Title: EMU CMS Cathode Strip Chambers Production Status at FNAL
1EMU CMS Cathode Strip Chambers Production Status
at FNAL
TASK H/EMU CMS
2Status of FNAL Activity
- Panels Production Status (LAB8)
- CSC Assembly Status(MP9 facility)
- CSC Validation Status(CRTS at LAB7)
- Foreign Factory Setup
- Chamber Integration efforts
3FNAL Activity
LAB7 Cosmic Ray Test Station Validation of first
20 CSCs
PNPI Site
parts and critical tooling (smaller chambers)
smaller CSCsElectronics, tested installation/comm
issioning
UC Site
large CSCs
large CSCsElectronics, tested installation/commis
sioning
Fermilab Site - panel production - large CSC
assembly
CERN
large CSCsElectronics, tested installation/commis
sioning
large CSCs
UF Site
Procurement
parts and critical tooling (smaller chambers)
smaller CSCsElectronics, tested installation/comm
issioning
Wire
Panels
IHEP Site
Guard strips
Gap bars (UF)
Wire fix bars
Frames (FNAL) HV Connector (UF)
Frames/HV Connector (UW)
Etc.
4FNAL Sub-sites
Production Flow
Lab 8 (Panels Production)
Gerber and Axxiom Cutting Strips Position
measurements
5FNAL Factories - Lab 8CSC Panels production
Facility
6LAB8Panels Production Rate
100 (148CSC) of ME23/2 at November 10
135 ME2324/2 Chamber(91) 19/950 Rejected
Panels (2. 0)
7Panels ProductionQC/QA
- Measurements with CMM machine
8Panels ProductionQC/QA
Rotation
X
1st groove
81st groove
For 50 of ME234/2 panels, alignment marks
analysis shows good quality and a process under
control
Y
Scale
81st groove
1st groove
Off-set
9Panels ProductionPhotogrammetry Techniques to
transfer Strips position outside of Chambers
- Cross-check on strips position after chamber
assembly (typically _at_ CERN)
Excellent correlation between CMM and
Photogrammetry Measurements
10Chambers AssemblyMP9 Facility.
Planned Layout - May 99
11Chambers AssemblyMP9 Facility.
Panel Lifting Equip.
MP9 CSC Factory
Winding Machine
Soldering Machine
12Plans Chambers AssemblyMP9 Facility. of CSC
assembly
50 (72) ME234/2 Chambers at CERN
6 months for FAST sites operations Shipments
Total 74 Chambers
- Start Factory Production - Jul 00
- Production Rate
- 2 chambers/month in Q3/CY00
- 1 chamber/week in Q4-CY00
- 1.1 chambers/week in CY01
13Validation of CSCs at FNAL(Cosmic Ray Station at
LAB7)
- Picture of FNALs CRTS - as a full scale
prototype of UF and UCLA FAST sites , historical
role of LAB7 facility (test of first several
prototypes, troubleshooting before CERN
test-beam, etc - Today this is facility for CSC integration
efforts Validation of 20 first production CSCs. - Why we decided to proceed with CSC Validation
works - We have not enough testing experience in EMU CMS
project and for some reasons testing of CSC at
FAST site and
14Preparation for ProductionIntegration
CSC Integration efforts
- Integration (UWFNAL efforts)
- Infrastructure
- Mechanical Support
- Cooling
- Cabling
- HV connectors
- Water fittings
- Electronics
- CFEBs
- ALCT
- Low Voltage Distribution
- Alignment
15(No Transcript)
16Foreign Factory Setup
- Setting up a Factory implies placing many
activities/items under control - 10 Chamber kits shipped to Russia/China by
Jan.-Feb. 01 - Tooling
- Assembly, Commissioning Shipment
- Operating Procedures
- Parts Control
- Parts Inspection Shipment
- Parts Accounting
- Parts Storage and Flow to the Production Floor
- Chamber Assembly Activities
- Assembly Procedures Personnel Training
- Definition/tooling for QA/QC Activities
- Discrepancy Report Scenarios
- Travelers and Measurements Data-basing
- Underlined Fermilab Responsibilities