Title: Henderson DUSEL Conceptual Design Mark Kuchta Minin
1Henderson DUSEL Conceptual Design
- Mark Kuchta
- Mining Engineering Department
- Colorado School of Mines
- Lee Petersen, CNA Consulting Engineers
- Greg Hulne, Miller Dunwiddie Architects
- Dale Holland, Dunham Associates
- John Jenkins, ILF
- Craig Covil, ARUP
2Engineering Design Team
Colorado School of Mines Mark Kuchta,
Scott Kieffer, (Mining Engineering, Geotechnical
Engineering) Henderson Mine
Chip deWolfe, Staff (Mining Engineering,
Safety) CNA Consulting Engineers Lee
Petersen (Engineering Team Leader, Civil
Engineering) Dunham Associates
Dale Holland (Mechanical/Electrical
Engineering) Miller Dunwiddie Architecture Greg
Hulne (Architect) ILF Consultants
John Jenkins (Internal Shaft Design) ARUP (Cost
review, construction management plan)
3Conceptual Design Overview
- Shared Mine Infrastructure
- Mine Services Summary
- Rock Conditions
- DUSEL Access Ramps
- Campus Layouts (Upper, Central, Lower, Outposts)
- Development Sequence
- System Design
- Fire and Life Safety Concepts and Code Review
- Surface Facilities
4Shared Mine Infrastructure
- Overriding design criteria
- Safety
- Share infrastructure that is of benefit to share
- Keep the DUSEL and mine operations as separate as
possible
5Site Overview
6Shared Mine Infrastructure
- Ventilation
- 150,000 cfm available for DUSEL
- Electricity
- 14 MW with 14MW backup available for DUSEL.
- Mine Dewatering
- About 3000 gpm pumping capacity available for
DUSEL - DUSEL estimated need 500 gpm
- URAD Water Treatment
- About 2000 gpm in excess capacity available for
DUSEL
7Shaft Schedule Man Cage
- Double Deck Man Cage
- Capacity 100 people
- Overall availability about 93.5
- Normally available 24/7
- Service Cage
- Capacity 100 People
- 30 Ton capacity
- Sling 50 tons with crosshead
- Cage 23 ft. long X 8.5 ft
- Wide X 13 ft high
- Can move DUSEL supplies at 1140 tons/week to 7500
tons/week depending on shift schedule used. - (SNOLab 336 tons/week)
8Rock Handling System
80 ton trucks dump rock at crusher. Gyratory
crusher reduces to 4 in. 1 mile PC1 and 10.5
mile long PC2 underground conveyors. 4 mile long
PC3 surface conveyor to mill site.
- 40,000 tons per day capacity
- Mine currently producing about 30,000 tons per
day - Maximum planned DUSEL production 3,000 tons per
day - DUSEL rock will be dumped at the crusher on the
7065 level, - A fee (/ton) will be charged for rock removal
9Henderson DUSEL Layout
10RQD DUSEL Exploration Hole 001
Section
Average RQD 92 (Very Good) Three lt 10 ft
fracture zones
Plan
11Henderson DUSEL Central Campus Access
12Access Ramps
13Ramps
14Internal Shaft (winze) Top at Central Campus
- 20 ft diameter
- Concrete lined
- Capacity 5 ton
- Capacity 20 people
- Sink top down
- Keep sinking bucket for hoisting Lower Campus
excavation rock
15Shaft Cross Section
16Access Ramp Cross Sections
Muck Haulage
Shipping Container
17Upper Campus Layout
18Upper Campus Layout
19Central Lower Campus Isometric
20Central Lower Campus Building Blocks
21Central Campus Layout
22Central Campus Layout w/ Large Multi-Purpose
Detector
23Lower Campus
24Infrastructure Design Life Criteria
- Suggested initial design life (capacity only)
- Lab life50? years
- Drift cross sectionsized for full expansion
- Duct size20 years
- Power conductors20 years
- Power transformers10 years
- Chiller piping20 years
- Chiller plant10 years
- Communications10 years
25Lab vs. Infrastructure Development Plan
26Development Sequence
27Fire Life Safety Concept
28Lower Campus FLS Provisions
29Lower Campus FLS Provisions
30Fire Life Safety Next Steps
- Meeting with MSHA and OSHA Regional offices on
March 30, 2006 - Meeting with Clear Creek County building code
officials on March 31, 2006 - ObjectiveMOU defining jurisdictions, codes, etc.
31Henderson DUSEL System Design
- Ventilation System
- Electrical System
- Incl. redundant, backup and emergency systems
- Fire and Life Safety
- Compartmentalization
- Monitoring alarm
- Fire suppression
- Fire separations
- Egress routes exit indicators
- Security stations
- Refuge Chambers
- Evacuation Routes
- Water Wastewater Systems
- Data Systems
- Personnel control
- Control room w/ CCTV
- Cameras
- Personnel monitors
- Paging system
- Emergency rescue systems
- Ambulance fire truck
- Emergency cabinets
- Blast doors
32System Conceptual Design
- Basic services
- Provided to occupied Upper, Central and Lower
campus areas - Power, air, potable water, fiber communications,
lighting, emergency safety systems and selected
drainage - Ventilation systems
- Provided to Upper, Central Lower Campuses
- Basic normal and emergency ventilation
- Distribution systems
- Central services
- Terminate at the experiment caverns for tenant
connections - Fresh air, chilled water, power, process piping,
communications, and safety systems
33Ventilation Cooling Design Criteria
- Virgin rock surface temperatures
- 90F at upper campus
- 107F at central campus
- 142F at lower campus
- Projection of bore hole temperature readings
- Heat transfer coefficient
- 0.098 Btu / hr-ft2 -F after 720 days
- Based upon published data
- Mine ventilation air
- Supplied to the central campus at 78F
34Ventilation Systems
- Access egress tunnel ventilation
- Normal Upper, Central Lower campus ventilation
- Interconnecting drifts ventilated using mine air
(no A.C.) - Caverns have conditioned air (chilled water
coils, electric heating coils to control
humidity, filtration) - Clean space ventilation system
- Safety ventilation systems
- Compartmentalization smoke ventilation
- Smothering gas ventilation
- Central exhaust system
- Special exhaust system
- Special process exhaust, toilets, flammable
liquid, etc. - 10,000 cfm each at Central Lower Campus
35Cooling
- Each campus will have a chilled water loop
- Estimated Immediate Cooling Load
- Upper Campus 25 Tons
- Central Campus 85 Tons
- Lower Campus 175 Tons
- Estimated Future Cooling Load
- Upper Campus 90 Tons
- Central Campus 395 Tons
- Lower Campus 430 Tons
36Plumbing
- Water systems
- Potable via bottles
- Non potable from mine system, stored in tanks
- Sanitary waste
- Lift station to a holding tank, periodic transfer
to surface - Gray water
- 500 gpm total flow
- Sumps at Central, Midway and Lower Campus
- Pumped into the Henderson mine water system
37Process Utilities Fire Protection System
- Process utilities
- Central nitrogen gas system
- Compressed gas system
- Clean dry compressed air
- Cryogen relief
- De-ionized water system
- Fire protection system
- Each campus will have a wet pipe sprinkler system
- Drift standpipe systems
- Fire protection water storage tanks
38Lighting
- Normal lighting
- Caverns 30 foot-candles (either metal halide or
fluorescent depending upon height) - Office, lunch, shops at 50 fc
- Miscellaneous at 20 fc
- Egress routes at 1 fc
- Emergency lighting
39Power
- New feed from the surface at 13,800 V
- Unit substations at each campus
- 277/480V for lighting power to mechanical
systems - 120/208V for receptacles
- Demand
- All campuses, immediate 2975 kVA
- All campuses, future increment 3990 kVA
- All campuses, total 6965 kVA
40Emergency Systems
- Emergency power
- Fire alarm system
- Surveillance cameras
- Access control
- Security
- Duress alarm
- Asset locator
- Personnel emergency device tracking
41Communications
- Backbone cabling
- Single-mode fiber
- 10-gigabit Ethernet
- 192 strands of fiber from surface and to each
campus - Campus cabling
- Category 6 unshielded twisted pair
42Site Placement
- Visitor Center Interface with Public
- Parking Relationship to Office
- Offices, Laboratories, Warehouse and Shops
Achieve a campus grouping of buildings - Dormitory Cafeteria - Location to be
determined, near campus - Future Expansion - Post Mine closure
43Surface Buildings
- Surface Building Program
- Visitors Center total 50,000 sf to yr 15 30,000
sf - Admin/Offices/Laboratories total 85,000 sf to yr
15 65,000 sf - Dormitory Cafeteria total 35,000 sf to yr 15
35,000 sf - Assembly, Shops Storage total 25,000 sf to yr
15 25,000 sf - Existing Facilities (available after about 2026)
- Office Building 87,759 sf
- Surface Shop 26,000 sf
- Shaft Hoist House 9,600 sf
- Surface Warehouse 14,000 sf
- Building reuse issues
- DUSEL program needs phased buildout
- Existing building locations
44 Surface Building Phased Buildout Budget
in thousands, 2006
Between year 15 year 20, existing Henderson
Mine buildings become available for DUSEL
re-development