HQs (includes
furniture modern technology in Battle Cmd Post
w/ Satellite Systems) 73.5M -- Custer Hill
Beddown Facilities 8 Facilities site work c/o
55K SF Bde HQs Band Facility (8610) Bn HQs
(8612 8616) COF (8630 8632) Vehicle Maint
(8650 8660) (Pre-engiineered) 44.6M -- 3
Barracks (Bldgs 7492, 7494, 7496 -- 468 spaces)
and substation (Bldg 7678) -- 06 Barracks 11M
-- DFAC (at Whitside) 9.9M -- Williston
Point Road
15 Nov 08 SUA Bde HQ Completion
Milestones
Issues / Concerns
26 Oct 08 Band Trng Fac, Bn Qd, COFs, TEMs, Org
Veh Pkng, Storage Completion
1 Nov 08 SUA DFAC _at_ Whitside Completion
4 Contracts 4 Awarded 9.9M placeholder for
Williston Point Road 34.5M SUA Custer Hill
Barracks 3 Barracks (420 Days) Complete 26
Dec 07 5 Jan 08 15 Jan 08
17 Feb 08 -- Bldg 7496 Complete
7 Feb 08 -- Bldg 7494 Complete
28 Jan 08 -- Bldg 7492 Complete
16 Nov 07 Div HQ Construction Completion
14 Jun 07 --SUA Bde HQ Construction Start
6 Mar 07 NTP SUA HQs
15 Feb 07 Inc 2 Contract Awarded
15 Aug 06 Inc 1 Contract Awarded
11 Aug 06 NTP
Building Acceptance
29 Mar 06 NTP DIV HQs
13CAB Complex Phase I
Project 63981 APPN BCA5 FY 07
152,000 CWE 152,000 Description 5.22M --
Aircraft Crash/Rescue (709), Unit Base Ops (744),
ECP 55M Southside 10M 3 Bn
HQs(ASB BN HQ, GSAB BN HQ, ...) 26M --
GSAB Aircraft Maintenance Hangar GSAB COF
(863A) GSAB Washrack Aircraft Maintenance
Parking Apron Aircraft Fueling Apron Admin
Facility 12M -- 2 5-COF Atk Bn (817A),
Aslt Bn (853A) 59M -- 4 Barracks (Whitside)
1 from PN47149) 8.2M -- DOC (1792) / TSB
LSB (1807) _at_ Funston (vs Ph 2???)
Feb 09 -- Airfield Construction Complete
Milestones
Issues / Concerns
Feb 09 -- BOD / Construction Completion 5th
Barracks
48 Storm Sewer Line Under Crash Rescue Base Ops
-62 Days Float Need Recovery Schedule
2 Oct 08 -- BOD / Construction Completion
Aircraft Crash Rescue
15 Sep 08 -- DOC TSB/LSB Construction Complete
3 Jul 08 -- BOD / Construction Completion 1st
Barracks
24 Apr 07 -- DOC TSB/LSB NTP
11 May 07 -- Aircraft Crash Rescue NTP
149M Received Task Order 1 94M Avn Unit Ops
deleted from Scope Increment increase by 50M.
Can add additional from 08 to 07.
29 Mar 07 -- Aircraft Crash Rescue Contract
Awarded
13 Apr 07 NTP S. Side, Runway
14CAB Complex Phase II
Project 65775 APPN BCA5 FY 08 109M CWE
109M Description 36M Southside
Facilities 4M -- 19,759 SF Bde HQ
Addition --Bldg 804 2M -- 2 Bn HQ Adds
(4585 SF per) Bldgs 802/808 4M --
38,712 SF COF Renovation-Bldgs 810/812
13M -- Aircraft Maintenance Hangar/COF (58.9K
SF) Bldg 837 and 9333 SY Aircraft Apron
13M -- AVIM Hangar Maintenance Apron 9M
12K SF DFAC with Drive Thru on MAAF 11M 1
Barracks (6th Barracks at Whitside) FY07 3M
TSBn/LSB Vehicle Maint Shop -- Funston 4.6M
12K SF Engr Maintenance Shop, 3500 SF Deployment
Storage Facility, and 10K SF Admin/Shop
Control 50M Northside Facilities??
12M 1-4COF 7M 1-2 COF
16M 4 TEMFs 11M
Org Pkng 2M 4 Unit Storage -- 13K
SF Avn Unit Ops Fac (830A) Electrical Sub
PH1?? -- Access Control Facility TSBn/LSBn
-- see Ph1
Milestones
Issues / Concerns
01 Jun 09 All Other Southside Facilities BOD
11 Feb 09 BOD Veh Maint COFs
Add Avn Unit Ops (Bldg 830A) to Phase
2 Reduced Increemnt by 50M forward funded in
FY07 45.5 North Side??
15 Feb 09 DFAC BOD
15 Nov 08 Bldg 808, 810, 812 BOD
Construction Start
1 Dec 08 -- 1- 4 COF BOD
15 Nov 07 DFAC Const TO Awarded
1 Oct 07 DFAC RFP Issued
20 Sep 07 NTP Veh Maint COFs
Contract Awarded