Title: Hythro Power Corporation Limited.
1Hythro Power Corporation Limited.
2Hythro Inception Background
- Hythro was established in the year 1989.
- Part of Tecpro Group, a leading EPC business
house providing comprehensive range of services
in power, steel, mining, cement other
industries in Infrastructure sector balance of
Plants for Power Sector. Tecpro Systems Limited,
a flagship company of Tecpro Group, which is
listed on Indian Stock Exchanges with a market
capitalisation of approximately US 200 Million.
The group turn over including listed other
entities is approximately US 800 Million. - One of the prominent EPC (Engineering,
Procurement Construction) player in all the
power sector segments i.e. from Power Generation
to Power Transmission to Power Distribution. - Undertaking large EPC contracts for many projects
from various prestigious organizations. And its
manufacturing facility of towers has played an
important role for its stupendous success in
Power Transmission segment. - With the in-house engineering/technical
competency organic/inorganic growth strategy
the company is all set to emerge out as the key
player in the Global Power industry.
3Vision Mission
- Our aspiration to grow our focus on
customers/ timely delivery focus on
quality/safety has been our guidelines in doing
our business. Our Vision Mission statements
capture them all
Vision To become one of the leading company in
the field of Turnkey projects up to 800 KV EHV
Transmission Lines and Sub-Stations in National
and International markets
Mission To be most preferred supplier by adding
value to the customers project focusing on
Quality, Cost, Innovation and Productivity with
due regard to occupational health, safety and
environment
4 Business From Power Generation to Load
Centers
GENERATION GENERATION
E-BOP NON-CONVENTIONAL/RENEWABLE ENERGY
Electrical Balance of Plant for Power Plants Creating Power Evacuation System for Renewable Energy Supply
TRANSMISSION DISTRIBUTION TRANSMISSION DISTRIBUTION TRANSMISSION DISTRIBUTION TRANSMISSION DISTRIBUTION TRANSMISSION DISTRIBUTION
TOWER PARTS MANUFACTURING EHV TRANSMISSION LINES EHV SUBSTATIONS MV, LV Distribution Lines RAILWAYS
State of art manufacturing plant situated at Bhiwadi, Rajasthan having capacity of 30000 MT /annum Turnkey projects upto 765 kV Class Turnkey projects upto 400 kV class Rural Electrification, RGGVY, APDRP, Feeder Separation Projects, Etc. Traction-overhead systems, switching stations, traction substations, etc.
LOAD CENTERS
INDUSTRIAL /COMMERCIAL ELECTRIFICATION
Creating electrical infrastructure for the manufacturing/commercial entities.
5Quality Management System With Health, Safety
Environment Policy
- We, as Hythro Power Corporation Ltd., lay high
emphasis on the quality management to ensure the
quality in every respect. We have been accredited
with ISO-9001-2008 certification. - Also we do take care of all the necessary safety
measurements established our HSE policy for the
same. We have been accredited with ISO-14001-2004
BS OHSAS 18001-2007 for our endeavors in this
regard.
6Design Capability
Project Type Design Capability
Substations Electrical Bus Configuration, Metering Relaying Diagram, Layout Design, Selection Of Relays , Ct / Pt Calculation, Vendor Drawing Review, Battery Charger Sizing, AC / DC Schematic Engineering, Fault Level Analysis, Relay Setting Calculation, Substation Automation Communication Engineering Civil Structurals Structural Steel, RCC Design, Foundation Design Analysis, RCC Building Design, Detailing Of RCC and Structural Steel Fire Fighting System PI Diagram, Fire Alarm MCC Fire System, Hydrant System CO2 System HVAC Heat Load Calculation, Selection Of Air-Conditioning Distribution System, Selection Of Fire Alarm Panel Control System
E-BOP Metering, Relaying Control System For Generator, Generator Transformer, Excitation Unit Auxiliary Transformer. Detailed Engineering Include Cable Sizing, Cable Routing Control Schematics ForCoal Handling System, Ash Handling System, Water Treatment Plant, Electrostatic Precipitator, Selection Of PCC MCC For Plant Electrics, Power Plant Earthing Design, Lighting Lightning Design, Fault Level Analysis, Relay Coordination/Recommendation And Instrumentation Engineering
Transmission Lines Tower Spotting, Sag Tension Calculation, Sag Template, Clearance Diagram, Stringing Chart, Structural Analysis Design Of Tower And Foundation Analysis Design
7Project Management
- The key to success in EPC projects is the ability
to manage the resources to provide quality and
delivery, meeting clients requirement. This
aspect of project management can be achieved only
by experience. - Our company has in its roles- successful and
cohesive team to manage projects from Survey to
commissioning with experienced professionals with
decades of experience behind them in executing
contracts of varied nature and sizes. - The combined experience of our executives in
Turnkey Projects shall ensure that our client
gets best in Technology and Quality at
competitive cost. - The project management team uses latest software
and an internally developed project reporting
system to provide the clients with progress and
plan for project execution and management.
8Manufacturing Plant
9Consolidated Financial Capability- Hythro Power
Its Subsidiaries
Considering 1 USD 50 INR Including
proportionate Finance of subsidiaries
10Our Accomplishments
- Executed several E-BOP projects ranging from 28
MW to 2 x 600 MW on turnkey / partial turnkey
basis. - Laid more than 10,000 ckt. kms of transmission
distribution lines. Have expertise to lay the
lines through difficult terrains (e.g. hilly
regions, deserts, river crossings, snow capped
regions, cultivated land, urban areas etc.) and
already executed such projects for our
prestigious clients including government
organisations private parties. - Constructed over 500 substations / switchyard
projects from 33kV to 400kV level in different
parts of the country under different
environmental conditions for the prestigious
clients including government organisations
private parties. - Continuous growth of the Hythro Group from USD
12.9 Million in FY 2006-07 to USD 167 Million in
FY 2010-11.
( Accomplishments by Hythro Power its
subsidiaries)
11Contact Details
CONTACT ADDRESSES CONTACT ADDRESSES CONTACT ADDRESSES
Head Office TECPRO HOUSE, Plot 78, Sector 34,NH-8, Gurgaon-122001 Ph 91 124 4880100/200/300/400 Fax 91 124 4880354 Email hpcl_at_hythropower.com
Bangalore No 1316/C, 2nd Floor, 80 Ft Road, 9th Cross, JP Nagar 2nd Phase, Bangalore- 560078 Ph 91 80 26588846/ 47 Fax 91 80 26588843 Email hpcl_at_hythropower.com
Kolkata Godrej Waterside, Tower-I, 11th Floor,Flat Nos. 1101 1102, Plot - 5, Block DP, Sector - V, Salt Lake City, Kolkata - 700 091 Phone 91 33 40261717 Fax 91 33 4026 1700 /1701 Email hpcl_at_hythropower.com
Mumbai 502-503, Building No. A-2, Jagdamba Commercial Complex, (Movie Time Complex) Link Road, Malad (West) Mumbai 400 064 Ph 91 22 4003 1257/ 42388500 Fax 91 22 4003 1256 Email hpcl_at_hythropower.com
Chennai G.E.T. Power Ltd. No.153, Developed Plots, Electrical Electronics Industrial Estate, Perungudi, Chennai - 600 096 Ph- 91-44-45991001/2/3 Fax 91-44-45991000 Email hpcl_at_hythropower.com
12Project Glimpse
Transmission Lines
S.No. Client Project Details
400kV Class Above 400kV Class Above 400kV Class Above
1 Shree Cement D/S/E/T/C of D/C line at Beawar ( Rajasthan)
2 Adani Power E/T/C of D/C Mundra-Zerda Transmission line of GETCO
3 PGCIL E/T/C of LILO D/C S/C Singrauli Kanpur Line
4 Aster E/T/C of D/C Mundra - Varsana Transmission line of GETCO
5 Areva D/C S/C line associated with NTPC Sipat
6 Sravanthi Infratech D/S of Quad Moose TL for 220MW Gas based Power Project
7 KWPCL (Avantha Power) D/S/E/T/C of TL for 2x600 MW KWPCL Raigarh Project, Chhattisgarh
8 Jyoti Structure S/E/T/C of TL at WRSS-Maharashtra of RETL.
13Project Glimpse
Transmission Lines
S.No. Client Project Details
220 kV Class 220 kV Class 220 kV Class
1 UPPTCL S/E/T/C of D/C Parichha- Mainpuri Line
2 RSEB E/T/C of S/C Bhilwara to Kankroli Line
3 UPPTCL S/E/T/C of D/C Transmission Line
4 PTCUL S/E/T/C of Rishikesh - Dharasu (I) chamba - Dharasu Transmission Line
5 HPPTCL D/S/E/T/C of S/C TL from 220KV Palchan S/S to 220KV A.D. Hydro Switchyard
6 Jaiprakash Associates S/E/T/C of D/C over line from Kunihar 220KV substation to JHCP Baga.
7 PTCUL S/E/T/C of D/C line of Single Zebra (Rudrapur-Srinagar via Ghansali)
8 RSEB Ratangarh -Sikar -Rengus
9 KPTCL D/S/E/T/C of Bastipura-Kushalnagara D/C T/L.
10 KPTCL D/S/E/T/C of Shimoga-Huygonahalli LILO T/L.
14Project Glimpse
Substation
S.No. Client Project Details
400kV Class 400kV Class 400kV Class
1 PGCIL D,S,E,T,C for bay extension works at 400kV Fatehabad S/S.
2 PGCIL D,S,E,T,C for bay extension works at 400kV Sonepat S/S -I, II and125 MVAR Bus Reactor Bay .
3 PGCIL D,S,E,T,C for bay extension works at 400kV Hosur S/S.
4 PGCIL D,S,E,T,C for bay extension works at 400kV Madurai S/S for 63 MVar Karaikudi line reactor.
5 PGCIL D,S,E,T,C for bay extension works at 400kV Trichy S/S.
6 PGCIL D,S,E,T,C for bay extension works at 400kV Udumalpeth S/S.
7 PGCIL (Thru BHEL) E,T,C of 400/220 kV Thiruvananthapuram S/S.
8 PGCIL (Thru BHEL) E,T,C of 400 kV Madurai S/S (extension bays).
9 TNEB (Thru BHEL) E,T,C of 400/30/110 kV Alamathy switchyard.
10 PGCIL (Thru ABB) E,T,C of 400/220 kV Hiriyur S/S.
11 KPTCL( Thru BHEL) E,T,C of 400 kV Guttur switchyard (extension bays)
12 IRCON International E,T,C of 400 kV Mapusa S/S
13 PGCIL(Thru Alstom) E,T,C of 400 kV Upper Indravati S/S.
14 NLC (Thru TATA Projects) E,T,C of 400/220/33 kV Neyveli S/S.
15 UPCL (Thru Alstom) E,T,C of 400/220 kV Muzzafarnagar switchyard.
15Project Glimpse
Substation
S.No. Client Project Details
220 KV Class 220 KV Class 220 KV Class
1 KPTCL (Thru Alstom) S,E,T,C of 220/110/66kV MRS Shimoga switchyard.
2 KPTCL D,S,E,T,C of 220/66/11 kV Huygonahalli substation.
3 KPTCL D,S,E,T,C of 220/66 kV 66/11 kV Naganathapura S/S.
4 KPTCL D,S,E,T,C of establishing 220/66 kV Kushalnagar substation.
5 Delhi TRANSCO Ltd. (Thru BHEL) E,T,C for 230/33 kV switchyard.
6 NLC (Thru LT) E,T,C of 220/11 kV Neyvelli switchtyard.
7 GRIDCO, Orissa (Thru TATA Projects) E,T,C for 220/33 kV Barkote Rairak switchyard.
8 Tanir Bavi Power Company(Thru ABB) E,T,C of 220 kV Mangalore S/S.
9 BGR Energy E/T/C of 230/11kV GIS Substation at Hyundai Motors India Ltd.
10 BSES Limited E/T/C of 220/11 KV , 2x40 MVA , 2 bay switchyard
16Our Accomplishments
Mr. Amul Gabrani, Chairman Managing
Director(L) and Mr. Ajay Kumar Bishnoi,
Director(R) receiving the SME of the Year
Most Promising SME in Power Telecom Sector
CRISIL powered CNBC-TV18-ICICI Bank Emerging
India Awards 2012,on behalf of Hythro Power
Corporation Ltd.
17Installations
18Installations
19Installations
20Installations
21Working Experience In Snow
22(No Transcript)
23(No Transcript)
24(No Transcript)
25