Title: EMU CMS Cathode Strip Chambers Production Status at FNAL


1
EMU CMS Cathode Strip Chambers Production Status
at FNAL
TASK H/EMU CMS
  • Yuriy Pischalnikov
  • UCLA

2
Status of FNAL Activity
  • Panels Production Status (LAB8)
  • CSC Assembly Status(MP9 facility)
  • CSC Validation Status(CRTS at LAB7)
  • Foreign Factory Setup
  • Chamber Integration efforts

3
FNAL Activity
LAB7 Cosmic Ray Test Station Validation of first
20 CSCs
PNPI Site
parts and critical tooling (smaller chambers)
smaller CSCsElectronics, tested installation/comm
issioning
UC Site
large CSCs
large CSCsElectronics, tested installation/commis
sioning
Fermilab Site - panel production - large CSC
assembly
CERN
large CSCsElectronics, tested installation/commis
sioning
large CSCs
UF Site
Procurement
parts and critical tooling (smaller chambers)
smaller CSCsElectronics, tested installation/comm
issioning
Wire
Panels
IHEP Site
Guard strips
Gap bars (UF)
Wire fix bars
Frames (FNAL) HV Connector (UF)
Frames/HV Connector (UW)
Etc.
4
FNAL Sub-sites
Production Flow

Lab 8 (Panels Production)

Gerber and Axxiom Cutting Strips Position
measurements









5
FNAL Factories - Lab 8CSC Panels production
Facility
  • Picture of LAB8

6
LAB8Panels Production Rate
100 (148CSC) of ME23/2 at November 10
135 ME2324/2 Chamber(91) 19/950 Rejected
Panels (2. 0)
7
Panels ProductionQC/QA
  • Measurements with CMM machine

8
Panels ProductionQC/QA
Rotation
X
1st groove
81st groove
For 50 of ME234/2 panels, alignment marks
analysis shows good quality and a process under
control
Y
Scale
81st groove
1st groove
Off-set
9
Panels ProductionPhotogrammetry Techniques to
transfer Strips position outside of Chambers
  • Cross-check on strips position after chamber
    assembly (typically _at_ CERN)

Excellent correlation between CMM and
Photogrammetry Measurements
10
Chambers AssemblyMP9 Facility.
Planned Layout - May 99
11
Chambers AssemblyMP9 Facility.
Panel Lifting Equip.
MP9 CSC Factory
Winding Machine
Soldering Machine
12
Plans Chambers AssemblyMP9 Facility. of CSC
assembly
50 (72) ME234/2 Chambers at CERN
6 months for FAST sites operations Shipments
Total 74 Chambers
  • Start Factory Production - Jul 00
  • Production Rate
  • 2 chambers/month in Q3/CY00
  • 1 chamber/week in Q4-CY00
  • 1.1 chambers/week in CY01

13
Validation of CSCs at FNAL(Cosmic Ray Station at
LAB7)
  • Picture of FNALs CRTS - as a full scale
    prototype of UF and UCLA FAST sites , historical
    role of LAB7 facility (test of first several
    prototypes, troubleshooting before CERN
    test-beam, etc
  • Today this is facility for CSC integration
    efforts Validation of 20 first production CSCs.
  • Why we decided to proceed with CSC Validation
    works
  • We have not enough testing experience in EMU CMS
    project and for some reasons testing of CSC at
    FAST site and

14
Preparation for ProductionIntegration
CSC Integration efforts
  • Integration (UWFNAL efforts)
  • Infrastructure
  • Mechanical Support
  • Cooling
  • Cabling
  • HV connectors
  • Water fittings
  • Electronics
  • CFEBs
  • ALCT
  • Low Voltage Distribution
  • Alignment

15
(No Transcript)
16
Foreign Factory Setup
  • Setting up a Factory implies placing many
    activities/items under control
  • 10 Chamber kits shipped to Russia/China by
    Jan.-Feb. 01
  • Tooling
  • Assembly, Commissioning Shipment
  • Operating Procedures
  • Parts Control
  • Parts Inspection Shipment
  • Parts Accounting
  • Parts Storage and Flow to the Production Floor
  • Chamber Assembly Activities
  • Assembly Procedures Personnel Training
  • Definition/tooling for QA/QC Activities
  • Discrepancy Report Scenarios
  • Travelers and Measurements Data-basing
  • Underlined Fermilab Responsibilities