Title: Application of Digital Relay Protection on APUA T&D Network
1Application of Digital Relay Protection on APUA
TD Network
Presented by
- Li Zhengrong Substation Maintenance
Protection Engineer - Andre MatthiasDivision Manager
- Electricity/ transmission Distribution Division
- Antigua Public Utilities Authority
- July 23-25, 2002
- 2002 Carilec Engineers Conference
- Montego Bay, Jamaica
2Application of Digital Relay Protection on APUA
TD Network
KEY WORDS
-
- Application Digital Relay Protection
- Communication Software Workstation
- 69kV Lines 11kV Feeders
31.General information
1.1 Introduction of APUA electric power system
- The total installed generation capacity is 64.5MW
and the present peak load is 34.8MW - Eight (8) 69kV transmission lines operating in
close-ring are 59.2kM in length - Twenty-two (22) 11kV feeders radiating and
covering entire Island are 539kM in length - Twelve (12) 69/11kV power transformers at seven
(7) step-up/-down substations possess a total
installed capacity of 160.34MVA.
41.General Information
1.2 . Requirement for relay upgrade
- 1.2.1 11kv primary feeders
-
- a. Under-frequency protection feature for
load-shedding - b. One-shot re-closing
- c. fuse-saving scheme
51.General Information
1.2 . Requirement for relay upgrade (continued)
- 1.2.2 69kv transmission lines
- a. eliminate protection dead zones
- b. reduce duration of faults on power system
- c. prevent equipment damage
- d. differentiate max. load current from min.
fault current - e. avoid misoperation of current balance
protection.
61.General Information
1.3 Relay protection upgrade project
- Replacing electromagnetic distance relay
protections on 69kv transmission lines with 351
digital relays was done in 2000 - Replacing electronic relays on 11kv feeders with
DFP-100 and 351/551 digital relays was done in
2001 - Replacing differential relays on 69/11kv power
transformers with SEL-587 relays is in progress. - The entire upgrade project that was from project
design, settings calculation to relay
programming, installing and testing, was carried
out by APUA staff.
72. Application of Digital Relays on 11kV Primary
Feeders
2.1 Fundamental Protection Feature
- 2.1.1 Phase-to-phase protection(positive-sequence
protection 50P) - Instantaneous over-current with time-delay(50PH )
- Time-definite over-current (50PL)
- 2.1.2 Earth fault protection (zero-sequence
protection 50N) - Time-definite zero-sequence over-current (50N)
- 2.1.3 Under-frequency protection for
load-shedding (81U1,81U1T) - 2.1.4 re-closing
- One-shot re-closing (SH0) is activated only under
phase-to-phase fault
82. Application of Digital Relay on 11kV Primary
Feeders
2.2 Definition of protection zone
- Phase-to-phase protection(50P)
- Instantaneous over-current with time-delay(50PH),
protects entire primary feeder and primary side
of distribution power transformers - Time-definite over-current (50PL) as backup
protection of 50PH and fuse links, protects
entire primary feeder and both sides of
distribution transformers. - Protection zone is shown in Figure 1 .
-
92. Application of Digital Relay on 11kV Primary
Feeders
2.2 Definition of protection zone (continued)
Solid link
Relay
Fuse link 1
Fuse link 2
Fuse link 3
50PH
50PL
Figure 1 phase-to-phase over-current protection
102. Application of Digital Relays on 11kV Primary
Feeders
2.2 Definition of protection zone (continued)
- B. Earth fault protection(50N)
- Time-definite zero-sequence over-current (50N) as
backup protection of fuse links, protects entire
primary feeder and primary sides of distribution
transformers under earth fault circumstance. - Protection zone is shown in Figure 2 .
-
112. Application of Digital Relay on 11kV Primary
Feeders
2.2 definition of protection zone (continued)
Relay
Solid link
Fuse link 2
Fuse link 1
50NH
Figure 2 earth-fault protection
122. Application of Digital Relay on 11kV Primary
Feeders
2.2 Definition of protection zone (continued)
- C. Fuse link protection
- Fuse link immediately clears faults on both sides
of protected distribution transformer - Fuse link clears faults on protected branch of
primary line. - Protection zone is shown in Figure 3.
-
132. Application of Digital Relay on 11kV Primary
Feeders
2.2 definition of protection zone (continued)
Fuse link 2
Relay
Solid link
Fuse link 1
Fuse link 3
Figure 3 protection zone of fuse link
142. Application of Digital Relay on 11kV Primary
Feeders
2.3. The trip-saving scheme
- Fuse link
- Fuse link blows out first to clear faulted
branch or distribution transformer - B. Phase-to-phase protection(50P)
- Instantaneous over-current with time-delay(50PH)
acts as backup protection for fuse links - Time-definite over-current (50PL) performs as
remote backup protection for both 50PH and fuse
links.
152. Application of Digital Relay on 11kV Primary
Feeders
2.3 The trip-saving scheme (continued)
- C. Earth fault protection(50N)
- Time-definite zero-sequence over-current (50N)
acts as backup protection for fuse links. - D. One-shot reclosing (SH0)
- One-shot reclosing is activated under
phase-to-phase faulty condition -
- (Notice Consider to avoid a human being or an
animal to be shocked twice while carelessly
touching a live conductor one-shot re-closing is
replaced by manual re-closing under earth fault
circumstance).
162. Application of Digital Relay on 11kV Primary
Feeders
2.4 The fuse-saving scheme
- Phase-to-phase protection(50P)
- Instantaneous over-current without
time-delay(50PH) will immediately clear fault and
then be locked by one-shot re-closing after
circuit-breaker tripping. - After 5 seconds, the feeder will be closed by
one-shot re-closing successfully if the temporary
fault disappears at once - The permanent fault area will be isolated by
related fuse link from entire feeder, or
time-definite over-current (50PL) trips entire
feeder - B. Earth fault protection(50N)
- Functions as same as that in the trip-saving
scheme -
172. Application of Digital Relay on 11kV Primary
Feeders
2.5 Recorded trips of 11kv feeders
-
- Date December 13, 2001
- Cause a freak storm
- Total tripped Feeders 11
- Total trip times 19
-
- Phase-to-ground fault 1 temporary
- Phase-to-phase fault 18 (12 temporary 6
permanent)
182. Application of Digital Relays on 11kV Primary
Feeders
2.6 Under-frequency protection for load-shedding
- a. Under-frequency protection with under-voltage
supervision -
- Use under-frequency trip (81UT) with
under-voltage supervision(27U) logic to
eliminate unnecessary trip under phase-to-phase
fault. -
- The trip logic is programmed as
trip81UT!27U -
- b. Circulatory change of trip sequence
- The different under-frequency settings and same
over-current settings can be preset in each of 6
groups for circulatory change of trip sequence by
activating certain settings group.
193. Application of Digital Relay on 69KV
Transmission lines
3.1 Protection Feature
- 3.1.1 Phase-to-phase protection
(positive-sequence protection 50P) - Directional instantaneous over-current without
time-delay(Zone one 67P1) - Directional instantaneous over-current with
time-delay (Zone two 67P2) - Directional time-definite over-current protection
(Zone three 67P3) -
203. Application of Digital Relay on 69KV
Transmission lines
3.1 Protection Feature (continued)
- 3.1.2 earth fault protection(zero-sequence
protection 50N) - Directional instantaneous over-current without
time-delay(Zone one 67N1) - Directional instantaneous over-current with
time-delay (Zone two 67N2) - Directional time-definite over-current protection
(Zone three 67N3) - Directional time-definite over-current protection
for phase-loss supervision (Zone four 67N4) - Zero-sequence over-voltage with time-delay (59N)
as a complement
213. Application of Digital Relay on 69KV
Transmission lines
3.1 Protection Feature
-
- 3.1.3 re-closing
- Synchronize-check (25A) or non-voltage check
(27S) to initiate re-closing - One-shot re-closing (SH0) is activated only under
phase-to-phase fault
223. Application of Digital Relay on 69KV
Transmission lines
3.2 Clockwise /Anticlockwise Coordination Route
TmaxOLD2.60Seconds TmaxNOW1.85Seconds
TmaxOLD2.60Seconds TmaxNOW1.85Seconds
13
11
7
8
9
12
14
10
15
Cassada
G
G
G
G
G
G
G
Crabbs
Friars Hill
K3
1
3
2
4
5
6
16
Swetes
Union Road
Lavington
Belmont
Figure 4 Clockwise in blue starts at 1 CB and
ends at 11/13 C.B Anticlockwise in red starts
at 10/12 and ends at 14 C.B
233. Application of Digital Relay on 69KV
Transmission lines
3.3 Reduce Duration of Fault Clearing
- The recommended time difference between adjacent
relays is 0.4-0.6 Seconds for electromagnetic
relays and 0.25-0.3seconds for digital/
electronic relays - The maximum time setting was coordinated as 2.60
seconds for previous electromagnetic distance
relays numbered 11,13 and 14, and that for SEL
digital relay protections at same location is
1.85seconds. - The net decrease of time settings between two
kinds of protections is 0.75seconds.
242. Application of Digital Relay on 69KV
Transmission lines
3.4 Eliminate protection dead zone
- 3.4.1 Zero-sequence over-voltage (59N) as a
complement at some lines while close-ring of
transmission lines is opened at some certain
point - Case A CB 1 opens (see Figure 5)
- Case B CB 9 opens (see Figure 6)
- 3.4.2 distinguish maximum load current ILD from
minimum fault current IF at 69kV section breaker
15 by load-encroachment Logic (see Figures
78) -
253. Application of Digital Relay on 69KV
Transmission lines
3.4 Eliminate protection dead zone(continued)
Earth fault
K(1.0)
O/V
13
11
7
8
9
12
10
14
15
YO/D
YO/D
Y/YO
Y/YO
Y/YO
Y/YO
YO/D
YO/D
Cassada
G
G
G
G
G
G
G
Crabbs
Friars Hill
1
3
2
4
Opened
5
6
16
Figure 5 Case A circuit-breaker 1 opens
263. Application of Digital Relay on 69KV
Transmission lines
3.4 Eliminate protection dead zone(continue)
Opened
8
13
11
7
9
12
10
O/V
Opened
14
15
YO/D
YO/D
Y/YO
Y/YO
Y/YO
Y/YO
YO/D
YO/D
K(1.0)
Cassada
G
G
G
G
G
G
G
K(1.0)
Crabbs
Friars Hill
K(1.0)
K(1.0)
1
3
2
4
5
O/V
O/V
6
16
O/V
Figure 6 Case B circuit-breaker 8 or 9 opens
K(1.0) -----Earth fault
273. Application of Digital Relay on 69KV
Transmission lines
3.4 Eliminate protection dead zone(continue)
IF2202A
IF58A
IF158A
K(2)
13
11
7
8
9
12
14
10
15
ILD219A
IF100A
Cassada
G
G
G
G
G
G
G
Crabbs
Friars Hill
1
3
2
4
5
6
16
Figure 7 Distinguishing IFMIN from ILDMAX at
circuit-breaker 15
283. Application of Digital Relay on 69KV
Transmission lines
3.4 Eliminate protection dead zone(continue)
X
fault
load
R
Load out
Load in
Figure 8 Distinguishing IFMIN from ILDMAX by
load-encroachment Logic
293. Application of Digital Relays on 69KV
Transmission lines
3.5 Prevent equipment damage from abnormal
condition
- 3.5.1 In the previous designs, the closing or
tripping coils or related relays were frequently
burned out by overheating when system operator
switched circuit-breaker by SCADA under following
abnormal conditions - a. Substations D.C. low-voltage (less than
70), or - b. The stuck output contact of auxiliary relay,
or - c. Mechanism jamming of circuit-breaker.
-
-
303. Application of Digital Relays on 69KV
Transmission lines
3.5 Prevent equipment damage from abnormal
condition(continued)
- 3.5.2 Measures being taken to prevent damage of
facilities - a unifying close/open (or trip) commands between
SCADA and relays - b. programming new relays and improving wiring
connection - c. programming output of close or open commands.
-
313. Application of Digital Relays on 69KV
Transmission lines
3.5 Prevent equipment damage from abnormal
condition(continued)
Protection relay
69kV circuit-breaker
SCADA System
Digital Relay
Figure 9 change of control/protection logic
323. Application of Digital Relays on 69KV
Transmission lines
3.6 Provide flexible Logic functions
- 3.6.1 Interlocking balance current protection
on 69kV double lines while single line operates
(see Figure 10) - 3.6.2 Speed-up tripping of Zone two (67P2)
while re-closing onto permanent faulted line
(see Figure 11) -
- 3.6.3 Anti-pump of circuit-breaker (see Figures
12) -
333. Application of Digital Relays on 69KV
Transmission lines
3.6 Provide flexible Logic functions (continued)
Close
Close
B/C 351
B/C 351
1
3
G1
G2
2
4
B/C 351
B/C 351
Open
Open
Output 2
Output 1
52A1
52A2
B/C trip
Trip circuit
Output1output contact of 1 351 relay
(67P2) Output2output contact of 2 351 relay
(67P2) 52A1 auxiliary contact of 1
circuit-breaker 52A2 auxiliary contact of 2
circuit-breaker B/C balance current
protection B/C triptrip contact of balance
current protection
Figure 10 Interlocking balance current protection
on 69kV double lines
343. Application of Digital Relays on 69KV
Transmission lines
3.6 Provide flexible Logic functions (continues)
67P1
Relay 1
K
Relay 2
G
67P2
67P3
Trip logic Trip 67P1T67P2T67P3T67P2\SH0
Where 67P1Ttimer of zone one (67P1)
67P2Ttimer of zone two (67P2)
67P3Ttimer of zone three (67P3)
\SH0 declining edge of one-shot reclosing
Figure 11 Speed-up tripping of Zone two (67P2)
while re-closing onto permanent faulted line
353. Application of Digital Relays on 69KV
Transmission lines
3.6 Provide flexible Logic functions (continued)
SCADA or Manual Closing command
T67P1T
Status of C.B (No logic)
TCL
TOP
Closing command With logic
TLDO
T67P1T
Status of C.B (with logic)
TCL
TOP
TOPinherent open time of circuit-breaker TCLinhe
rent close time of circuit-breaker T67P1Ttimer
of relay zone one (67P1) TLDOdrop-off timer of
logic-controlled contact (TCL T67P1T TOPgt TLDOgt
TCL)
- Figures 12 Anti-pump of circuit-breaker under
permanent faulty condition -
363. Application of Digital Relay on 69KV
Transmission lines
3.7 Provide reliable and useful data information
a. The magnitude and phase angle of three-phase
current and voltage b. Dual-directional
single/three-phase active/reactive power and
energy c. Dual-directional load flow d. Power
factor and work frequency e. DC voltage f.
Pre-fault and fault current and voltage See
downloaded data information
37 CRB-CAS 1 69KV LINE Date
05/29/02 Time 111355.618 CRABBS
SUBSTATION A B C
N G I MAG (A) 77.534
74.927 78.517 0.387 0.424 I ANG (DEG)
-35.34 -153.68 87.31 134.14 123.30
A B
C S V MAG (KV) 41.222
40.328 40.812 40.583 V ANG (DEG) 0.00
-119.97 117.52 -0.57
A B C 3P MW
2.607 2.514 2.769
7.890 MVAR 1.849 1.677 1.612
5.138 PF 0.816 0.832
0.864 0.838 LAG
LAG LAG LAG I1 3I2
3I0 V1 V2 3V0 MAG
76.978 6.342 0.424 40.779
0.334 2.551 ANG (DEG) -33.90 -105.67
123.30 -0.82 150.90 29.60 FREQ (Hz)
59.92 VDC (V)
114.8 IA IB IC
IN IG 3I2 DEMAND 77.5
74.6 78.4 0.4 0.4
6.7 PEAK 146.4 133.7 150.0
35.2 35.3 35.3
MWA MWB MWC MW3P MVARA
MVARB MVARC MVAR3P DEMAND IN 0.0
0.0 0.0 0.0
0.0 0.0 0.0
0.0 PEAK IN 0.2 0.2
0.4 0.6 0.2
0.2 1.2 1.2 DEMAND OUT
2.6 2.5 2.8 7.9
1.8 1.7 1.6
5.1 PEAK OUT 4.6 4.3
5.2 14.1 3.8
3.2 3.1 10.1 MWhA MWhB
MWhC MWh3P MVARhA MVARhB MVARhC
MVARh3P IN 0.2
0.2 0.2 0.5 1.0
1.1 1.2
3.3 OUT 28278.4 26797.4
31523.3 86599.1 21038.4 17781.7
17006.4 55826.5
383. Application of Digital Relays on 69KV
Transmission lines
3.8 Provide useful supervision
- PT voltage memory polarization unit secures
reliable operation of relay employed on short
line while a three-phase fault occurs close to
busbar. - b. Directional elements with V2 and V0 voltage
polarization units secure reliability and
selectivity of relay under earth fault condition.
393. Application of Digital Relays on 69KV
Transmission lines
3.8 Provide useful supervision (continued)
- AC under- and over-voltage
- 69kV PT phase-loss supervision
- 69kV line phase-loss supervision
- Over-/under-frequency
- DC over-/under-voltage
- DC source loss
- Circuit breaker operating and wearing status
- Fault location indication
- k. Relay fault alarm.
403. Application of Digital Relays on 69KV
Transmission lines
3.9 other advantages of 351 Digital Relay
- 3.9.1 Two-level access-in password
- First-level available for protection technicians
to routinely inspect and review. - Second-level available for protection
Engineer/senior technicians to program relays and
operate circuit-breakers. - 3.9.2 others
- flexible-to-program
- easy-to-install-and-test
- free-to-maintain
- small-in-size
- sealed in metal box to prevent radio interference
and climate affection - work under temperature range of 40--85C
414. 2030 Communication Relay Software
4.1 2030 Configuration Feature
- A. Configuration
- Being called as Master relay for substation
communication and integration - Seventeen(17) 9-pin communication ports
- Programmable relay
- B. Feature
- Data information collection, storage and
distribution - Remote or local control, metering and monitoring
- Event alarming/ paging
- Time and date synchronization
424. 2030 Communication Relay Software
4.2 Workstation
WORKSTATION REMOTE PC (5040)
2030
MODEM
MODEM
2030
MODEM
PHONE (PAGING)
TELEPHONE BOARD
2030
MODEM
MODEM
LOCAL PC
2030
MODEM
587
351
551
321
DFP-100
Figure 13 communication configuration
434. 2030 Communication Relay Software
4.3 Communication software
- 4.3.1 Human machine interface (HMI)
- Hyper Terminal is a widely used software for
either local or remote relay communication - 4.3.2 5010 Setting assistance software
- The most complex work on 351 relay is
programming due to 512 settings in one of six
groups. -
- This software can
- make relay programming facilitated
- synchronize date and time on relays.
-
-
444. 2030 Communication Relay Software
4.3 Communication software (continued)
-
- 4.3.3 5040 Power system report manager
-
- 5040 software was designed for
establishment of Workstation. - It can
- periodically or automatically retrieve the latest
event reports from designated digital relays - save event reports in database of workstation for
viewing in oscillography.
455. A Captured Event
IAF1911A IAS1407A 0S
IAF552A
INF2054A INS2016A 0S
INF701A
IAF1642A IAS378A 0.5S
13
11
7
8
9
12
10
14
15
IA(1.0) L1.62KM
INF1589A INS450A 0.5S
Y/ Yo
Yo/Y
Yo/Y
Y/ Yo
Cassada
G
G
G
G
G
G
G
Crabbs
Friars Hill
IAF699A IAS675A 0S
INF700A INS531A 0S
3
2
4
5
6
16
1
1
Y/ Yo
Y/ Yo
Y/ Yo
Y/ Yo
Lavington
Swetes
Belmont
Union Road
Figure 14 fault current distribution situation
on May 05,2002
465. A Captured Event( continued)
- CRA-LAV
- DATE TIME EVENT LOCAT CURR
FREQ GRP SHOT TARGETS - 05/05/02 062126.909 AG T 1.62 1911 60.06
1 0 INST 50 - 42 05/05/02 062126.901 67N4
Asserted - 41 05/05/02 062126.905 67N3
Asserted - 40 05/05/02 062126.905 67P3
Asserted - 39 05/05/02 062126.909 67N2
Asserted - 38 05/05/02 062126.909 67P2
Asserted - 37 05/05/02 062126.917 67N1
Asserted - 36 05/05/02 062126.917 67P1
Asserted - 35 05/05/02 062126.917 67N1T
Asserted - 34 05/05/02 062126.917 67P1T
Asserted - 33 05/05/02 062126.917 TRIP
Asserted - 32 05/05/02 062126.917 OUT202
Asserted - 31 05/05/02 062126.917 OUT201
Asserted - 26 05/05/02 062126.963 IN101
Deasserted - 21 05/05/02 062126.972 52A
Deasserted
475. A Captured Event( continued)
- LAV-CRA
- 4 05/05/02 062146.408 AG T 5.71 699
60.07 1 0 INST 50 -
- 40 05/05/02 062146.404 67N3
Asserted - 39 05/05/02 062146.404 67N2
Asserted - 38 05/05/02 062146.404 67P3
Asserted - 37 05/05/02 062146.413 67N1
Asserted - 36 05/05/02 062146.413 67N1T
Asserted - 34 05/05/02 062146.413 TRIP
Asserted - 33 05/05/02 062146.413 OUT201
Asserted - 32 05/05/02 062146.421 67P1
Asserted - 31 05/05/02 062146.421 67P1T
Asserted - 20 05/05/02 062146.454 IN101
Deasserted - 17 05/05/02 062146.463 52A
Deasserted
486. Conclusion
- About two year operating experience shows that
- a. the digital relay protections secure 69kV
transmission lines and 11kV primary feeders
operating under safe, reliable condition - b. the micro-processed directional over-current
protection can be applied to the close-ring
transmission network, especially, to the short
lines connected to small power system. -
-
496. Conclusion
- The established workstation makes daily
inspection of relays and fault analysis easier. - All event reports recorded in related relays can
be immediately downloaded by 5040 software within
few minutes once an event occurs. - In accordance with the event reports listed in
table, the event sequence and cause, conclusion
can be easily obtained to guide system
improvement. -
-
506. Conclusion
-
- 3. Based on application of 2030 communication
relays and 5040 and other related software, the
established workstation performs functions as
mini-SCADA system on protection, monitoring,
metering and control.